Full Text
REGD. No. D. L.-33004/99
The Gazette of India
CG-DL-E-04062024-254526
EXTRAORDINARY
PART II-Section 3-Sub-section (ii)
PUBLISHED BY AUTHORITY
No. 2064]
NEW DELHI, MONDAY, JUNE 3, 2024/JYAISHTHA 13, 1946
MINISTRY OF POWER
NOTIFICATION
New Delhi, the 31st May, 2024
S.O. 2163(E). In exercise of the powers conferred by sub- para 3.2 of the Guidelines circulated under
Section 63 of the Electricity Act, 2003 (no. 36 of 2003), the Central Government had notified/ modified scope of
following transmission scheme, for implementation under Tariff Based Competitive Bidding (TBCB) mode, vide
Gazette Notification mentioned below table:
+--------+-------------------------------------------------------------+----------------------------------------------+
| Sl. No.| Name of the Scheme | Gazette Notification by which Scheme |
| | | was notified |
+========+=============================================================+==============================================+
| 1. | Transmission system for evacuation of power from | S.O.1364(E)dated |
| | Rajasthan REZ Ph-IV (Part-3: 6 GW) [Bikaner complex] | 15.03.2024[F.No.15/3/2018-Trans-Part(4)] |
| | : Part A | |
+--------+-------------------------------------------------------------+----------------------------------------------+
2. Now, the Central Government has decided to modify the scope of above mentioned scheme, after
examining the corrigendum to the 18thmeeting of National Committee on Transmission (NCT). As such, the
scope mentioned at Sl. No. 3 of above scheme is hereby modified as mentioned below; other scopesof the
Transmission Scheme and Bid Process Co-ordinatorshall remain unchanged:
+--------+-------------------------------------------------------------+--------+-------------------------------------------------+---------------------+
| Sl. No.| Name of the Scheme | Sl. | Scope of the Transmission Scheme | Capacity / line |
| | | No. | | length km |
+========+=============================================================+========+=================================================+=====================+
| 1. | Transmission system | 3. | LILO of both ckts of Bikaner II PS- Bikaner III | Length -20 km |
| | for evacuation of | | PS (Quad) direct 400 kV line at Bikaner-IV PS | (Quad) |
| | power from Rajasthan | | | (LILO |
| | REZ Ph-IV (Part-3: 6 | | | length) |
| | GW) [Bikaner | | | |
| | complex] : Part A | | | |
+--------+-------------------------------------------------------------+--------+-------------------------------------------------+---------------------+
[F. No. 15/3/2018-Trans-Pt(4)]
NAOREM INDRAKUMAR SINGH, Under Secy. (Trans)
Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064
and Published by the Controller of Publications, Delhi-110054. RAVINDER Digitally signed by
KUMAR RAVINDER KUMAR
Date: 2024.06.04
13:57:05 +05'30'
Login to read full text