MINISTRY OF POWER
RESOLUTIO N
New Delhi, the 17th November, 2023
Amendment to the Guidelines for Tariff Based Competitive Bidding Process for Procurement Power from Grid
Connected Wind Power Projects
No. 48 -19/2/2023 -NRE .—The Guidelines for Tariff Based Competitive Bidding Process f or Procurement of
Power from Grid Connected Wind Power Projects have been notified vide Resolution No.27/02/2023 -RCM published
in the Gazette of India (Extraordinary) (Part1 - Section 1) on 26th July 2023.
2. The Central Government hereby notifies the following amendment in the said guidelines dated 26th July,
2023: -
Clause 14.4 of the existing guidelines is substituted with the following,
Clause 14.4 . Early Commencement of Supply of Power: The WPG shall be permitted for c ommencement of supply
from full as well as part capacity of the Project even prior to the SCSD subject to availability of transmission
connectivity and Long -Term Access (LTA)/General Network Access (GNA). In cases of early part or full
commencement of supp ly of power, the developer shall give fifteen (15) days advance notice to both End Procurer(s)
and Intermediary Procurer regarding the advance commissioning of full or part capacity. The End Procurer(s) and
Intermediary Procurer shall give acceptance for a vailing such power within 15 days from the date of service of notice.
In case, both the End Procurer(s) and Intermediary Procurer do not give their acceptance to purchase power within the
stipulated period, the developer can sell the power to the extent no t accepted by the End Procurer(s) and Intermediary
Procurer in the power exchanges or through bilateral arrangements.
Provided that in case both the End Procurer(s) and Intermediary Procurer give their acceptance to purchase the power,
the End Procurer(s) will be accorded priority in availing such power.
Provided further that in such cases tariff payable by the End Procurer(s) and the Intermediary Procurer shall be equal
to the PPA tariff.
HEMANT KUMAR PANDEY, Chief Engineer (R&R)