Core Purpose

Resolution amending Paragraph 15 of the Guidelines for Encouraging Competition in Development of Transmission Projects to reassign project-survey allocation duties.

Detailed Summary

The Ministry of Power issued a Resolution dated 4th July 2023 (No. 15/3/2018-Trans-Part(3)) amending Paragraph 15 of the Guidelines for Encouraging Competition in Development of Transmission Projects, which had originally been notified vide Ministry of Power Resolution No. 15/1/2017-Trans dated 10th August 2021 under the Electricity Act, 2003; the amendment replaces the earlier provision, under which the task of preparing survey reports was allocated by the National Committee on Transmission (NCT) on a roster basis among the Central Transmission Utility (CTU) and Bid Process Coordinators (BPCs), with a new provision under which the NCT shall allocate the survey-report task directly to the respective Bid Process Coordinators; the resolution was issued under file number F. No. 15/3/2018-Trans-Pt(3) and signed by Dr. Sai Baba Darbamulla, Joint Secretary (Trans).

Full Text

EXTRAORDINARY PART I—Section 1 PUBLISHED BY AUTHORITY No. 169] NEW DELHI, TUES DAY, JULY 4, 2023/ASHADHA 13, 194 5 CG-DL-E-05072023-247026 MINISTRY OF POWER RESOLUTION New Delhi, t he 4th July, 2023 Guidelines for Encouraging Competition in Development of Transmission Projects No. 15/3/2018 -Trans -Part(3) - The Guidelines for Encouraging Competition in Development of Transmission Projects had been notified vide Ministry of Power Resol ution No. 15/1/2017 -Trans dated 10.08.2021, under the provisions of the Electricity Act, 2003. In this regard, Para 15 of the above Guidelines is hereby amended as under: PROJECT FORMULATION Existing Para Amended Para ..............The task of preparing survey report shall be allocated by National Committee on Transmission (NCT) by maintaining a roster amongst agencies namely CTU & BPCs. After actual decision regarding the mode of execution of any transmission project, the relevant survey report shall be procured by the agency bidding out the transmission project from the agency nominated by NCT for survey upon reimbursement of the cost incurred. ...............The NCT shall allocate the task of carrying out survey repor t of transmission projects to the respective Bid Process Coordinators (BPCs). [F. No. 15/3/2018 -Trans -Pt(3)] Dr. SAI BABA DARBAMULLA , Jt. Secy . (Trans) Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi -110064 and Published by the Controller of Publications, Delhi -110054.

Never miss important gazettes

Create a free account to save gazettes, add notes, and get email alerts for keywords you care about.

Sign Up Free