Delhi, the 17th January, 2024
Draft Rehabilitation and Resettlement Scheme
F. No. ADM/LAC/SE/2023/05/kh.No.221/Part-II/984.—In the exercise of the powers conferred by
sub section (2) of section 16 of the Right to Fair Compensation and Transparency in Land Acquisition Act, 2013, the
draft Rehabilitation and Resettlement Scheme has been prepared under section 16 of the Right to Fair Compensation
and Transparency in Land Acquisition Act, 2013, for families affected with the proposed acquisition of land bearing
Khasra No. 221/2/1 (459.192 Sqm.) & 221/2/3 (709.901 Sqm.) total land measuring (1169.093Sqm.) of Village
Nangli Razapur for infrastructure Project for Construction of 3rdPhase of Elevated Road on Barapulla Nallah from
Sarai Kale Khan to Mayur Vihar, New Delhi the same is being published under rule 7 (5) of the Right to Fair
Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (Compensation Rehabilitation
and Resettlement and Development Plan) Rules 2015,
Preface: -
Vide Preliminary Notification No. F. No .ADM/LAC/SE/2023/05/860 dated 21.12.2023 issued by District
Magistrate (South-East), Govt. of NCT, the land bearing Khasra No. 221/2/1 (459.192 Sqm.) & 221/2/3 (709.901
Sqm.) total land measuring (1169.093 Sqm.) of Revenue Estate of Village Nangli Razapur was notified for acquisition
u/s 11 (1) of Right to Fair Compensation and Transparency in Land Acquisition Act, 2013 for infrastructure project
for Construction of 3rdPhase of Elevated Road on Barapulla Nallah from Sarai Kale Khan to Mayur Vihar, New Delhi.
Vide above notification, Additional District Magistrate (South East) was appointed as the Administrator
under sub section (1) of Section 43 of the said Act for Rehabilitation & Resettlement of affected families due to
acquisition of the said land as mentioned above.
As per section 16 of the Right to Fair Compensation and Transparency in Land Acquisition Rehabilitation &
Resettlement Act, 2013, Draft Rehabilitation & Resettlement Scheme is to be prepared by the Administrator.
Upon the publication of the preliminary notification under sub-section 1 of section 11 by the Collector, South
East, a survey u/s 16(1) was carried out on 10/01/2024 regarding census of the affected families, particular of land and
immovable properties, structures, trees, infrastructure facilities and utilities etc. of land bearing Khasra no. 221/2/1 &
221/2/3.
(a) Particulars of lands and Immovable properties being acquired of each affected family: -
List of land holding in the affected area:-
Total land being acquired Kh. 221/2/1 (459.192 Sqm.) & 221/2/3 (709.901 Sqm.) total land measuring
(1169.093 Sqm.), Nature of land:-Yamuna.
+--------+------------+---------------------------+---------------+--------------------------------------------------------------+----------------------------------------------+
| Sl. No.| Khasra No. | Area under | Type of Title | Name of recorded owners | Name of Persons in cultivation |
| | | acquisition | | | |
| | | (in hectares) | | | |
+========+============+===========================+===============+==============================================================+==============================================+
| 1. | 221/2/1 | 0.0459192 | Shamlat Taraf | Thok Hira Singh & Thok Rambaksh as per | Thok Hira Singh & Thok Rambaksh as per |
| | | (459.192 Sqm) | | their respective shares and Gram Sabha | their respective shares |
| | | | | through DDA. | |
+--------+------------+---------------------------+---------------+--------------------------------------------------------------+----------------------------------------------+
| 2. | 221/2/3 | 0.0709901 | Shamlat Taraf | Thok Hira Singh &Thok Rambaksh as per | Thok Hira Singh & Thok Rambaksh as per |
| | | (709.901 Sqm) | | their respective shares and Gram Sabha | their respective shares |
| | | | | through DDA | |
+--------+------------+---------------------------+---------------+--------------------------------------------------------------+----------------------------------------------+
Trees:
+------------+----------+--------+
| Khasra No. | Variety | Number |
+============+==========+========+
| 221/2/1 | Bakayan | 05 |
| | Neem | 01 |
+------------+----------+--------+
| 221/2/3 | Teek | 05 |
| | Shehtoot | 02 |
| | Neem | 04 |
| | Bakayan | 09 |
| | Peepal | 03 |
| | Shehtoot | 04 |
| | Sheesham | 01 |
+------------+----------+--------+
| Total | | 34 |
+------------+----------+--------+
Other immovable properties or assets:-Nil
(b) Livelihoods lost in respect of land losers and landless whose livelihood are primarily dependent on the
lands being acquired: -
The villagers had stated that only the villagers, who are holding and cultivating the land as per their shares,
are the affected families and there is no landless person. Only the livelihood of the villagers and their
families/dependents are affected by the proposed land acquisition.
Accordingly, it is evident that the recorded owners have other land in the village and their families are not
primarily dependent on this land for their livelihood and they have other sources of income.
List of trade or businesses in the affected area:
Not applicable.
List of persons belonging to SC/ST Handicapped or physically challenged persons in the affected
area:NIL
(c) A list of public utilities and Govt. building which are affected or likely to be affected where
resettlement of affected families is involved: -Nil
No living quarters/human settlements are getting affected and the acquisition does not affect any amenities
and infrastructural facilities as it does not exist in the vicinity.
This may be treated as Not Applicable.
(d) Details of the amenities and infrastructural facilities which are affected or likely to be affected, where
resettlement of affected families is involved: -
The acquisition does not affect any amenities and infrastructural facilities as none exist.This may be treated
as Not Applicable.
(e) Details of any common property resource being acquired: -
No common property. This may be treated as Not Applicable.
DRAFT REHABILITATION & RESETTLEMENT SCHEME:
As per chapter VI, Procedure and manner of Rehabilitation & Resettlement, section 43 of Right to Fair
Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 the undersigned has
been appointed as the administrator for drafting Rehabilitation & Resettlement Scheme. This draft Rehabilitation &
Resettlement Scheme (RR Scheme) is being drafted in consonance with Section 16,31,41, 42 (if applicable), 43.
Second schedule of RFCTLARR Act, 2013 and Rule 7,9 (if applicable), 16, Form IV (if applicable) and Form VII of
RFCTLARR (Compensation, Rehabilitation and Resettlement and Development Plan) Rules, 2015.
The Draft Rehabilitation and Resettlement Scheme is prepared based on the Second Schedule (Elements of
Rehabilitation and Resettlement Entitlements for all the affected (Both land owners and families whose livelihood is
primarily dependent on land acquired) in addition to those provided in the First Schedule). The Rehabilitation and
Resettlement Scheme is drafted and summarized in the format (enclosed) and recommended for review by Land
Acquisition Collector under section 17 of the Right to Fair Compensation and Transparency in Land Acquisition,
Rehabilitation and Resettlement Act, 2013.
SUMMARY FOR REHABILITATION & RESETTLEMENTSCHEME
1. Name of Project
3rd Phase of the Project, for Construction of Elevated Road over the BarapullahNallah starting from Sarai
Kale Khan to Mayur Vihar, New Delhi
2. Name/Number of persons interested in the land and the nature of their respective
As mentioned at Serial No.4
3.Time limit for provision of Rehabilitation and Resettlement Entitlement given to the affected families
Within 06 months from the date of award u/s 38 of RFCTLARR Act, 2013
4.
+--------+-------------------------------+------------+------------+---------------------------------------------+----------------------------------------------------------------------+
| S. No. | Name of Claimant/ | Aadhar No. | Occupation | Rehabilitation and | Remarks |
| | Affected Family | | | Resettlement Entitlement | |
+========+===============================+============+============+=============================================+======================================================================+
| 1. | NIL | NA | NA | (i) Provision of | (i) NA, as there is no displacement of |
| | | | | housing unit in case | affected family. |
| | | | | of displacement. | |
| | | | | | (ii) NA, it is not an irrigation project. |
| | | | | (ii) Land to be | |
| | | | | allotted. | (iii) NA, as land is not being acquired |
| | | | | | for urbanization purpose. |
| | | | | (iii) Offer of | |
| | | | | Developed Land | (iv) NA, as there is neither displacement |
| | | | | | of affected family nor loss of livelihood |
| | | | | (iv) Annunity/ | (families having alternate source of |
| | | | | Employment | income). |
| | | | | | |
| | | | | (v) Subsistence grant | (v) NA, as there is no displacement of |
| | | | | for displaced family | affected family. |
| | | | | for period of one | |
| | | | | year. | (vi) Na, as there is no displacement of |
| | | | | | affected family. |
| | | | | (vi) ransportation | |
| | | | | cost for displaced | (vii) NA, no cattle shed or shop found |
| | | | | family. | on the land. |
| | | | | | |
| | | | | (vii) Cattle shed, | (viii) NA, as land being acquire is not a |
| | | | | petty shop. | non-agriculture land /commercial |
| | | | | | /industrial structure in the affected area. |
| | | | | (viii) One time grant | |
| | | | | to artisan small | (ix) NA, it is not an irrigation/hydel |
| | | | | traders and certain | project. |
| | | | | others. | |
| | | | | | (x) NA |
| | | | | (ix) Fishing rights. | |
| | | | | | (xi) To be borne by the requisition |
| | | | | (x) Onetime | department/body (PWD). |
| | | | | resettlement | |
| | | | | allowances. | |
| | | | | | |
| | | | | (xi) Stamp duty and | |
| | | | | registration fee. | |
+--------+-------------------------------+------------+------------+---------------------------------------------+----------------------------------------------------------------------+
SHAILENDRA KUMAR SINGH, Administator (Rehabilitation & Resettlement)
Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064
and Published by the Controller of Publications, Delhi-110054.
Digitally signed by
MANOJ KUMAR MANOJ KUMAR VERMA
VERMA
Date: 2024.01.18
Login to read full text