Full Text
REGD. No. D. L.-33004/99
The Gazette of India
CG-KA-E-22072025-264881
EXTRAORDINARY
PART II—Section 3—Sub-section (ii)
PUBLISHED BY AUTHORITY
No. 3275]
NEW DELHI, MONDAY, JULY 21, 2025/ASHADHA 30, 1947
MINISTRY OF RAILWAYS
(SOUTH WESTERN RAILWAY CONSTRUCTION ORGANISATION)
NOTIFICATION
Bengaluru, the 21st July, 2025
S.O. 3348(E).— In exercise of the powers conferred by sub-Section (1) of Section 20A of the Railway Act,
1989 (24 of 1989) (hereinafter referred to as the said Act), the Ministry of Railways (South Western Railway,
Construction Organization Bengaluru Cantonment) after being satisfied that for the public purpose, the land, the brief
description of which has been given in the Schedule annexed hereto, is required for the execution of the Special
Railway Project, namely, "Londa - Vasco - Road Over Bridge in lieu of Level Crossing No. 17", in the State of Goa,
hereby declares its intention to acquire such land:
Any person interested in the said land may, within thirty days from the date of publication of this notification
in the official Gazette, raise objection to the acquisition and use of such land for the aforesaid purpose under sub-
section (1) of Section 20D of the said Act;
Every such objection shall be made to the 'Competent Authority', namely, Dy. Collecter & Sub
Divisional Officer, Quepem and Secretary (Revenue), South Goa as ‘Arbitrator' for the land acquisition process
required for the "Londa - Vasco - Road Over Bridge in lieu of Level Crossing No. 17" in writing and shall set out the
grounds thereof and the competent authority shall give the objector an opportunity of being heard, either in person or
by legal practitioner, and may, after hearing all such objections and after making such further enquiry, if any, as the
competent authority thinks necessary, by order, either allow or disallow the objections;
Any order made by the competent authority under sub-section (2) of Section 20D of the said Act shall be
final;
The land plans and other details of the land covered under this notification are available and can be inspected
by the interested person at the aforesaid Office of the competent authority.
SCHEDULE
+-------+-------------------+------------+------------------+------------------+
| Sl. No. | Name of the Village | Survey No. | Sub - Division No. | Area in Hectare |
+-------+-------------------+------------+------------------+------------------+
| 1. | Xelvona | 1 | 1 (P) | 0.2000 |
| 2. | Xelvona | 1 | 2 (P) | 0.0867 |
| 3. | Xelvona | 2 | 2 (P) | 0.6150 |
| 4. | Xelvona | 2 | 2- B (P) | 0.1155 |
| 5. | Xelvona | 2 | 2-E (P) | 0.1980 |
| 6. | Xelvona | 3 | 1 (P) | 0.0400 |
| 7. | Xelvona | 5 | 2 (P) | 0.1680 |
| 8. | Xelvona | 5 | 3 (P) | 0.1457 |
| 9. | Odar | 30 | 1 (P) | 0.2650 |
| 10. | Odar | 35 | 1 (P) | 0.6600 |
| 11. | Odar | 36 | 0 (P) | 0.8854 |
+-------+-------------------+------------+------------------+------------------+
| | | | Total | 3.3793 |
+-------+-------------------+------------+------------------+------------------+
[F.No.W.271/CN/BNC/2025-26/Land SRP/1219]
PARDEEP PURI, Chief Engineer-III/Construction