Full Text
7875 GI/202 3 (1)
EXTRAORDINARY
PART II —Section 3 —Sub-section ( ii)
PUBLISHED BY AUTHORITY
No. 5186] NEW DELHI, FRIDAY , DECEMBER 22, 2023/ PAUSA 1, 1945
CG-DL-E-22122023-250822
MINISTRY OF POWER
ORDER
New Delhi, the 11th December, 2023
S.O. 5416(E).—Whereas M/s Juna Renewable Energy Private Limited has its registered address at J -1/37,
3rd Floor, DLF City Phase -II, Gurugram, Haryana - 122002, India has applied for authorization under Section 164 of
the Electricity Act, 2003 for laying of overhead transmission line un der “Installation of dedicated overhead
transmission line included in the transmission system for providing connectivity to Juna Renewable Energy Private
Limited for its 335 MW (290 MW + 45 MW) Solar Power Plant in Bikaner, Rajasthan”.
And whereas, Central Electricity Authority (CEA), Ministry of Power, Government of India vide its letter
CEA -PS-11-21(25)/1/2018 -PSPA -I Division dated 08.02.2023 had granted prior approval under section 68(1) of the
Electricity Act, 2003 for the overhead line covered under “I nstallation of dedicated overhead transmission line
included in the transmission system for providing connectivity to Juna Renewable Energy Private Limited for its 335
MW (290 MW + 45 MW) Solar Power Plant in Bikaner, Rajasthan”.
M/s Juna Renewable Energy Private Limited had published notice for transmission scheme in local
newspapers The Indian Express (in English) dated 04.03.2023, Dainik Navajyoti (in Hindi) dated 04.03.2023, and in
Weekly Gazette of India dated 20.05.2023 for the general public to make observations/representations on the proposed
transmission route within 2 Months from the date of publication. Subsequently, M/s Juna Renewable Energy Private
Limited has submitted an affidavit dated 08.11.2023 declaring that no observation/representation w as received within
2 Months from the date of Publication in the official gazette of Government of India.
And now the applicant has requested to confer upon him, all the powers under section 164 of the Electricity
Act, 2003, which the telegraph authority p ossess under the Indian Telegraph Act, 1885 with respect to the placing of
telegraph lines and posts for the purpose of a telegraph established or maintained by Government or to be so
established or maintained for laying of electric lines under “Installati on of dedicated overhead transmission line
included in the transmission system for providing connectivity to Juna Renewable Energy Private Limited for its 335
MW (290 MW + 45 MW) Solar Power Plant in Bikaner, Rajasthan”. The following overhead line is cove red under
this scheme:
1. Juna Renewable Energy Private Limited Solar Power Plant (switchyard located in Village Kawani,
District -Bikaner, Rajasthan) – Bikaner -II (ISTS) Pooling station 220 kV S/c Line on D/c towers.
The transmission line covered under the above scheme will pass through, over, around and between the
following villages, towns and cities of Rajasthan:
Sl. No. Name of Villages Tehsil District
1. Kawani Kolayat Bikaner
2. Jaimalsar Kolayat Bikaner
3. Sharah Borla Bikaner (Nal Badi) Bikaner
Now, after careful consideration, Ministry of Power, Government of India, under section 164 of the
Electricity Act, 2003, confers all the powers to M/s Juna Renewable Energy Private Limited for laying above
overhead line, which telegraph authority possesses under the Indian Telegraph Act, 1885 with respect to placing of
telegraph lines and posts for the purposes of a telegraph established or maintained, by Go vernment or to be established
or maintained subject to following terms and conditions for installing the above mentioned line, namely:
(i) The approval is granted for 25 years.
(ii) The Applicant shall have to seek the consent of the concern ed authorities i.e., local bodies, Railways, National
Highways, State Highways etc. before erection of proposed line.
(iii) The Applicant shall have to follow regulations/codes of the Appropriate Commission regarding transmission,
O&M, open access, e tc., framed under Electricity Act, 2003.
(iv) The Applicant shall operate the line after approval of Electrical Inspector / Chief Electrical Inspector of
Central Government.
(v) The approval is subject to compliance of the requirement of the p rovisions of the Electricity Act, 2003 and the
rules made there under by the applicant.
(vi) M/s Juna Renewable Energy Private Limited shall have to submit the requisite clearances to Central
Electricity Authority after obtaining the same from concer ned authorities like Civil Aviation, Defense etc., at the time
of Electrical Inspection.
(vii) In case, the route of above overhead lines (or some portion of the route of above overhead line ) falls in the
Great Indian Bustard (GIB) potential zone (or priority zone) marked in the map which is part of the order of the
Hon’ble Supreme Court order dated 19.04.2021, in the petition No.838 of 2019 regarding Great Indian Bustard (GIB)
case, the applicant has to comply with the directions of the Hon’ble Supre me Court, with regard to undergrounding of
the above overhead transmission line and/or fixing of bird diverters, as the case may be as per the Hon’ble Supreme
Court Order dated 19.04.2021 and the directions of the technical committee constituted by the Hon ’ble Supreme Court
in this regard.
[F. No. 25-16/33/2023 -PG]
M.V.N. VARA PRASAD , Under Sec y. (PG)
Uploaded by Dte. of Printing at Government of India Press, Ring R oad, Mayapuri, New Delhi -110064