MINISTRY OF POWER
RESOLUTION
New Delhi, the 2nd February, 2024
Amendment to the Guidelines for Tariff Based Competitive Bidding Process for Procurement of Power from
Grid Connected Solar PV Power Projects
No. 48-19/2/2024-NRE.—The Guidelines for Tariff Based Competitive Bidding Process for Procurement of
Power from Grid Connected Solar PV Power Projectshave been notified vide Resolution No. 27/01/2023-RCM
published in the Gazette of India (Extraordinary) (Part 1 Section 1) on 28th July 2023.
2.
The Central Government hereby notifies the following amendment in the said guidelines dated
28th July, 2023:-
Clause 13.3 of the existing guidelines is modified as follows :-
Clause 13.3:Delay in Commencement of Supply of Power:
Clause 13.3 (b) (ii) shall stand deleted.
HEMANT KUMAR PANDEY, Chief Engineer (R&R)