Ministry of Power, Government of India confers powers under Section 164 of the Electricity Act, 2003 to M/s NTPC Renewable Energy Limited for laying a 400 kV S/C Overhead Line from PSS2 to KPS2.

Detailed Summary

The Ministry of Power, Government of India, issued Order S.O. 2014(E) on 29th April, 2025, concerning an application by M/s NTPC Renewable Energy Limited, with its registered office in Greater Noida, Uttar Pradesh. NTPC REL applied for authorization under Section 164 of the Electricity Act, 2003, to lay a 400 kV S/C Overhead Line from PSS2 to KPS2 for its 1555 MW Solar Power Project at Khavda RE Park, Gujarat. The Ministry had previously granted prior approval under Section 68(1) of the Electricity Act, 2003, vide File No. 25-17/18/2023-PG dated 11.09.2023. NTPC REL published public notices in the Times of India (English) on 23-11-2024, Garvi Gujarat (Hindi) on 22-11-2024, and the Weekly Gazette of India on 14.12.2024. An affidavit dated 01.04.2025 confirmed no observations or representations were received within two months of the official Gazette publication. Under Section 164 of the Electricity Act, 2003, the Ministry confers upon NTPC REL all powers that the telegraph authority possesses under the Indian Telegraph Act, 1885, for placing telegraph lines and posts for government-established/maintained telegraphs, specifically for the NTPC REL Pooling Station 2 - KPS2 400 kV S/C line (on D/C tower). This line will pass through areas including the RE Park at Khavda in Bhuj Tehsil, Kutch District, Gujarat. The approval is granted for 25 years, subject to conditions including seeking consent from relevant authorities (local bodies, Railways, National Highways, State Highways etc.), following Appropriate Commission regulations/codes, operating the line after approval from the Electrical Inspector / Chief Electrical Inspector of Central Government, complying with the Electricity Act, 2003 and rules, submitting clearances from authorities like Civil Aviation and Defense to the Central Electricity Authority, and complying with Hon'ble Supreme Court orders in Petition No. 838 of 2019 regarding the Great Indian Bustard (GIB) case if the route is in the GIB area. The order was issued by M.V.N. VARA PRASAD, Under Secretary (PG).

Full Text

REGD. No. D. L.-33004/99 The Gazette of India CG-DL-E-05052025-262910 EXTRAORDINARY PART II—Section 3—Sub-section (ii) PUBLISHED BY AUTHORITY No. 1970] NEW DELHI, MONDAY, MAY 5, 2025/VAISAKHA 15, 1947 2966 GI/2025 MINISTRY OF POWER ORDER New Delhi, the 29th April, 2025 S.O. 2014(E).- Whereas M/s NTPC Renewable Energy Limited, the applicant with its registered office at NTPC REL, E3, Ecotech-II, Udyog Vihar, Greater Noida, Uttar Pradesh-201306 has applied for authorization under Section 164 of the Electricity Act, 2003 to NTPC REL for laying of 400 kV S/C Overhead Line from PSS2 to KPS2 for its 1555 MW Solar Power Project at Khavda RE Park, Gujarat. And whereas, Ministry of Power, Government of India vide its File No.25-17/18/2023-PG dated 11.09.2023 had granted prior approval under section 68(1) of the Electricity Act, 2003 to NTPC REL for laying of 400 kV S/C Overhead Line from PSS2 to KPS2 for its 1555 MW Solar Power Project at Khavda RE Park, Gujarat. M/s NTPC Renewable Energy Limited had published notice for transmission scheme in local newspapers Times of India (in English) dated 23-11-2024 & Garvi Gujarat (in Hindi) dated 22-11-2024, and in Weekly Gazette of India dated 14.12.2024 for the general public to make observations/ representations on the proposed transmission route within two months from the date of publication. Subsequently, M/s NTPC Renewable Energy Limited has submitted an affidavit dated 01.04.2025 declaring that no observation/ representation was received within two months from the date of Publication in the official Gazette of Government of India. And now the applicant has requested to confer upon him, all the powers under section 164 of the Electricity Act, 2003, which the telegraph authority possess under the Indian Telegraph Act, 1885 with respect to the placing of telegraph lines and posts for the purpose of a telegraph established or maintained by Government or to be so established or maintained for laying of overhead transmission line for M/s NTPC Renewable Energy Limited. The following overhead transmission line is covered under this scheme: 1. NTPC REL Pooling Station 2 - KPS2 400 kV S/C line (on D/C tower) The overhead transmission line covered under the above scheme will pass through, over, around and between the following villages, towns and cities of Gujarat: +------------------+---------+----------+---------+ | Villages | Tehsil | District | State | +==================+=========+==========+=========+ | RE Park at Khavda| Bhuj | Kutch | Gujarat | +------------------+---------+----------+---------+ Now, after careful consideration, Ministry of Power, Government of India, under section 164 of the Electricity Act, 2003, confers all the powers to M/s NTPC Renewable Energy Limited for laying above overhead transmission line, which telegraph authority possesses under the Indian Telegraph Act, 1885 with respect to placing of telegraph lines and posts for the purposes of a telegraph established or maintained, by Government or to be established or maintained subject to following terms and conditions for installing the above mentioned line, namely: i. The approval is granted for 25 years. ii. The Applicant shall have to seek the consent of the concerned authorities i.e., local bodies, Railways, National Highways, State Highways etc. before erection of proposed line. iii. The Applicant shall have to follow regulations/ codes of the Appropriate Commission regarding transmission, O&M, open access, etc., framed under the Electricity Act, 2003. iv. The Applicant shall operate the line after approval of Electrical Inspector / Chief Electrical Inspector of Central Government. V. The approval is subject to compliance of the requirement of the provisions of the Electricity Act, 2003 and the rules made there under by the applicant. vi. M/s NTPC Renewable Energy Limited shall have to submit the requisite clearances to Central Electricity Authority after obtaining the same from concerned authorities like Civil Aviation, Defense etc., at the time of Electrical Inspection. vii. In case, the route of above overhead lines (or some portion of the route of above overhead line) falls in the Great Indian Bustard (GIB) area, the applicant has to comply with the orders of the Hon'ble Supreme Court in the petition No.838 of 2019 regarding Great Indian Bustard (GIB) case, and the directions of the technical/expert committee constituted by the Hon'ble Supreme Court in this regard. [F. No. 25-16/32/2025-PG] M.V.N. VARA PRASAD, Under Secy. (PG)

Never miss important gazettes

Create a free account to save gazettes, add notes, and get email alerts for keywords you care about.

Sign Up Free