Full Text
REGD. No. D. L.-33004/99
The Gazette of India
CG-TL-E-02072026-274021
EXTRAORDINARY
PART II—Section 3—Sub-section (ii)
PUBLISHED BY AUTHORITY
No. 3363]
NEW DELHI, MONDAY, JUNE 29, 2026/ ASHADHA 8, 1948
[F. No. E-313959/20E/270626]
MOHIT VERMA, Chief Engineer/Con-V
MINISTRY OF RAILWAYS
(South Central Railway)
NOTIFICATION
Secunderabad, the 3rd June, 2026
S.O. 3498(E).— Whereas, by the notification of the Government of India, in the Ministry of Railways
(Railway Board), number, S.O. 2299 (E) dated the 23 May 2025 published in Gazette of India, Extraordinary, Part II,
section 3 Sub-section(ii), dated the 20 May 2025 (hereinafter referred to as the said notification) and issued under sub-
section (1) of section 20(A) of the Railway Act, 1989 (24 of 1989), the Central Government declared its intention to
acquire the land specified in the schedule annexed to the said notification for the purpose of execution, maintenance,
management and operation of Special Railway Project, namely “Chhatrapati Sambhajinagar (Aurangabad) -
Ankai Doubling project” in the District of Nashik in the State of Maharashtra.
And whereas, the substance of the said notification was published in daily News Paper " Lokmat Times"
"Navbharat" & "Navarashtra" dated 04 June 2025, under sub section (4) of section 20A of the said Act,
And whereas, in Saygaon village, objections were not received and accordingly report have been passed by the
Competent Authority;
And whereas, in pursuance of sub-section (1) of 20E of the said Act, the competent authority has submitted its
report to the Central Government;
Now therefore, upon receipt of the report of the Competent Authority and in exercise of the powers conferred
by sub-section (1) of section 20(E). of the said Act, the Central Government hereby declares that the lands specified in
the schedule annexed hereto shall be acquired for the aforesaid purpose;
And further, in pursuance of sub-section (2) of section 20E of the said Act, the Central Government hereby
declares that on publication of this notification in the official Gazette, the land specified in the schedule annexed
hereto shall vest absolutely in the Central government free from all encumbrances.
SCHEDULE
"Chhatrapati Sambhajinagar (Aurangabad) - Ankai Doubling project” in Saygaon Village of Nashik District,
Under Sub- Divisional Officer & Land Acquisition officer Yeola and Competent Authority for Land Acquisition,
Yeola for Land Acquisition in the state of Maharashtra.
Brief description of the land to be acquired with or without structures, falling within the Special Railway Project
"Chhatrapati Sambhajinagar (Aurangabad) - Ankai Doubling project” in the State of Maharashtra.
+--------+------------------------------------+-------------------+-----------------------+--------------------------------------------------------------------------------------------------+------------+-----------------------+---------------------------------+---------------------------+-----------------------------------------+---------------+----------+---------+
| S. No. | Case No. | Taluka & District | Name of the village | As Per 7/12 Land holder's name | Survey No. | Land holding method | Total Area as per 7/12 (H.R) | Acquisition Area (H.R) | Well, / Bore | Constructions | Trees | Remarks |
+========+====================================+===================+=======================+==================================================================================================+============+=======================+=================================+===========================+=========================================+---------------+----------+---------+
| 1 | | | | Jijabai Bhanudas Kuldhar, | 68 | 1 | 3.88 | 0.03 | - | - | - | |
| | | | | Bhanudas Banderao Kuldhar, | | | | | | | | |
| | | | | Balnath Banderao Kuldhar | | | | | | | | |
+--------+------------------------------------+-------------------+-----------------------+--------------------------------------------------------------------------------------------------+------------+-----------------------+---------------------------------+---------------------------+-----------------------------------------+---------------+----------+---------+
| 2 | Case No.05/25 LA/Kavi/313/2026 | | Saygaon | Balnath Banderao Kuldhar | 82 | 1 | 2.43 | 0.07 | - | - | - | |
+--------+------------------------------------+-------------------+-----------------------+--------------------------------------------------------------------------------------------------+------------+-----------------------+---------------------------------+---------------------------+-----------------------------------------+---------------+----------+---------+
| 3 | Case No.05/25 LA/Kavi/313/2026 | | Yeola | Shubham Babasaheb Jathar, | 83 | 1 | 4.60 | 0.07 | - | - | - | |
| | | | | Jayshri Babasaheb Jathar, | | | | | | | | |
| | | | | Kacharu Karbhari Jathar, | | | | | | | | |
| | | | | Kantabai Namdev Jathar, | | | | | | | | |
| | | | | Ashok Pandurang Kuldhar, | | | | | | | | |
| | | | | Balnath Banderao Kuldhar. | | | | | | | | |
+--------+------------------------------------+-------------------+-----------------------+--------------------------------------------------------------------------------------------------+------------+-----------------------+---------------------------------+---------------------------+-----------------------------------------+---------------+----------+---------+
| 4 | | | | Lahanu Dada Dhakane, | 310 | 1 | 0.06 | 0.01 | - | - | - | |
| | | | | Dada Rama Dhakane, | | | | | | | | |
| | | | | Ranganath Kisan Dhakane, | | | | | | | | |
| | | | | Bhaga Rama Dhakane, | | | | | | | | |
| | | | | Bandu Dada Dhakane, | | | | | | | | |
| | | | | Kashinath Vitthal Dhakane, | | | | | | | | |
| | | | | Sudam Vitthal Dhakane, | | | | | | | | |
| | | | | Balu Vitthal Dhakane, | | | | | | | | |
| | | | | Sulyabai Baburao Ippar, | | | | | | | | |
| | | | | Sonyabai Vithoba Ugale, | | | | | | | | |
| | | | | Chandrbhaga Ashok Nagare | | | | | | | | |
+--------+------------------------------------+-------------------+-----------------------+--------------------------------------------------------------------------------------------------+------------+-----------------------+---------------------------------+---------------------------+-----------------------------------------+---------------+----------+---------+
| 5 | | | | Dilip Bandu Dhakane, | 311 | 1 | 2.22 | 0.08 | Borewell-1 PVC | | | |
| | | | | Navanath Bandu Dhakane. | | | | | Pipeline -1 (230 meter) | | | |
+--------+------------------------------------+-------------------+-----------------------+--------------------------------------------------------------------------------------------------+------------+-----------------------+---------------------------------+---------------------------+-----------------------------------------+---------------+----------+---------+
| 6 | | | | Bandu Dada Dhakane | 324 | 1 | 0.58 | 0.07.50 | - | - | - | |
+--------+------------------------------------+-------------------+-----------------------+--------------------------------------------------------------------------------------------------+------------+-----------------------+---------------------------------+---------------------------+-----------------------------------------+---------------+----------+---------+
| | | | Total | | | | | 0.33.50 | | | | |
+--------+------------------------------------+-------------------+-----------------------+--------------------------------------------------------------------------------------------------+------------+-----------------------+---------------------------------+---------------------------+-----------------------------------------+---------------+----------+---------+
[F. No. E-313959/20E/270626]
MOHIT VERMA, Chief Engineer/Con-V