Mumbai, the 30th October, 2025
Under clause 37A of the Railway (Amendment) Act 2008
S.O. 5106(E).—In exercise of the powers conferred by clause (37A) of Section 2 of The
Railways Act, 1989 (24 of 1989) (hereinafter referred to the Railway (Amendment) Act 2008
(No.11 of 2008), the Central Government hereby notifies “PH-53:- Provision of 2 Nos. 6 M wide
Foot Over Bridge with ramp at Kasbe Sukene Station for Kumbh Mela 2027 at Dist. – Nashik” as
a Railway project under Central Railway, under "Special Railway Project" for acquisition of land
in Nashik District in the State of Maharashtra, for providing national infrastructure for a public
purpose with effect from the date of publication of this notification in the Official Gazette.
[F. No. G197/Nashik Kumbh 2027/Kasbe Sukene/SRP/37A]
AVANISH KUMAR PANDEY, Chief Admn. Officer (Construction)