MINISTRY OF POWER
ORDER
New Delhi, the 10th September,2025
S.O. 4140(E).— Whereas M/s Powergrid Sikar Khetri Transmission Limited, the applicant with
its registered office at B-9, Qutab Institutional Area, Katwaria Sarai, Hauz Khas, New Delhi, South Delhi,
Delhi, India -110016 has applied for authorization under Section 164 of the Electricity Act, 2003 for laying
of overhead transmission line included in the transmission scheme for evacuation of power from Renewable
Energy Zones (REZ) in Rajasthan (20 GW) under Phase-III- Part D, Phase-I.
And whereas, Central Electricity Authority (CEA), Ministry of Power, Government of India vide its
File No. 25-17/53/2023-PG dated 22.12.2023 had granted prior approval under section 68(1) of the Electricity
Act, 2003 for laying of overhead transmission line included in the transmission scheme for evacuation of
power from Renewable Energy Zones (REZ) in Rajasthan (20 GW) under Phase-III- Part D, Phase-I.
M/s Powergrid Sikar Khetri Transmission Limited had published notice for transmission scheme in
local newspapers The Times of India (in English) dated 12.06.2024 along with corrigendum dated
24.04.2025, The Tribune (in English) dated 23.04.2025 along with corrigendum dated 24.04.2025, Rajasthan
Patrika and Amar Ujala (both in Hindi) dated 12.06.2024 along with corrigendum dated 24.04.2025, and in
Weekly Gazette of India dated 20.07.2024 along with corrigendum dated 14.06.2025 for the general public
to make observations/ representations on the proposed transmission route within two months from the date
of publication. Subsequently, M/s Powergrid Sikar Khetri Transmission Limited has submitted an affidavit
dated 19.08.2025 declaring that one observation/ representation was received within two months from the date
of Publication in the official Gazette of Government of India and Newspapers and the same have been
answered by M/s Powergrid Sikar Khetri Transmission Limited and that no further representations were
received.
And now the applicant has requested to confer upon him, all the powers under section 164 of the
Electricity Act, 2003, which the telegraph authority possess under the Indian Telegraph Act, 1885 with
respect to the placing of telegraph lines and posts for the purpose of a telegraph established or maintained by
Government or to be so established or maintained for laying of overhead transmission line for M/s Powergrid
Sikar Khetri Transmission Limited. The following overhead transmission line is covered under this scheme:
1. Sikar-II Narela 765 kV D/C Line
The overhead transmission line covered under the above scheme will pass through, over, around and between
the following villages, towns and cities of Rajasthan, Haryana and Delhi
| Villages ```