Notification under Section 63 of the Electricity Act, 2003, notifying two inter-state transmission schemes to be implemented under the Tariff Based Competitive Bidding (TBCB) mode, along with their respective Bid Process Coordinators.

Detailed Summary

By notification S.O. 3545(E) dated 20th August 2024, the Ministry of Power, exercising powers under sub-para 3.2 of Para 3 of the Guidelines issued under Section 63 of the Electricity Act, 2003 (No. 36 of 2003), and on the recommendations of the 20th meeting of the National Committee on Transmission, notified two transmission schemes under the TBCB mode: (1) the Network Expansion scheme in the Western Region to cater to pumped storage potential near Talegaon (Pune), with REC Power Development and Consultancy Limited as Bid-Process Coordinator and a tentative implementation timeframe of 1st January 2027 (minimum 24 months from SPV transfer), comprising a new 2x1500 MVA 765/400 kV substation south of Kalamb with associated bus reactors, a LILO of the Pune-III-Boisar-II 765 kV double-circuit line at the South Kalamb substation (40 km route length), and installation of switchable 240 MVAr line reactors, and (2) the provision of ICT Augmentation and Bus Reactor at Bhuj-II Pooling Station, with PFC Consulting Limited as Bid-Process Coordinator and a tentative implementation timeframe of 21 months from SPV transfer, comprising augmentation of transformation capacity by 3x500 MVA 400/220 kV ICTs and 1x1500 MVA 765/400 kV ICT, installation of a 330 MVAr 765 kV bus reactor, and implementation of a 220 kV GIS line bay for Aditya Birla Renewables Subsidiary Limited (application no. 2200000321, 362 MW).

Full Text

REGD. No. D. L.-33004/99 The Gazette of India CG-DL-E-22082024-256561 EXTRAORDINARY PART II-Section 3-Sub-section (ii) PUBLISHED BY AUTHORITY No. 3229] NEW DELHI, WEDNESDAY, AUGUST 21, 2024/ SHRAVANA 30, 1946 MINISTRY OF POWER NOTIFICATION New Delhi, the 20th August, 2024 S.O. 3545(E).—In exercise of the powers conferred by sub-para 3.2 of Para 3 of the Guidelines circulated under Section 63 of the Electricity Act, 2003 (No. 36 of 2003), the Central Government, on the recommendations of 20th meeting of National Committee on Transmission, hereby notifies the following transmission schemes under TBCB mode, with details of respective Bid-Process Coordinators (BPCs): - +-----+---------------------------------------------------------------------------------------------------------------------------------------+ | Sl. | Name & Scope of the Transmission Scheme | | No. | | +=====+=======================================================================================================================================+ | 1. | Network Expansion scheme in Western Region to cater to Pumped storage potential near Talegaon (Pune) | | | | | | Tentative implementation timeframe : 01.01.2027 subject to minimum implementation schedule of 24 months from SPV transfer | | | BPC: REC Power Development and Consultancy Limited | | | Scope: | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | Sl. | Scope of the Transmission Scheme | Capacity (MVA) / Route Length (Km) | | | | No. | | | | | +=====+=====================================================================================================================+===================================================================================================================+ | | | 1. | Establishment 2x1500 MVA, 765/400 kV Substation near South of Kalamb with 2x330 MVAR, 765 kV bus reactor and 2x125 | 765/400 kV, 1500 MVA ICT – 2 Nos. (7x500 MVA single phase units including one spare ICT Unit) | | | | | MVAR, 420 kV bus reactor | | | | | | | 765 kV ICT bays – 2 Nos. | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | | Future provision (space for): | | | | | | ➤ 765/400 kV ICT along with bays- 10 Nos. (2 Nos. on Sec-I, 4 Nos. in Sec-II & 4 Nos. on Sec-III) | 400 kV ICT bays – 2 Nos. | | | | | ➤ 765 kV line bays along with switchable line reactors - 6 Nos. (4 Nos. on Sec-II & 2 Nos. on Sec-III) | 765 kV Line bays – 4 Nos. | | | | | ➤ 765 kV Bus Reactor along with bay: 4 Nos. (2 Nos. on Sec-II & 2 No. on Sec-III) | 330 MVAr, 765 kV bus reactor- 2 Nos. (7x110 MVAR single phase Reactors including one spare | | | | | | Unit for bus /line reactor) | | | | | ➤ 765 kV Sectionaliser: 2 -sets | 765 kV Bus reactor bay – 2 Nos. | | | | | ➤ 400 kV line bays along with switchable line reactors- 20 Nos. (6 Nos. on Sec-I, 6 Nos. on Sec- II & 8 Nos. on Sec-III) | 125 MVAr, 420 kV reactor- 2 Nos. | | | | | ➤ 400/220 kV ICT along with bays -4 Nos. (on 400 kV Sec-III: 2 Nos. on 220 kV Sec-I & 2 Nos. on 220 kV Sec-II) | 400 kV Reactor bay- 2 Nos. | | | | | ➤ 400 kV Bus Reactor along with bays: 4 Nos. (2 Nos. on Sec-II & 2 No. on Sec-III) | 400 kV line bays - 2 Nos. (for interconnection of PSP) | | | | | ➤ 400 kV Sectionalization bay: 2- set | | | | | | ➤ 220 kV line bays: 8 Nos. (4 Nos. on Sec-I & 4 Nos. on Sec-II) | | | | | | ➤ 220 kV Sectionalization bay: 1 set | | | | | | ➤ 220 kV BC and TBC: 2 Nos. | | | | | | ➤ Establishment of 6000 MW, ± 800 kV South Kalamb (HVDC) [LCC] terminal station (4x1500 MW) along with | | | | | | associated interconnections with 400 kV HVAC Switchyard (2x1500 MW on 400 kV Sec-I & 2x1500 MW on 400 kV Sec-II) | | | | | | & all associated equipment (incl. filters)/bus extension, etc. | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | 2. | LILO of Pune-III – Boisar-II 765 kV D/c line at South Kalamb S/s with associated bays at South Kalamb S/s | • LILO Route length: 40 km (160 ckm.) | | | | | | • The Pune-III – Boisar-II 765 kV D/c line is of Hexa Zebra configuration and LILO shall be of | | | | | | similar conductor configuration | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | 3. | Installation of 1x240 MVAr switchable line reactor on each ckt at South Kalamb end of Boisar-II – South Kalamb 765 | • 1x240 MVAr, 765 kV switchable line reactor - 2 Nos. | | | | | kV D/c line (formed after above LILO) | • Switching equipment for 765 kV line reactor – 2 Nos. | | | | | | • Spare Reactor (1-ph, 1x80 MVAr) unit at 765/400 kV South Kalamb S/s | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | 2. | Provision of ICT Augmentation & Bus Reactor at Bhuj-II PS | | | | Tentative implementation timeframe: 21 months from SPV transfer | | | | BPC: PFC Consulting Limited | | | | Scope: | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | Sl. | Scope of the Transmission Scheme | Capacity (MVA)/ Route Length (Km) | | | | No. | | | | | +=====+=====================================================================================================================+===================================================================================================================+ | | | 1. | Augmentation of transformation capacity at Bhuj-II PS (GIS) by 3x500 MVA, 400/220 kV ICT (7th, 8th & 9th) | 500 MVA, 400/220 kV ICTs: 3 No. | | | | | | 400 kV ICT bays: 3 No. (with addl. 3 Nos. for dia completion) | | | | | | 220 kV ICT bays: 3 No.. | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | 2. | Augmentation of transformation capacity at Bhuj-II PS (GIS) by 1x1500 MVA, 765/400 kV ICT (4th) | 1500 MVA, 765/400 kV ICT: 1 No. | | | | | | 765 kV ICT bay: 1 No. (with addl. 1 No. for dia completion) | | | | | | 400 kV ICT bay: Nil. (1 No. considered at Sl. No.1 above) | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | 3. | Installation of 1x330 MVAr 765 kV Bus Reactor (2nd) along-with associated bay | 330 MVAr, 765 kV Bus Reactor: 1 No. | | | | | | 765 kV BR bay: Nil (1 No. considered at Sl. No.2 above) | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | 4. | Implementation of 220 kV GIS line bay at Bhuj-II PS for Aditya Birla Renewables Subsidiary Limited (ABRSL) [Appln | 220 kV line bay – 1 No. (GIS) (Bus Sec-II) | | | | | No: 2200000321(362MW)] | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | 5. | Implementation of 220 kV GIS line bay at Bhuj-II PS for ACME Cleantech Solutions Private Limited (ACSPL) [Appln | 220 kV line bay – 1 No. (GIS) (Bus Sec-II) | | | | | No: 2200000382(350 MW)] | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | 6. | Implementation of 220 kV GIS line bay at Bhuj-II PS for ACME Cleantech Solutions Private Limited (ACSPL) [Appln | 220 kV line bay – 1 No. (GIS) (Bus Sec-II) | | | | | No: 2200000431(50 MW)] | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | 7. | Implementation of 220 kV GIS line bay at Bhuj-II PS for Avaada Energy Pvt Ltd. (AEPL) [Appl. No: 2200000444(100 | 220 kV line bay – 1 No. (GIS) (Bus Sec-II) | | | | | MW)] | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | 8. | Implementation of 220 kV GIS line bays at Bhuj-II PS for Adani Green Energy Thirty-Two Ltd. (AGE32L) [Appl. No: | 220 kV line bay – 1 No. (GIS) (Bus Sec-II) | | | | | 2200000514 (260.5MW)] | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | 9. | Implementation of 220 kV GIS line bays at Bhuj-II PS for Adani Renewable Energy Eight Ltd. (ARE8L) [Appl. No: | 220 kV line bay – 1 No. (GIS) (Bus Sec-II) | | | | | 2200000545 (115MW)] | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | 3. | Transmission System for evacuation of power from Mahan Energen Limited Generating Station in Madhya Pradesh | | | | Tentative Implementation Time: 30 months from SPV transfer | | | | BPC: PFC Consulting Limited | | | | Scope: | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | Sl. | Scope of the Transmission Scheme | Capacity/km | | | | No. | | | | | +=====+=====================================================================================================================+===================================================================================================================+ | | | 3. | Mahan (existing bus) – Rewa PS (PG) 400 kV D/c (Quad ACSR/AAAC/AL59 moose equivalent)line | 110 km. | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | 4. | 2 Nos. 400 kV bays at Rewa PS (PG) for termination of Mahan (existing bus) – Rewa PS (PG) 400 kV D/c line (Quad | 400 kV bays: 2 Nos. | | | | | ACSR/AAAC/AL59 moose equivalent)line | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | Note: | | | | • 2 Nos. 400 kV line bays at MEL (existing) shall be under the scope of MEL | | | | • POWERGRID to provide space at Rewa PS (PG) for scope at Sl. 2 | | +-----+---------------------------------------------------------------------------------------------------------------------------------------+ | 4. | Transmission system for Augmentation of transformation capacity at 765/400 kV Lakadia S/s (WRSS XXI(A) Transco Ltd) in Gujarat – Part B | | | Tentative Implementation Time: As per Detailed Scope | | | BPC: REC Power Development and Consultancy Limited | | | Scope: | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+-------------------+ | | | Sl. | Scope of the Transmission Scheme | Capacity/km | Time-frame | | | | No. | | | | | | +=====+=====================================================================================================================+===================================================================================================================+===================+ | | | 1. | Installation of 2x500 MVA, 400/220 kV ICTs (3rd & 4th) at Lakadia PS along with associated ICT bays | 400/220 kV, 1x500 MVA ICT – 2 Nos. | 18 months from | | | | | | • 400 kV ICT bay – 2 Nos. | date of allocation| | | | | | • 220 kV ICT bay – 2 Nos. (220 kV bus section-I) | to implementing | | | | | | | agency | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+-------------------+ | | | 2. | Implementation of 220 kV line bay at Lakadia PS for TEQ Green Power XVII Private Limited (TGPXVIIPL: 300 MW) | 220 kV line bay – 1 no. (220 kV bus section-I) | 18 months from | | | | | | | date of allocation| | | | | | | to implementing | | | | | | | agency | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+-------------------+ | | | 3. | Implementation of 220 kV line bay at Lakadia PS for Arcelor Mittal Nippon Steel India Limited (AMNSIL: 350 MW) | 220 kV line bay – 1 no. (220 kV bus section-I) | 18 months from | | | | | | | date of allocation| | | | | | | to implementing | | | | | | | agency | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+-------------------+ | | | 4. | Implementation of 220 kV line bay at Lakadia PS for Renew Solar (Shakti Eight) Private Limited (RS(S8)PL: 200 MW) | 220 kV line bay – 1 no. (220 kV bus section-I) | 30.09.2026 (as | | | | | | | per start date | | | | | | | requested by | | | | | | | applicant)* | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+-------------------+ | | | 5. | Creation of New 220 kV Bus Section-II at Lakadia PS along with 220 kV Sectionaliser arrangement between 220 kV | 220 kV Bus Sectionaliser - 1 set | 18 months from | | | | | Bus sec-I & Sec-II | BC – 1 No. | date of allocation| | | | | | • TBC-1 No. | to implementing | | | | | | | agency | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+-------------------+ | | | 6. | Augmentation of transformation capacity at Lakadia PS by 4x500 MVA, 400/220 kV ICTs (5th 6th, 7th & 8th) terminated | | | | | | | on new 220 kV Bus Section-II | | | | | | | 6a 2x500MVA ICTs (5th & 6th) | • 500 MVA, 400/220 kV ICTs: 2 No. | 18 months from | | | | | | • 400 kV ICT bays: 2 Nos. | date of allocation| | | | | | • 220 kV ICT bays: 2 No. (New Bus Section-II) | to implementing | | | | | | | agency | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+-------------------+ | | | 6b | 1x500MVA ICT (7th) | • 500 MVA, 400/220 kV ICT: 1 No. | 31.12.2026 | | | | | | • 400 kV ICT bay: 1 No. | | | | | | | • 220 kV ICT bays: 1 No. (New Bus Section-II) | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+-------------------+ | | | 6c | 1x500MVA ICT (8th) | • 500 MVA, 400/220 kV ICT: 1 No. | 30.06.2027 | | | | | | • 400 kV ICT bay: 1 No. | | | | | | | • 220 kV ICT bays: 1 No. (New Bus Section-II) | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+-------------------+ | | | 7. | Implementation of 220 kV line bay at Lakadia PS for Juniper Green Energy Private Limited (JGEPL) (Appl. No. | 220 kV line bay – 1 No. (New Bus Section-II) | 30.06.2027 (as | | | | | 2200000376: 300 MW) | | per start date | | | | | | | requested by | | | | | | | applicant) | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+-------------------+ | | | 8. | Implementation of 220 kV line bay at Lakadia PS for TEQ Green Power XVI Pvt. Ltd. (TGPXVIPL) (Appl. No. | 220 kV line bay – 1 No. (New Bus Section-II) | 30.09.2026 (as | | | | | 2200000398: 76MW) | | per start date | | | | | | | requested by | | | | | | | applicant)* | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+-------------------+ | | | 9. | Implementation of 220 kV line bay at Lakadia PS for Ganeko Solar Pvt. Ltd. (GSPL) (Appl. No. 2200000458: 290 MW) | 220 kV line bay – 1 No. (New Bus Section-II) | 31.12.2026 (as | | | | | | | per start date | | | | | | | requested by | | | | | | | applicant)* | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+-------------------+ | | | 10. | Implementation of 220 kV line bay at Lakadia PS for Juniper Green Energy Private Limited (JGEPL) (Appl. No. | 220 kV line bay – 1 No. (New Bus Section-II) | 31.03.2027 (as | | | | | 2200000500: 150 MW) | | per start date | | | | | | | requested by | | | | | | | applicant) | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+-------------------+ | | | 11. | Implementation of 220 kV line bay at Lakadia PS for Serentica Renewables India Private Limited (SRIPL) (Appl. No. | 220 kV line bay – 1 No. (New Bus Section-II) | 30.06.2026* | | | | | 2200000610: 200 MW) | | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+-------------------+ | | | 12. | Implementation of 220 kV line bay at Lakadia PS for RDS Solar Park Private Limited (RDSSPPL) (Appl. No. | 220 kV line bay – 1 No. (New Bus Section-II) | 30.06.2026* | | | | | 2200000639: 350 MW) | | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+-------------------+ | | | 13. | Implementation of 220 kV line bay at Lakadia PS for Percentum Renewables Private Limited (PRPL) (Appl. No. | 220 kV line bay – 1 No. (New Bus Section-II) | 30.06.2026* | | | | | 2200000673: 148 MW) | | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+-------------------+ | | | 14. | Installation of 1x330 MVAr 765 kV Bus Reactor (2nd) along-with associated bay | 330 MVAr, 765 kV Bus Reactor: 1 No. | 18 months from | | | | | | • 765 kV BR bay: 1 No. | date of allocation| | | | | | | to implementing | | | | | | | agency | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+-------------------+ | | | 15. | Augmentation of transformation capacity at Lakadia PS by 1x1500 MVA, 765/400 kV ICTs (3rd) | 1500 MVA, 765/400 kV ICT: 1 No. | 18 months from | | | | | | • 400 kV ICT bay: 1 No. | date of allocation| | | | | | • 765 kV ICT bay: 1 No. | to implementing | | | | | | | agency | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+-------------------+ | | *subject to minimum schedule of 18 months from the date of allocation to implementing agency. | | | | | Note: | | | | | TSP of Lakadia S/s (WRSS XXI(A) Transco Ltd.) shall provide space for above augmentation works at Lakadia S/s | | | +-----+---------------------------------------------------------------------------------------------------------------------------------------+ | 5. | Transmission system for evacuation of RE power from Raghanesda area of Gujarat – 3 GW under Phase-I | | | Tentative Implementation Time: 30 months from SPV transfer | | | BPC: PFC Consulting Limited | | | Scope: | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | Sl. | Scope of the Transmission Scheme | Capacity/km | | | | No. | | | | | +=====+=====================================================================================================================+===================================================================================================================+ | | | 1. | Establishment of 3x1500 MVA, 765/400 kV Substation near Raghanesda (GIS) with 2x330 MVAR, 765 kV bus reactor and | • 765/400 kV, 1500 MVA ICT – 3 Nos. (10x500 MVA single phase units including one spare ICT Unit) | | | | | 2x125 MVAR, 420 kV bus reactor | • 765 kV ICT bays - 3 Nos. | | | | | | • 400 kV ICT bays - 3 Nos. | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | | Future provision (space for): | | | | | | ➤ 765/400 kV ICT along with bays- 5 Nos. (1 No. in Sec-I & 4 Nos. on Sec-II) | • 765 kV Line bays – 2 Nos. | | | | | ➤ 765 kV line bays along with switchable line reactors - 10 Nos. (4 Nos. on Sec-I & 6 Nos. on Sec-II) | • 1x330 MVAr, 765 kV bus reactor- 2 Nos. (7x110 MVAR single phase Reactors including one spare Unit for bus /line reactor) | | | | | ➤ 765 kV Bus Reactor along with bay: 2 Nos. (on Sec-II) | • 765 kV Bus reactor bay – 2 Nos. | | | | | ➤ 765 kV Sectionaliser: 1 -set | • 125 MVAr, 420 kV reactor- 2 Nos. | | | | | ➤ 400 kV line bays along with switchable line reactors- 12 Nos. (4 Nos. on Sec-I & 8 Nos. on Sec-II) | • 400 kV Reactor bay- 2 Nos. | | | | | ➤ 400/220 kV ICT along with bays - 8 Nos. (4 Nos. on each 400 kV Section) | • 400 kV line bays - 4 Nos. (for interconnection of RE Projects) | | | | | ➤ 400 kV Bus Reactor along with bays: 2 Nos. (Sec-II) | | | | | | ➤ 400 kV Sectionalization bay: 1- set | | | | | | ➤ 220 kV line bays: 12 Nos. (6 Nos. on each 220 kV Section) | | | | | | ➤ 220 kV Sectionalization bay: 1 set | | | | | | ➤ 220 kV BC: 1 No. | | | | | | ➤ Establishment of 6000 MW, ± 800 kV Raghanesda (HVDC) [LCC] terminal station (4x1500 MW) along with | | | | | | associated interconnections with 400 kV HVAC Switchyard & all associated equipment (incl. filters)/bus extension, etc. | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | 2. | Raghanesda (GIS) – Banaskantha (PG) 765 kV D/c line | 95 km | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | 3. | 2 Nos. 765 kV line bays at Banaskantha (PG) S/s | 765 kV line bays – 2 Nos. | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | Note: | | | | • TSP of Banaskantha S/s (POWERGRID) shall provide space for scope at Sl. 3 above. | | +-----+---------------------------------------------------------------------------------------------------------------------------------------+ | 6. | Transmission scheme for evacuation of power from Ratle HEP (850 MW) & Kiru HEP (624 MW): Part-A | | | Tentative Implementation Time: 24 months from SPV transfer | | | BPC: REC Power Development and Consultancy Limited | | | Scope: | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | SI. | Description of Transmission Element | Scope of work (Type of Substation/Conductor capacity/km/no. of bays etc.) | | | | No. | | | | | +=====+=====================================================================================================================+===================================================================================================================+ | | | 1 | LILO of 400 kV Kishenpur- Dulhasti line (Twin) at Kishtwar S/s along with associated bays at Kishtwar S/s | LILO Length- 3km | | | | | | • 400 kV Kishenpur -Kishtwar (LILO section) shall be on Twin HTLS (with minimum 2100 MVA capacity) configuration | | | | | | • 400 kV Dulhasti -Kishtwar (LILO section) shall be on Twin Zebra configuration | | | | | | • 400 kV line bays at Kishtwar – 2 Nos. (GIS) (line bays at Kishtwar S/s end shall be rated accordingly) | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | 2 | 400 kV Kishenpur-Samba D/c line (Quad) (only one circuit is to be terminated at Kishenpur utilizing 1 no. of 400 kV | Length -36 km (Quad) | | | | | vacated line bay at Kishenur S/s (formed with bypassing of one ckt of 400 kV Kishtwar Kishenpur 400 kV D/c line | | | | | | (Quad) at Kishenpur) while second circuit would be connected to bypassed circuit of 400 kV Kishtwar – Kishenpur | | | | | | line (Quad)) | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | 3 | Bypassing of one ckt of 400 kV Kishtwar Kishenpur 400 kV D/c line (Quad) at Kishenpur and connecting it with one of | | | | | | the circuit of Kishenpur-Samba 400 kV D/c line(Quad), thus forming 400 kV Kishtwar - Samba (Quad) direct line (one | | | | | | ckt) | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | 4 | 1x80 MVAr Switchable line reactor at Samba end of 400 kV Kishtwar-Samba 400 kV line-165 km (Quad) [formed after | • 420 kV, 80 MVAr switchable line reactors at Samba S/s end- 1 Nos. | | | | | bypassing of 400 kV Kishtwar Kishenpur line (Quad) at Kishenpur and connecting it with one of the circuit of | • Switching equipment for 420 kV, 80 MVAr switchable line reactors at Samba S/s end 1 no | | | | | Kishenpur-Samba_400 kV D/c line(Quad)) | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | 5 | 1x63 MVAr Switchable line reactor on each ckt at Jallandhar end of Kishenpur– Jalandhar D/c direct line -171km(Twin)| • 420 kV, 63 MVAr switchable line reactors at Jallandhar S/s end- 2 Nos. | | | | | (formed after bypassing both ckts of 400 kV Kishenpur Samba D/c line (Twin) & 400 kV Samba Jalandhar D/c line | • Switching equipment for 420 kV, 63 MVAr switchable line reactors at Jallandhar S/s end – 2 no | | | | | (Twin) at Samba and connecting them together to form Kishenpur– Jalandhar D/c direct line (Twin)) | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | 6 | 400 kV Samba- Jalandhar D/c line(Quad) (only one circuit is to be terminated at Jalandhar utilizing 1 no. of 400 kV | Line Length -145 km | | | | | vacated line bay at Jalandhar S/s (formed with bypassing of 400 kV Jalandhar Nakodar line (Quad) at Jalandhar) | | | | | | while second circuit would be connected to bypassed circuit of Jalandhar -Nakodar 400 kV line (Quad)) | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | 7 | 1x80 MVAr Switchable line reactor at Samba end of Samba -Nakodar direct line (Quad) (187km) formed after bypassing | • 420 kV, 80 MVAr switchable line reactors at Samba S/s end- 1 no. | | | | | of 400 kV Jalandhar Nakodar line (Quad) at Jalandhar and connecting it with one of the circuit of Samba-Jalandhar | • Switching equipment for 420 kV, 80 MVAr switchable line reactors at Samba S/s end1 no. | | | | | 400 kV D/c line(Quad Moose), thus forming Samba Nakodar line (Quad) | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | | 8 | Bypassing 400 kV Jalandhar Nakodar line (Quad) at Jalandhar and connecting it with one of the circuit of | | | | | | Samba-Jalandhar 400 kV D/c line(Quad Moose), thus forming 400 kV Samba Nakodar (Quad) direct line | | | | +-----+---------------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+ | | Note: | | | | • M/s Sterlite shall provide space for 2 Nos. of 400 kV line bays (GIS) at Kishtwar S/s | | | | • M/s POWERGRID shall provide space for 1 no. 80 MVAr Switchable line reactor (along with switching equipment) at Samba end | | | | of 400 kV Kishtwar-Samba 400 kV line | | | | • M/s POWERGRID shall provide space for 2 Nos. 63 MVAr Switchable line reactor (along with switching equipment) at | | | | Jallandhar end of Kishenpur– Jalandhar D/c direct line (on each ckt) | | | | • M/s POWERGRID shall provide space for 1 no. 80 MVAr Switchable line reactor (along with switching equipment) at Samba end | | | | of Samba –Nakodar direct line | | +-----+---------------------------------------------------------------------------------------------------------------------------------------+ | 7. | Transmission system strengthening at Kurnool-III PS for integration of additional RE generation projects | | | Tentative Implementation Time: | | | i. Package A-24 months | | | ii. Package B - progressively from June'25 to Dec'27 | | | iii. Package C - 24 months | | | BPC: PFC Consulting Limited | | | Scope: | | | +--------+-----------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+------------+ | | | Pack | Scope of the Transmission Scheme | Capacity/km | Schedule | | | | age | | | | | | +========+=================================================================================================================+===================================================================================================================+============+ | | | A | Augmentation of transformation capacity by 3x1500 MVA, 765/400 kV ICTs at Kurnool-III PS | • 3x1500 MVA, 765/400 kV ICT | 24 months | | | | | | • 765 kV ICT bay – 3 Nos. | | | | | | | • 400 kV ICT bay – 3 Nos. | | | | | | | • 400 kV Bus Sectionaliser - 1 Set | | | | | | Kurnool-III PS – Chilakaluripeta 765 kV D/c line with 240 MVAr switchable line reactors at both ends | ~ 260 km | | | | | | | • 765 kV line bays – 2 Nos. (at Kurnool-III PS) | | | | | | | • 765 kV line bays – 2 Nos. (at Chilakaluripeta) | | | | | | | • 765 kV, 240 MVAr SLR at Kurnool-III PS-2 Nos. (6x80 MVAr units) | | | | | | | • 765 kV, 240 MVAr SLR at Chilakaluripeta – te2 Nos. (6x80 MVAr units) | | | | +--------+-----------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+------------+ | | | B | 2 Nos. of 400 kV line bays at Kurnool-III PS for termination of dedicated transmission line of M/s Adani | • 400 kV line bays - 1 Nos. | 30.06.26 | | | | | Renewable Energy Forty Two Ltd. | • 400 kV line bays – 1 Nos. | 24 months | | | | | 4 Nos. of 400 kV line bay at Kurnool-III PS for termination of dedicated transmission lines of M/s Indosol Solar | • 400 kV line bays – 2 Nos. | 31.03.27 | | | | | Pvt. Ltd. | • 400 kV line bays – 2 Nos. | 31.12.27 | | | | | 2 Nos. of 400 kV line bays at Kurnool-III PS for termination of dedicated transmission line of M/s Adani | | | | | | | Renewable Energy Fifty One Ltd. | | | | | +--------+-----------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+------------+ | | | C | Augmentation of 1x1500 MVA 765/400 kV ICT (7th) at Kurnool-II PS | • 1x1500 MVA, 765/400 kV ICT | 24 months | | | | | | • 765 kV ICT bay – 1 Nos. | | | | | | | • 400 kV ICT bay – 1 Nos. | | | | +--------+-----------------------------------------------------------------------------------------------------------------+-------------------------------------------------------------------------------------------------------------------+------------+ | 2. | The appointment of the Bid Process Coordinator is subject to the conditions laid down in the Guidelines issued by Ministry of Power in this regard, amended from time to time. | | | [F. No. 15/3/2018- Trans- Part(4)] | | | NAOREM INDRAKUMAR SINGH, Under Secy. (Transmission) | | | Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064 and Published by the Controller of Publications, Delhi-110054. | +-----+---------------------------------------------------------------------------------------------------------------------------------------+

Never miss important gazettes

Create a free account to save gazettes, add notes, and get email alerts for keywords you care about.

Sign Up Free