Notification amending the Electricity (Transmission System Planning, Development and Recovery of Inter-State Transmission Charges) Rules, 2021.

Detailed Summary

The Ministry of Power, through Notification G.S.R. 414(E) dated 23rd June, 2025, has introduced the Electricity (Transmission System Planning, Development and Recovery of Inter-State Transmission Charges) Amendment Rules, 2025. These rules, made in exercise of powers conferred by sub-section (1) and clause (z) of sub-section (2) of section 176 of the Electricity Act, 2003 (36 of 2003), amend the principal Electricity (Transmission System Planning, Development and Recovery of Inter-State Transmission Charges) Rules, 2021, which were originally published vide G.S.R. 711(E) dated 1st October, 2021. The amendment involves inserting a new proviso after the first proviso in rule 3, sub-rule (5) of the 2021 Rules. This new proviso states that the Central Government may delegate powers to the National Committee on Transmission and Central Transmission Utility for approving Inter-State Transmission System projects, subject to cost limits specified by the Central Government from time to time. The Amendment Rules, 2025, shall come into force on the date of their publication in the Official Gazette. The notification was signed by SRIKANT NAGULAPALLI, Addl. Secy.

Full Text

REGD. No. D. L.-33004/99 The Gazette of India CG-DL-E-27062025-264200 EXTRAORDINARY PART II-Section 3-Sub-section (i) PUBLISHED BY AUTHORITY No. 371] NEW DELHI, THURSDAY, JUNE 26, 2025/ASHADHA 5, 1947 MINISTRY OF POWER NOTIFICATION New Delhi, the 23rd June, 2025 G.S.R. 414(E). — In exercise of the powers conferred by sub-section (1) and clause (z) of sub-section (2) of section 176 of the Electricity Act, 2003 (36 of 2003), the Central Government hereby makes the following rules to amend the Electricity (Transmission System Planning, Development and Recovery of Inter-State Transmission Charges) Rules, 2021, namely:- 1. (1) These rules may be called the Electricity (Transmission System Planning, Development and Recovery of Inter-State Transmission Charges) Amendment Rules, 2025. (2) They shall come into force on the date of their publication in the Official Gazette. 2. In the Electricity (Transmission System Planning, Development and Recovery of Inter-State Transmission Charges) Rules, 2021, in rule 3, in sub-rule (5), after the first proviso, the following proviso shall be inserted, namely:- "Provided further that the Central Government may delegate powers to the National Committee on Transmission and Central Transmission Utility for approving Inter-State Transmission System projects subject to the cost limits specified by the Central Government from time to time." [F. No. 15/3/2018-Trans-Part(7)] SRIKANT NAGULAPALLI, Addl. Secy. Note: The principal rules were published in the Gazette of India, Extraordinary, Part II, Section 3, Sub-section (i), vide number G.S.R. 711(E), dated the 1st October, 2021. Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064 and Published by the Controller of Publications, Delhi-110054. KUMER CHAND MEENA Digitally signed by KUMER CHAND Date: 2025.06.27 22:05:32 +0530

Never miss important gazettes

Create a free account to save gazettes, add notes, and get email alerts for keywords you care about.

Sign Up Free