Full Text
8272 GI/202 4 (1)
EXTRAORDINARY
PART II —Section 3 —Sub-section ( i)
PUBLISHED BY AUTHORITY
No. 716] NEW DELHI, MONDAY , DECEMBER 23, 2024 /PAUSHA 2 , 194 6
CG-DL-E-23122024-259608
MINISTRY OF RAILWAYS
(Railway Board)
NOTIFICATION
New Delhi, the 23rd December , 2024
G.S.R 778(E).—In exercise of the powers conferred by clause (g) of sub -section (2) of section 60 read with
section 198 of the Railways Act, 1989 (24 of 1989), the Central Government hereby makes the following rules further
to amend the Indian Railways (Open Lines ) Genera l Rules, 1976 , namely: -
1. (1) These rules may be called th e Indian Railways (Open Lines) Genera l (Second Amendment) Rules, 2024.
(2) They shall come into force from the date of their publication in the Official Gazette.
2. In th e Indian Railways (Open Lines) Genera l Rules, 1976 , (hereinafter referred to as said rules), in rule 3.07, in
sub-rule (7), the following shall be inserted , namely: -
“Provided that, a colour light Distant signal may be permitted to be combined with the last Stop signal of a station in
rear or with an Intermediate Block signal or with a Stop signal protecting a level crossing with arrangements as above,
by the Sanctioning Authority (in case of item (a) below – Principal Chief Signal and Telecom Engineer o f the
concerned Zonal Railway, and in case of item (b), (c) and (d) below - General Manager of the concerned Railway) for
the purpose of -
(a) Interlocking of level crossings outside station limits;
(b) Double Distant signaling alongwith corresponding changes at adjacent stations without yard remodelling;
(c) Intermediate Block signaling except in section with Slip siding and Catch siding, alongwith corresponding
changes at adjacent stations without yard remodelling; and
(d) Automatic Block signaling except in section w ith Slip siding and Catch siding, alongwith corresponding
changes at adjacent stations without yard remodelling.”
3. In the said rules, in rule 3.26 , the following shall b e inserted , namely : -
“Provided that fixed signals can be brought into use if they have been passed by the Sanctioning Authority (in case of
item (a) below - Principal Chief Signal and Telecom Engineer of the concerned Zonal Railway, and in case of item
(b), (c) and (d) below - General Manager of the concerned Railway) as being sufficient to secure the safe working of
trains, for the purpose of -
(a) Interlocking of level crossings outside station limits;
(b) Double Distant signa ling alongwith corresponding changes at adjacent station s without yard remode lling;
(c) Intermediate Block signaling except in section with Slip siding and Catch siding, alongwith corresponding
changes at adjacent stations without yard remode lling; and
(d) Automatic Block signaling except in section with Slip siding and Catch siding, alongwith corresponding
changes at adjacent stations without yard remode lling.”
[F. No.2022/Safety(A&R)/19/26]
HITENDRA MALHOTRA , Member (O & BD) and Ex -Officio Sec y.
Note: -The principal rule s were published in the Gazette of India , Extrao rdinary, Part -II, Section 3, Sub -section (i)
vide number G.S.R. 445( E) dated 21st July, 1981 and last amended vide number G.S.R. 160(E)
dated 7th March , 202 4.
Uploaded by Dte. of Printing at Government of India Press, Ring R oad, Mayapuri, New Delhi -110064