The National Committee on Transmission de-notifies a previously approved transmission scheme for the evacuation of power from Luhri Stage-I HEP.

Detailed Summary

The Ministry of Power, through the Central Electricity Authority, issued a notification on March 16, 2026, de-notifying a specific transmission scheme. This action is taken in exercise of powers conferred by Para 3.2 of the Tariff Based Competitive Bidding Guidelines for Transmission Services, framed under Section 63 of the Electricity Act, 2003 (no. 36 of 2003), and Ministry of Power office order dated October 28, 2021. The National Committee on Transmission (NCT), chaired by the Chairperson of the Central Electricity Authority, had originally notified the "Transmission system for evacuation of power from Luhri Stage-I HEP" for implementation under Tariff Based Competitive Bidding (TBCB) via a Gazette Notification dated June 2, 2022 [F. No. CEA-PS- 11-15(11)/1/2021- PSPA I Division]. However, following its 38th meeting on February 25, 2026, the NCT recommended a modified scheme for approval by the Ministry of Power, leading to the de-notification of the aforementioned scheme, including its scope.

Full Text

REGD. No. D. L.-33004/99 The Gazette of India CG-DL-E-04042026-271558 EXTRAORDINARY PART IIIโ€”Section 4 PUBLISHED BY AUTHORITY No. 236] NEW DELHI, THURSDAY, APRIL 2, 2026/CHAITRA 12, 1948 MINISTRY OF POWER (Central Electricity Authority) NOTIFICATION New Delhi, the 16th March, 2026 F. No. CEA-PS-12-13/3/2022-PSPA-II Division. In exercise of the powers conferred by Para 3.2 of the Tariff Based Competitive Bidding Guidelines for Transmission Services framed under Section 63 of the Electricity Act, 2003 (no. 36 of 2003) and Ministry of Power office order dated 28.10.2021, National Committee on Transmission (NCT) headed by Chairperson, Central Electricity Authority had notified following transmission scheme for implementation under Tariff Based Competitive Bidding (TBCB) vide Gazette Notification mentioned in below table:- +-----+---------------------------------------------+-------------------------------------------------------------+ | Sr. | Name of Transmission Scheme | Gazette Notification by which Transmission Scheme | | No. | | was notified | +=====+=============================================+=============================================================+ | 1 | Transmission system for evacuation of power | Dated 02.06.2022 [F. No. CEA-PS- 11-15(11)/1/2021- | | | from Luhri Stage-I HEP | PSPA I Division] | +-----+---------------------------------------------+-------------------------------------------------------------+ 2. Now, the National Committee on Transmission (NCT) in the 38th meeting held on 25.02.2026 has recommended modified scheme for approval of MoP. As such, the above scheme including its scope is hereby de-notified. RAKESH KUMAR, Secy., CEA [ADVT.-III/04/Exty./04/2026-27]

Never miss important gazettes

Create a free account to save gazettes, add notes, and get email alerts for keywords you care about.

Sign Up Free