Full Text
8283 GI/202 4 (1)
EXTRAORDINARY
PART II —Section 3 —Sub-section ( ii)
PUBLISHED BY AUTHORITY
No. 5117] NEW DELHI , MON DAY , DEC EMBER 23, 2024 /PAUSA 2, 194 6
CG-DL-E-26122024-259626
MINISTRY OF POWER
ORDER
New Delhi , the 23rd December , 2024
S.O. 5532(E).—Whereas M/s VEH Jayin Renewables Private Limited, having its corporate office at
9th Floor, My Home Twitza, Plot No 30/A, TSIIC Hyderabad Knowledge City, Raidurg, Hyderabad, Telangana -
500081 has applied for authorization under Section 164 o f the Electricity Act, 2003 for installation of the dedicated
overhead transmission line included in the transmission system for providing connectivity to M/s VEH Jayin
Renewables Private Limited for the quantum of 151.8MW Hybrid Project with the installed capacity of 196.8MW
(151.8 MW Wind Power Projec t+ 45MW Solar Power Project) in Dhar District, Madhya Pradesh.
And whereas, Ministry of Power, Government of India vide its File No. 25 -17/52/2023 -PG dated 22.12.2023
had granted prior approval under section 68(1) of the Electricity Act, 2003 for installat ion of the dedicated overhead
transmission line included in the transmission system for providing connectivity to M/s VEH Jayin Renewables
Private Limited for the quantum of 151.8MW Hybrid Project with the installed capacity of 196.8MW (151.8 MW
Wind Power Project+ 45MW Solar Power Project) in Dhar District, Madhya Pradesh.
M/s VEH Jayin Renewables Private Limited had published notice for transmission scheme in local
newspapers The Times of Inda (in English) dated 13.03.2024, Dainik Bhaskar (in Hindi) dated 13.03.2024 and in
Weekly Gazette of India dated 11.05.2024 for the general public to make observations/representations on the proposed
transmission route within two months from the date of publication. Subsequently, M/s VEH Jayin Renewables Private
Limite d has submitted an affidavit dated 22.08.2024 declaring that no observation/representation was received within
two months from the date of Publication in the official Gazette of Government of India.
And now the applicant has requested to confer upon him, all the powers under section 164 of the Electricity
Act, 2003, which the telegraph authority possess under the Indian Telegraph Act, 1885 with respect to the placing of
telegraph lines and posts for the purpose of a telegraph established or maintained by G overnment or to be so
established or maintained for installation of the dedicated overhead transmission line included in the transmission
system for providing connectivity to M/s VEH Jayin Renewables Private Limited for the quantum of 151.8MW
Hybrid Projec t with the installed capacity of 196.8MW (151.8 MW Wind Power Project+ 45MW Solar Power
Project) in Dhar District, Madhya Pradesh. The following overhead transmission line is covered under this scheme: -
(i) VEH Jayin Renewable Pvt. Ltd (Generation Switchy ard in Hanumantya Kag Village, Sardarpur Tehsil, Dhar
District, Madhya Pradesh) - Rajgarh (PG) 220kV S/C line
The overhead transmission line covered under the above scheme will pass through, over, around and between
the following villages, towns and cities of Madhya Pradesh:
Villages Tehsil District State
Dhulet, Amodiya, Narsingh Dewla, Paswada, Moya Kheda,
Hanumantiya Kag Sardarpur Dhar Madhya
Pradesh
Now, after careful consideration, Ministry of Power, Government of India, under section 164 of the Elec tricity
Act, 2003, confers all the powers to M/s VEH Jayin Renewables Private Limited for laying above overhead
transmission line, which telegraph author ity possesses under the Indian Telegraph Act, 1885 with respect to placing of
telegraph lines and posts for the purposes of a telegraph established or maintained, by Government or to be established
or maintained subject to following terms and conditions fo r installing the above mentioned line, namely:
i. The approval is granted for 25 years.
ii. The Applicant shal l have to seek the consent of the concerned authorities i.e., local bodies, Railways,
National Highways, State Highways etc. before erection of proposed line.
iii. The Applicant shall have to follow regulations/codes of the Appropriate Commission regarding tran smission,
O&M, open access, etc., framed under the Electricity Act, 2003.
iv. The Applicant shall operate the line after approval of Electrical Inspector / C hief Electrical Inspector of
Central Government.
v. The approval is subject to compliance of the requireme nt of the provisions of the Electricity Act, 2003 and
the rules made there under by the applicant.
vi. M/s VEH Jayin Renewables Private Limited shall have to submit the requisite clearances to Central
Electricity Authority after obtaining the same from concern ed authorities like Civil Aviation, Defense etc., at
the time of Electrical Inspection.
vii. In case, the route of above overhead lines (or some portion of th e route of above overhead line) falls in the
Great Indian Bustard (GIB) area, the applicant has to comp ly with the orders of the Hon’ble Supreme Court
in the petition No.838 of 2019 regarding Great Indian Bustard (GIB) case, and the directions of the
techn ical/expert committee constituted by the Hon’ble Supreme Court in this regard.
[F.No. 25-16/42/2024 -PG]
M.V.N. VARA PRASAD , Under Sec y. (PG)
Uploaded by Dte. of Printing at Gov ernment of India Press, Ring R oad, Mayapuri, New Delhi -110064
and Published by the Controller of Publications, Delhi -110054.
Login to read full text