Gazette Tracker
Gazette Tracker

Core Purpose

The Central Government declares the acquisition of specified lands and their absolute vesting in the Central Government for the Manmad-Jalgaon 4th Line Special Railway Project, in exercise of powers conferred by sub-section (1) and (2) of section 20E of the Railway (Amendment) Act, 2008.

Detailed Summary

This notification, S.O. 3241(E), issued by the Ministry of Railways (Central Railway) on July 15, 2025, declares the acquisition of land for the Manmad-Jalgaon 4th Line Special Railway Project in the districts of Jalgaon and Nashik in Maharashtra. This declaration is made under sub-section (1) and (2) of section 20E of the Railway (Amendment) Act, 2008 (11 of 2008), following a previous intention to acquire published via notification S.O. 2450(E) dated June 25, 2024, under sub-section (1) of section 20A of the Railway Act, 1989 (24 of 1989) and the Railway (Amendment) Act, 2008. The substance of the initial notification was published in "Dainik Sakaal" and "Dainik Deshonnati" on April 24, 2025, as per sub-section (4) of section 20A. Objections received were heard by the Competent Authority, and orders were passed in terms of Section D of the said Act. Subsequently, the Competent Authority submitted its report to the Central Government under sub-section 20E. Upon receipt of this report, the Central Government now declares that the lands specified in the annexed schedule, located in Kharzai, Vadala-Vadali, and Patonda villages of Chalisgaon Taluka, Jalgaon District, with a total acquisition area of 2.42 Hectares, shall be acquired and shall vest absolutely in the Central Government free from all encumbrances upon publication of this notification.

Full Text

REGD. No. D. L.-33004/99 The Gazette of India CG-MH-E-16072025-264720 EXTRAORDINARY PART II-Section 3-Sub-section (ii) PUBLISHED BY AUTHORITY No. 3171] NEW DELHI, WEDNESDAY, JULY 16, 2025/ASHADHA 25, 1947 MINISTRY OF RAILWAYS (Central Railway) NOTIFICATION Mumbai, the 15th July, 2025 Under clause 20E of the Railway (Amendment) Act 2008 S.O. 3241(E).— Whereas, by the notification of the Government of India in the Ministry of Railways (Railway Board), number, S.O 2450 € dated 25th June 2024 published in Gazette of India, Extraordinary, Part II, section 3 Sub-section (ii), dated the 25th June 2024 (hereinafter referred to as the said notification ) and issued under sub-section (1) of section 20A of the Railway Act, 1989 (24 of 1989) and Railway (Amendment) Act, 2008 (11 of 2008) (hereinafter referred to as the said Act), the Central Government declares its intention to acquire the land specified in the schedule annexed to the said notification for the purpose of execution, maintenance, management and operation of Special Railway Project, namely Manmad-Jalgaon 4th Line in the district of Jalgaon & Nashik in the State of Maharashtra. And whereas, the substance of the said notification was published in for Sub Divisional Officer/Pachora in daily newspapers namely "Dainik Sakaal” & “Dainik Deshonnati” Dated 24-04-2025 under sub section (4) of section 20A of the said Act; And whereas, objections were received. Competent Authority has heard the objections and orders have been passed in terms of Section D of the said act; And whereas, in pursuance of sub-section 20E of the said Act, the competent authority has submitted its report to the Central Government; Now therefore, upon receipt of the report of the Competent Authority and in exercise of the powers conferred by sub-section (1) of section 20E of the said Act, the Central Government hereby declares that the lands specified in the schedule annexed hereto shall be acquired for the aforesaid purpose; And further, in pursuance of sub-section (2) of section 20E of the said Act, the Central Government hereby declares that on publication of this notification in the official Gazette, the land specified in the schedule annexed hereto shall vest absolutely in the Central government free from all encumbrances. SCHEDULE Brief description of the land to be acquired, with or without structures, falling within the Special Railway Project of Manmad-Jalgaon 4th Line for 3 village in the District Jalgaon in the State of Maharashtra +----+----------------------------+----------+------------+-----------------------------------+-----------------+---------------------+------------------------+-------------------+ |S.N.|Land Acquisition Proposal No.|Village |Taluka |Land Owners Name according to 7/12 |Survey No./Gatt No.|Land Holding Method |Area as per 7/12 Extracts (Ha.)|Acquisition Area (Ha.)| +----+----------------------------+----------+------------+-----------------------------------+-----------------+---------------------+------------------------+-------------------+ | 1 | | | |Rajendra Bhaurao Ahire |71/1A+1B |I |0.72 |0.06 | | | | | |& Sagarbai Bhaurao Ahire | | | | | | 2 | | | |Surekha Eshwar Patil |80/1 |I |0.64 |0.11 | | 3 |34/2025 |Kharzai |Chalisgaon |Dhonddu Damu Patil |80/2 |I |0.64 |0.12 | | 4 | | | |Narayan Jagannath Patil, |80/3 |I |1.22 |0.25 | | | | | |Bhushan Jagannath Patil, | | | | | | | | | |Madhavrao Jagannath | | | | | | | | | |Patil | | | | | | | | | | | |Total |3.22 (Ha.) |0.54 (Ha.) | +----+----------------------------+----------+------------+-----------------------------------+-----------------+---------------------+------------------------+-------------------+ | 1 | | | |Kalabai Santosh Aamle, |91 |I |0.58 |0.020 | | | | | |Hanumant Santosh Aamle, | | | | | | | | | |Bhausaheb Santosh Aamle | | | | | | 2 |35/2025 |Vadala- |Chalisgaon |Shankar Devchand Patil |94 |I |0.13 |0.13 | | | |Vadali | |Kashinath Raghunath | | | | | | 3 | | | |Patil, Gorakhnath Patil, |95 |I |2.72 |0.65 | | | | | |Machhindranath | | | | | | | | | |Raghunath Patil | | | | | | | | | | | |Total |3.43 (Ha.) |0.80 (Ha.) | +----+----------------------------+----------+------------+-----------------------------------+-----------------+---------------------+------------------------+-------------------+ | 1 |36/2025 |Patonda |Chalisgaon |Jagannath Subhash Mali |772 |I |1.35 |0.41 | | 2 | | | |Ashok Khushal Mali, |778 |I |2.72 |0.67 | | | | | |Dharma Khushal Mali, | | | | | | | | | |Bhikan Khushal Mali | | | | | | | | | | | |Total |4.07 (Ha.) |1.08 (Ha.) | +----+----------------------------+----------+------------+-----------------------------------+-----------------+---------------------+------------------------+-------------------+ | | | | | | |Grand Total |10.72 (Ha.) |2.42 (Ha.) | +----+----------------------------+----------+------------+-----------------------------------+-----------------+---------------------+------------------------+-------------------+ [F. No. G197/Manmad-Jalgaon 4th line/Kharzai+2 Vlgs/July/20E] AVANISH KUMAR PANDEY, Chief Administrative Officer (Construction)

Never miss important gazettes

Create a free account to save gazettes, add notes, and get email alerts for keywords you care about.

Sign Up Free