Full Text
REGD. No. D. L.-33004/99
The Gazette of India
CG-DL-E-04082025-265195
EXTRAORDINARY
PART II-Section 3-Sub-section (ii)
PUBLISHED BY AUTHORITY
No. 3475]
NEW DELHI, FRIDAY, AUGUST 1, 2025/SHRAVANA 10, 1947
MINISTRY OF POWER
NOTIFICATION
New Delhi, the 1st August, 2025
S.O. 3561(E). In exercise of the powers conferred by sub-section (1) of section 8 of the Electricity Act,
2003 (here after in this notification referred to as the Act) and in supersession of the notification of the Government of
India in the Ministry of Power, S.O. 550(E), dated the 18th April, 2006, except as respects things done or omitted to
be done before such supersession, the Central Government hereby issues the following notification, namely:—
(1) Schemes for setting up of hydro generating stations, involving an estimated capital expenditure exceeding rupees
three thousand crores shall require the concurrence of the Central Electricity Authority:
Provided that off-stream closed-loop pumped storage schemes, irrespective of the quantum of capital
expenditure, shall be exempted from the requirement of concurrence by the Authority:
Provided also that for the schemes falling under the exempted category, the developer may seek technical
guidance from the Authority.
(2) The developer referred to in paragraph (1) shall ensure adherence to the provisions of the National Dam Safety
Act, 2021.
[F.No. 15-23/3/2021-Hydel-II]
MOHAMMAD AFZAL, Jt. Secy.