Full Text
7907 GI/202 3 (1)
EXTRAORDINARY
PART II —Section 3 —Sub-section ( ii)
PUBLISHED BY AUTHORITY
No. 5206] NEW DELHI, FRIDAY , DECEMBER 22, 2023/ PAUS HA 1, 1945
CG-DL-E-23122023-250853
MINISTRY OF POWER
ORDER
New Delhi, the 22nd December, 2023
S.O. 5436(E).— Whereas M/s Juniper Nirjara Energy Private Limited (JNEPL)(erstwhile M/s Spring Nirjara
Energy Private Lim ited), the applicant with its registered address at F -9, First Floor, Manish Plaza -1, Plot No. 7 MLU,
Sector -10, Dwarka New Delhi -110075has applied for authorization under Section 164 of the Electricity Act, 2003 for
laying of overhead transmission line un der the scheme “Installation of the dedicated overhead transmission line
included in the transmission system for providing connectivity to Juniper Nirjara Energy Private Limited for its 50
MW Solar Power Project in Bikaner District of Rajasthan”.
And where as, Ministry of Power, Government of India vide its letter No. 25 -17/14/2023 -PG dated
10.08.2023 had granted prior approval under section 68(1) of the Electricity Act, 2003 for the overhead line covered
under the scheme “Installation of the dedicated overh ead transmission line included in the transmission system for
providing connectivity to Juniper Nirjara Energy Private Limited for its 50 MW Solar Power Project in Bikaner
District of Rajasthan”.
M/s Juniper Nirjara Energy Private Limited had published not ice for transmission scheme in local
newspapers Indian Express (in English) dated 17.08.2023, Dainik Bhaskar(in Hindi) dated 17.08.2023 and in Weekly
Gazette of India dated 02.09.2023 for the general public to make observations/representations on the propo sed
transmission route within Two Months from the date of publication. Subsequently, M/s Juniper Nirjara Energy Private
Limited has submitted an affidavit dated 02.11.2023 declaring that no observation/representation was received within
Two Months from the date of publication in the official gazette of Government of India.
And now the applicant has requested to confer upon him, all the powers under section 164 of the Electricity
Act, 2003, which the telegraph authority possess under the Indian Telegraph Ac t, 1885 with respect to the placing of
telegraph lines and posts for the purpose of a telegraph established or maintained by Government or to be so
established or maintained for laying of transmission line underthe scheme“Installation of the dedicated over head
transmission line included in the transmission system for providing connectivity to Juniper Nirjara Energy Private
Limited for its 50 MW Solar Power Project in Bikaner District of Rajasthan”. The following overhead transmission
line is covered under t his scheme:
Juniper Nirjara Energy Private Limited (Solar Power Project) – Bikaner II (ISTS) Pooling Station 220kV line
The transmission line covered under the above scheme will pass through, over, around and between the following
villages, towns and citi es of Rajasthan:
S. No. Name of Villages Tehsil District
1 NokhaDaiya, Nokha Kolayat Bikaner
2 Kawani, Jaimalsar, Sarah Borla Bikaner Bikaner
3 Bhanipura Pugal Bikaner
Now, after careful consideration, Ministry of Power, Government of India, under section 164 of the Electricity
Act, 2003, confers all the powers to M/s Juniper Nirjara Energy Private Limited for laying above overhead
transmission line, which telegraph authority possesses under the Indian Telegraph Act, 1885 with respect to placing of
telegraph lines and posts for the purposes of a telegraph established or maintained, by Government or to be established
or maintained subject to following terms and conditions for installing the above mentioned line, namely:
i. The approval is granted for 25 years.
ii. The Applicant shall have to seek the consent of the concerned authorities i.e., local bodies, Railways,
National Highways, State Highways etc. before erection of proposed line.
iii. The Applicant shall have to follow regulations/codes of the Appropriate Commission regarding transmission,
O&M, open access, etc., framed under Electricity Act, 2003.
iv. The Applicant shall operate the line after approval of Electrical Inspector / Chief Electrical Inspector of
Central Government.
v. The approval is subject to compli ance of the requirement of the provisions of the Electricity Act, 2003 and
the rules made there under by the applicant.
vi. M/s Juniper Nirjara Energy Private Limited shall have to submit the requisite clearances to Central
Electricity Authority after obtainin g the same from concerned authorities like Civil Aviation, Defense etc., at
the time of Electrical Inspection.
vii. In case, the route of above overhead lines (or some portion of the route of above overhead line ) falls in the
GIB potential zone (or priority zo ne) marked in the map which is part of the order of the Hon’ble Supreme
Court order dated 19.04.2021, in the petition No.838 of 2019 regarding GIB (Great Indian Bustard) case, the
applicant has to comply with the directions of the Hon’ble Supreme Court, wi th regard to undergrounding of
the above overhead transmission line and / or fixing of bird diverters, as the case may be as per the Hon’ble
Supreme Court Order dated 19.04.2021 and the directions of the technical committee constituted by the
Hon’ble Supre me Court in this regard.
[F. No.25 -16/36/2023 -PG]
M. V. N. VARA PRASAD , Under Secy . (PG)
Uploaded by Dte. of Printing at Government of India Press, Ring R oad, Mayapuri, New Delhi -110064
and Published by the Cont roller of Publications, Delhi -110054.