The Gazette of India
CG-DL-E-03032025-261444
EXTRAORDINARY
PART II-Section 3-Sub-section (ii)
PUBLISHED BY AUTHORITY
No. 1069]
NEW DELHI, MONDAY, MARCH 3, 2025/PHALGUNA 12, 1946
MINISTRY OF POWER
ORDER
New Delhi, the 3rd March, 2025
S.O. 1077(E).—Whereas M/s AMPIN Energy Green Private Limited, the applicant with its registered office
at 309, 3rd Floor, Rectangle One, Behind Sheraton Hotel, Saket, New Delhi, India- 110017, has applied for
authorization under Section 164 of the Electricity Act, 2003 for laying of dedicated overhead transmission line
included in the transmission scheme for providing connectivity to M/s AMPIN Energy Green Private Limited for its
proposed 300 MW Hybrid Power Project in Barmer, Rajasthan.
And whereas, Central Electricity Authority (CEA), Ministry of Power, Government of India vide its File No.
25-17/65/2024-PG dated 01st July, 2024 had granted prior approval under section 68(1) of the Electricity Act, 2003
for laying of dedicated overhead transmission line included in the transmission scheme for providing connectivity to
M/s AMPIN Energy Green Private Limited for its proposed 300 MW Hybrid Power Project in Barmer, Rajasthan.
M/s AMPIN Energy Green Private Limited had published notice for transmission scheme in local
newspapers The Times of India (in English) dated 26.07.2024 & Dainik Bhaskar (in Hindi) dated 26.07.2024, and in
Weekly Gazette of India dated 24.08.2024 for the general public to make observations/ representations on the
proposed transmission route within two months from the date of publication. Subsequently, M/s AMPIN Energy
Green Private Limited has submitted an affidavit dated 01.11.2024 declaring that no observation/ representation was
received within two months from the date of Publication in the official Gazette of Government of India.
And now the applicant has requested to confer upon him, all the powers under section 164 of the Electricity
Act, 2003, which the telegraph authority possess under the Indian Telegraph Act, 1885 with respect to the placing of
telegraph lines and posts for the purpose of a telegraph established or maintained by Government or to be so
established or maintained for laying of dedicated overhead transmission line for providing connectivity to M/s
AMPIN Energy Green Private Limited for its proposed 300 MW Hybrid Power Project in Barmer, Rajasthan. The
following overhead transmission line is covered under this scheme:
•
Common Pooling station of AMP Energy Green Eight, Ten & Three Hybrid Power Projects in village Balai,
District Barmer, Rajasthan – Fatehgarh IV (ISTS) Pooling Station (Sec-I) 220kV S/c line
The overhead transmission line covered under the above scheme will pass through, over, around and between the
following villages, towns and cities of Rajasthan:
+---------------------+---------+----------+-----------+
| Villages | Tehsil | District | State |
+=====================+=========+==========+===========+
| Gunga, Pujraj Singh Ki Dhani, | Sheo | Barmer | Rajasthan |
| Bisu Kala, Pushad, Sita Ram Ki | | | |
| Dhani | | | |
+---------------------+---------+----------+-----------+
Now, after careful consideration, Ministry of Power, Government of India, under section 164 of the Electricity
Act, 2003, confers all the powers to M/s AMPIN Energy Green Private Limited for laying above overhead
transmission line, which telegraph authority possesses under the Indian Telegraph Act, 1885 with respect to placing of
telegraph lines and posts for the purposes of a telegraph established or maintained, by Government or to be established
or maintained subject to following terms and conditions for installing the above-mentioned line, namely:
I.
The approval is granted for 25 years.
II.
The Applicant shall have to seek the consent of the concerned authorities i.e., local bodies, Railways,
National Highways, State Highways etc. before erection of proposed line.
III.
The Applicant shall have to follow regulations/ codes of the Appropriate Commission regarding
transmission, O&M, open access, etc., framed under the Electricity Act, 2003.
IV.
The Applicant shall operate the line after approval of Electrical Inspector / Chief Electrical Inspector of
Central Government.
V.
The approval is subject to compliance of the requirement of the provisions of the Electricity Act, 2003 and
the rules made there under by the applicant.
VI.
M/s AMPIN Energy Green Private Limited shall have to submit the requisite clearances to Central
Electricity Authority after obtaining the same from concerned authorities like Civil Aviation, Defense etc.,
at the time of Electrical Inspection.
VII.
In case, the route of above overhead lines (or some portion of the route of above overhead line) falls in the
Great Indian Bustard (GIB) area, the applicant has to comply with the orders of the Hon'ble Supreme
Court in the petition No.838 of 2019 regarding Great Indian Bustard (GIB) case, and the directions of the
technical/expert committee constituted by the Hon'ble Supreme Court in this regard.
[F. No. 25-16/14/2025-PG]
M.V.N. VARA PRASAD, Under Secy. (PG)