Full Text
REGD. No. D. L.-33004/99
The Gazette of India
CG-MH-E-10112025-267491
EXTRAORDINARY
PART II-Section 3-Sub-section (ii)
PUBLISHED BY AUTHORITY
No. 4901] NEW DELHI, FRIDAY, NOVEMBER 7, 2025/KARTIKA 16, 1947
MINISTRY OF RAILWAYS
(Central Railway)
NOTIFICATION
Mumbai, 27 October, 2025
Under clause 20E of the Railway (Amendment) Act 2008
THE GAZETTE OF INDIA : EXTRAORDINARY
[PART II-SEC. 3(ii)]
S.O. 5056(E).—Whereas, by the notification of the Government of India in the Ministry of Railways
(Railway Board), number, S.O 3651 (E) dated 6th August 2025 published in Gazette of India, Extraordinary, Part II,
section 3 Sub-section (ii), (hereinafter referred to as the said notification ) and issued under sub-section (1) of section
20A of the Railway Act, 1989 (24 of 1989) and Railway (Amendment) Act, 2008 (11 of 2008) (hereinafter referred to
the Railway (Amendment) Act 2008 (11 of 2008), the Central Government declares its intention to acquire the land
specified in the schedule annexed to the said notification for the purpose of execution, maintenance, management and
operation of Special Railway Project, namely “Ahmednagar-Beed-Parli-Vaijnath (261 Km.) New Line Maharashtra”
in the district of Beed in the State of Maharashtra.
And whereas, the substance of the said notification was published in for Deputy Collector Ja. Pra. Beed in
daily Marathi newspapers namely “Samarth Rajyog” & “Abhiman” on dated 14-10-2025 under sub section (4) of
section 20A of the said Act;
And whereas, no objections were received.
And whereas, in pursuance of sub-section 20E of the said Act, the competent authority has submitted its
report to the Central Government;
Now therefore, upon receipt of the report of the Competent Authority and in exercise of the powers
conferred by sub-section (1) of section 20E of the said Act, the Central Government hereby declares that the lands
specified in the schedule annexed hereto shall be acquired for the aforesaid purpose;
And further, in pursuance of sub-section (2) of section 20E of the said Act, the Central Government hereby declares
that on publication of this notification in the official Gazette, the land specified in the schedule annexed hereto shall
vest absolutely in the Central government free from all encumbrances.
SCHEDULE
Brief description of the land to be acquired, with or without structures, falling within the Special Railway
Project of Ahmednagar-Beed-Parli-Vaijnath (261 Km.) New Line Maharashtra for Ghatsavali village in the
District Beed in the State of Maharashtra
+-----+-------------+--------------+--------------+------------------------------------------------+------------------+--------------------+-----------------------------+--------------------------+------------+-------------------------------------------------------------+---------------------------------------------------------+
| S.N | LAQ | Village | Sub Division | Name Of Land Holder's as per 7/12 | Survey | Land Tenure | Total Area as per | Land to be | Bore/ | Construction | Trees |
| | Case No | Name | | | No/gat No | System | 7/12 (Ha) | Acquired (Ha) | Well | | |
+-----+-------------+--------------+--------------+------------------------------------------------+------------------+--------------------+-----------------------------+--------------------------+------------+-------------------------------------------------------------+---------------------------------------------------------+
| 1 | 01/2025 | Ghatsavali | Beed | Yogesh Bharat Phad | 18 Part | 1 | | 0.0039 | 0 | 39 sqm. Tin Shed | 0 |
| 2 | 01/2025 | Ghatsavali | Beed | Govind Dharmaraj Jadhav, Shrihari Vaijnath | 18 Part | 1 | | 0.0034 | 0 | 34 sqm. Tin Shed | 0 |
| | | | | Jadhav | | | | | | | |
| 3 | 01/2025 | Ghatsavali | Beed | Santosh Pralhad Bade | 18 Part | 1 | | 0.0042 | 0 | 33 sqm. Tin Shed | Gooseberry-1 |
| 4 | 01/2025 | Ghatsavali | Beed | Motiram Vitthal Borwadkar | 18 Part | 1 | | 0.0033 | 0 | 24 sqm. Tin Shed | 0 |
| 5 | 01/2025 | Ghatsavali | Beed | Bhausaheb Shankar Phad | 18 Part | 1 | | 0.0049 | Bore-1 | 20 sqm. Tin Shed | Mango-2 |
| 6 | 01/2025 | Ghatsavali | Beed | Appasaheb Shankar Phad | 18 Part | 1 | | 0.0048 | 0 | 23.75 sqm. RCC Construction | Mango-2 |
| 7 | 01/2025 | Ghatsavali | Beed | Muktabai Tukaram Phad | 18 Part | 1 | | 0.0046 | 0 | 46 sqm. Tin Shed | Custard Apple-2 Mango-4 |
| 8 | 01/2025 | Ghatsavali | Beed | Prabhakar Vithiba Nannaware | 18 Part | 1 | 3.83 | 0.0051 | Bore-1 | 51 sqm. RCC Construction | Black Berry-1 |
| 9 | 01/2025 | Ghatsavali | Beed | Arun Murlidhar Lande | 18 Part | 1 | | 0.0077 | Bore-1 | 64 sqm. RCC Construction | Mango-3 Coconut-1 |
| 10 | 01/2025 | Ghatsavali | Beed | Bhaskar Vachisht Phad | 18 Part | 1 | | 0.004 | 0 | 0 | 0 |
| 11 | 01/2025 | Ghatsavali | Beed | Baban Apparao Aage | 18 Part | 1 | | 0.0048 | 0 | 35 sqm. Tin Shed | 0 |
| 12 | 01/2025 | Ghatsavali | Beed | Gorakh Jivan | 18 Part | 1 | | 0.0028 | 0 | 0 | Jujube-3 |
| 13 | 01/2025 | Ghatsavali | Beed | Ganesh Eknath Phad | 18 Part | 1 | | 0.0049 | 0 | 26 sqm. Tin Shed & RCC Construction Home | Mango-2 |
| 14 | 01/2025 | Ghatsavali | Beed | Surekha Raghunath Phad | 18 Part | 1 | | 0.002 | 0 | 15 sqm. Tin Shed | 0 |
| 15 | 01/2025 | Ghatsavali | Beed | Pandit Rajaram Lande | 18 Part | 1 | | 0.0055 | Bore-1 | 6 sqm. Tin Shed & 19 sqm RCC Construction | 0 |
| 16 | 01/2025 | Ghatsavali | Beed | Shankar Sopanrao Phad | 18 Part | 1 | | 0.0056 | Bore-1 | 56 sqm. RCC Construction & Tin Shed | Mango-2 Gooseberry-1 |
| 17 | 01/2025 | Ghatsavali | Beed | Shakuntala Shivajirao Phad | 18 Part | 1 | | 0.0185 | 0 | 30 sqm. RCC Construction & 33 sqm. Tin Shed | Mango-2 Coconut-1 Gooseberry-1 |
| 18 | 01/2025 | Ghatsavali | Beed | Kalyan Abasaheb Lande | 18 Part | 1 | | 0.0055 | 0 | 0 | 0 |
| 19 | 01/2025 | Ghatsavali | Beed | Shrikisan Manik Lande | 18 Part | 1 | | 0.0054 | Bore-1 | 54 sqm. RCC Construction | Mango-1 Sapodilla-1 Jackfruit-2 |
| 20 | 01/2025 | Ghatsavali | Beed | Radhakisan Manikrao Phad | 18 Part | 1 | | 0.0055 | Bore-1 | 55 sqm. RCC Construction | Mango-4 |
| 21 | 01/2025 | Ghatsavali | Beed | Babn Appa Aage | 18 Part | 1 | | 0.0055 | 0 | 55 sqm. RCC Construction | 0 |
| 22 | 01/2025 | Ghatsavali | Beed | Surekha Raghunath Phad | 18 Part | 1 | | 0.0021 | 0 | 0 | 0 |
| 23 | 01/2025 | Ghatsavali | Beed | Salim Vazir Tamboli | 18 Part | 1 | | 0.0055 | Bore-1 | 49 sqm. RCC Construction | Mango-2 |
| 24 | 01/2025 | Ghatsavali | Beed | Arjun Maruti Andhare | 17 Part | 1 | 0.45 | 0.0077 | 0 | 0 | 0 |
| 25 | 01/2025 | Ghatsavali | Beed | Kiran Ratan Adwani | 17 Part | 1 | | 0.0037 | 0 | 0 | 0 |
| 26 | 01/2025 | Ghatsavali | Beed | Shinde Balbhim | 17 Part | 1 | | 0.0032 | 0 | 0 | 0 |
| 27 | 01/2025 | Ghatsavali | Beed | Lata Shivaji Andhare (TABA-Afsar Vazir Tamboli,| 16 Part | 1 | 0.40 | 0.0067 | Bore-1 | 46 sqm. RCC Construction | 0 |
| | | | | Ekbal Vazir Tamboli, Aslam Munshi Pathan) | | | | | | | |
| 28 | 01/2025 | Ghatsavali | Beed | Abhiman Rangnath Andhare, Ganesh Rangnath | 15 Part | 1 | 0.40 | 0.0072 | Bore-1 | 42 sqm. RCC Construction | 0 |
| | | | | Andhare, Prakash Rangnath Andhare, Balu Kaka | | | | | | | |
| | | | | Rangnath Andhare, Laxman Rangnath Andhare | | | | | | | |
| | | | | (TABA-Aslam Munshi Pathan, Sadiq Munshil | | | | | | | |
| | | | | Pathan, Jamal Abhir Pathan, Subhash Nagnath | | | | | | | |
| | | | | Jadhav) | | | | | | | |
| 29 | 01/2025 | Ghatsavali | Beed | Shivaji Panduran Khvtad & Other Six | 13 Part | 1 | 2.59 | 0.0034 | 0 | 5 sqm. RCC Construction | 0 |
| | | | | (TABA- Aslam Munshi Pathan, Sadiq Munshil | | | | | | | |
| | | | | Pathan, Jamal Abhir Pathan, Subhash Nagnath | | | | | | | |
| | | | | Jadhav) | | | | | | | |
| 30 | 01/2025 | Ghatsavali | Beed | Ashabai Aprugabai Jadhav | 11 Part | 1 | 0.82 | 0.0091 | 0 | 0 | 0 |
| 31 | 01/2025 | Ghatsavali | Beed | Ms. Samarth Oil Refinery LLHP, Prop. Partner- | 9 Part | 1 | 1.41 | 0.00255 | 0 | Protective wall, leaf shed, RCC wall, compound, iron gate, | 0 |
| | | | | Dattaprasad Kisan Tapadiya | | | | | | boiler, 12.00 Sqm.RCC Construction, House | |
| 32 | 01/2025 | Ghatsavali | Beed | Rurekha Ranjit Tangade | 9 Part | 1 | | 0.054 | 0 | 0 | Mango-5 Coconut-5 BlackBerry-2 SapodilLa-2 |
| 33 | 01/2025 | Ghatsavali | Beed | Kiran Ratan Adwani | 8 Part | 1 | 0.24 | 0.0032 | 0 | 0 | 0 |
| 34 | 01/2025 | Ghatsavali | Beed | Taramati Ratan Adwani Chauphule & others | 12 Part | 1 | | 0.0032 | 0 | 0 | Mango-2 |
| 35 | 01/2025 | Ghatsavali | Beed | Annasaheb Trimbak Khavtad, Shivaji Trimbak | 12 Part | 1 | 0.55 | 0.007 | 0 | 48.72 sqm. RCC Construction | Coconut-3 Mango-3 |
| | | | | Khavtad, Kedarnath Trimbak Khavtad | | | | | | | |
| 36 | 01/2025 | Ghatsavali | Beed | Rudranath Trimbak Khavtad, Jagannath Trimbak | 12 Part | 1 | | 0.004 | 0 | Dagadi Pavad | Mango-4 |
| | | | | Khavtad | | | | | | | |
| 37 | 01/2025 | Ghatsavali | Beed | Sharadabai Bhagwat Phad, Jagdish Bhagwat Phad | 3 Part | 1 | 1.6 | 0.055 | 0 | 0 | Balck Berry-3 Sapodila-5 Mango-7 Limboni-2 Coconut-3 |
| | | | | (Babasaheb Genu Salve, Sanket Namdev Tangade, | | | | | | | Jackfruit-1 |
| | | | | Vishnu Saduji Tangade, Bhagwat Sudaji Tangade, | | | | | | | |
| | | | | Eknath Saduji Tangade) | | | | | | | |
+-----+-------------+--------------+--------------+------------------------------------------------+------------------+--------------------+-----------------------------+--------------------------+------------+-------------------------------------------------------------+---------------------------------------------------------+
| Total | | | | | | | 12.29 H.a | 0.28945 H.a | | | |
+-----+-------------+--------------+--------------+------------------------------------------------+------------------+--------------------+-----------------------------+--------------------------+------------+-------------------------------------------------------------+---------------------------------------------------------+
[F. No. G197/ANG-Beed-Parli-Vaij/Ghatsavali Vlg/20E]
AVANISH KUMAR PANDEY, Chief Administrative Officer (Construction)
Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064
and Published by the Controller of Publications, Delhi-110054. GORAKHA NATH YADAVA
Digitally signed by GORAKHA NATH YADAVA
Date: 2025.11.10 16:01:57 +05'30'