No. 687]
NEW DELHI, THURSDAY, FEBRUARY 12, 2026/MAGHA 23, 1947
New Delhi, 11 February, 2026
1040 GI/2026
2
THE GAZETTE OF INDIA : EXTRAORDINARY
[PART II-SEC. 3(ii)]
3
4
THE GAZETTE OF INDIA : EXTRAORDINARY
[PART II-SEC. 3(ii)]
5
6
THE GAZETTE OF INDIA : EXTRAORDINARY
[PART II-SEC. 3(ii)]
7
8
THE GAZETTE OF INDIA : EXTRAORDINARY
[PART II-SEC. 3(ii)]
9
10
THE GAZETTE OF INDIA : EXTRAORDINARY
[PART II-SEC. 3(ii)]
11
12
THE GAZETTE OF INDIA : EXTRAORDINARY
[PART II-SEC. 3(ii)]
13
14
THE GAZETTE OF INDIA : EXTRAORDINARY
[PART II-SEC. 3(ii)]
MINISTRY OF POWER
NOTIFICATION
New Delhi, the 11th February, 2026
S.O. 725(E). In exercise of the powers conferred by sub-para 3.2 of Para 3 of the Guidelines circulated
under Section 63 of the Electricity Act, 2003 (No. 36 of 2003), the Central Government on the recommendations of
37th meeting of National Committee on Transmission, hereby notifies the following transmission schemes under
TBCB mode, with details of respective Bid-Process Coordinator (BPC): -
1. Augmentation at Bhadla-III, Ramgarh PS and Kanpur (PG)
Tentative implementation timeframe: 20.01.2029
BPC: REC Power Development and Consultancy Limited
Scope:
SI. No. | Scope of the Transmission Scheme | Item Description
1. | Augmentation of 400/220 kV, 5x500 MVA (6th to 10th) ICTs at 765/400/220kV Bhadla-III PS | • 500 MVA, 400/220 kV ICT - 5 nos. (4 nos. ICTs in 220kV Sec-2 (6th to 9th) and 1 no. ICT in 220kV Sec-1 (10th) | • 400kV ICT bays – 5 nos. | • 220 kV ICT bay – 4 nos. | • 220 kV ICT (GIS) bay – 1 no. (for 10th ICT) | • 220kV GIS bus duct/Cable for interconnection of 220 kV side of ICT (10th) to 220kV GIS bay (Section-1)
2. | Implementation of 5 nos. of 220kV line bays at 765/400/220kV Bhadla-III PS. | • 220kV line bay - 5 nos.
3. | Implementation of 1 no. of 400kV line bay at 765/400/220kV Bhadla-III PS. | • 400kV line bay - 1 no.
4. | Implementation of 2 sets 400kV sectionlizer bay at 765/400/220kV Bhadla-III PS | • 400kV sectionlizer bay – 2 sets
5. | Augmentation of 765/400 kV, 2x1500 MVA (3rd & 4th) ICTs at 765/400kV Ramgarh PS | • 1500 MVA, 765/400 kV ICT - 2 nos. | • 765kV ICT bays – 2 nos. | • 400 kV ICT bay – 2 nos.
6. | Augmentation of 400/220 kV, 2x500 MVA (3rd & 4th) ICTs at 765/400kV Ramgarh PS | • 500 MVA, 400/220 kV ICT - 2 nos. | • 400kV ICT bays – 2 nos. | • 220 kV ICT bay – 2 nos.
7. | Implementation of 2 nos. of 220kV line bays at 765/400kV Ramgarh PS | • 220kV line bay - 2 nos.
8. | Implementation of 1 no. of 400kV line bay at 765/400kV Ramgarh PS | • 400kV line bay – 1 no.
9. | Augmentation of 765/400 kV, 1x1500 MVA (3rd) ICT at 765/400kV Kanpur (PG) substation | • 1500 MVA(3x500MVA), 765/400 kV ICT - 1 no. | • 765kV ICT bay (GIS) including completion of diameter. | • 400 kV ICT bay (GIS) in existing spare bay | • All associated GIS duct with terminations.
2. Transmission System for integration of Ananthpuram-III PS REZ Phase-I (3GW)
Tentative implementation timeframe: 30 Months
BPC: Power Finance Corporation Limited (PFC)
15
Scope:
SI. No. | Scope of the Transmission Scheme | Capacity /km
1 | Establishment of 3x1500 MVA, 765/400 kV and 7x500 MVA, 400/220kV Ananthapuram-III Pooling Station near Urvakonda / Beluguppa / Kalyandurg areas in Anantapur district along with 2x330 MVAr (765 kV) bus reactors at Ananthapuram-III PS with provision of two (2) sections of 4500 MVA each at 400kV level | • 765/400kV, 1500 MVA, ICTS – 3 Nos. (10x500 MVA incl. 1 spare unit) | • 765kV ICT bays - 3 Nos. | • 400kV ICT bays - 3 Nos. | • 765kV line bays - 2 Nos. (at Ananthapuram-III PS for termination of Ananthapuram-III – Krishnagiri 765kV D/c line) | • 765 kV, 330 MVAr Bus Reactor – 2 Nos. (7x110 MVAr inc. 1 switchable spare unit for both bus reactor and line reactor) | • 765 kV Bus Reactor bays – 2 Nos. | • 400/220kV, 500 MVA, ICTs – 7 Nos. | • 400kV ICT bays – 7 Nos. | • 220kV ICT bays – 7 Nos. | • 220kV line bays – 10 Nos. | • 220kV Bus Sectionalizer: 1 set | • 220 kV Bus Coupler (BC) Bay – 2 Nos. | 220 kV Transfer Bus Coupler (TBC) Bay – 2 Nos.
Future Space Provisions: |
• 765/400kV, 1500 MVA, ICTs - 3 Nos. |
• 765kV ICT bays - 3 Nos. |
• 400kV ICT bays - 3 Nos. |
• 400/220kV, 500 MVA, ICTs – 7 Nos. |
• 400kV ICT bays – 7 Nos. |
• 220kV ICT bays – 7 Nos. |
• 765kV line bays – 12 Nos. (with provision for SLR) |
• 400kV line bays – 11 Nos. (with provision for SLR) |
• 220kV line bays – 15 Nos. |
• 220kV Bus Sectionalizer : 2 sets |
• 220 kV Bus Coupler (BC) Bay – 2 nos. |
• 220 kV Transfer Bus Coupler (TBC) Bay - 2 nos. |
• 400kV Bus Sectionalizer: 1 set |
2 | ± 300 MVAr STATCOM at Ananthapuram-III PS | • 400kV bay – 1 no. | • ± 300 MVAr STATCOM - 1 set | ~ 140 km
3 | Ananthapuram-III – Krishnagiri 765 kV D/c line with 240 MVAr SLR (convertible) at Ananthapuram-III end on both circuits | • 765 kV line bays – 2 Nos. (at Krishnagiri) | • 765 kV, 240 MVAr SLR at Ananthapuram-III PS – 2 Nos. (7x80 MVAr inc. 1 switchable spare unit) Switching Equipment for 765 kV SLR at Ananthapuram-III PS – 2 Nos.
3. Transmission system for Integration of Power from RE Projects in Jam Khambhaliya REZ in Gujarat - Phase II (5500MW) and Jamnagar Phase-I (1000 MW)
Tentative implementation timeframe: 31.03.2030
BPC: Power Finance Corporation Limited (PFC)
Scope:
SI. No. | Scope of the Transmission Scheme | Capacity /km
1. | Establishment 4x1500 MVA, 765/400 kV & 10x500MVA, 400/220kV Substation near Kalyanpur (GIS) with 2x330 MVAR, 765 kV bus reactor and 2x125 MVAR, 420 kV bus reactor | • 765/400 kV, 1500 MVA ICT – 4 Nos. (13x500 MVA single phase units including one spare ICT Unit) (3 on Sec-I & 1 on Sec-II) | • 400/220kV, 500MVA ICT – 10 Nos. (5 on Sec-I & 5 on Sec-II) | • 765 kV ICT bays - 4 Nos. | • 400 kV ICT bays – 14 Nos. | • 220kV ICT bays - 10 Nos. | • 765 kV Line bays – 4 Nos. (2 on Sec-I & 2 on
Future provision (space for): |
➤ 765/400 kV, 1500MVA ICT along with bays- 2 Nos. (on Sec-II) |
➤ 765 kV line bays along with switchable line reactors – 8 Nos. (4 Nos. on Sec-I & 4 Nos. on Sec-II) |
➤ 765 kV, 330MVAr Bus Reactor |
16
THE GAZETTE OF INDIA: EXTRAORDINARY
[PART II-SEC. 3(ii)]
along with bay: 2 Nos. (1 on Sec-I & 1 on Sec-II) | Sec-II)
• 400 kV line bays along with switchable line reactors- 12 Nos. (4 Nos. on Sec-I & 8 Nos. on Sec-II) | • 765 kV Sectionaliser bay: 1 -set
• 420 kV, 125MVAr Bus Reactor along with bays: 2 Nos. (1 on Sec-I & 1 on Sec-II) | • 400 kV Sectionalization bay: 1- set
• 220 kV line bays: 3 No. on Sec-I & 3 Nos. on Section-II | • 220 kV Sectionalization bay: 1 set
• Establishment of 6000 MW, ± 800 kV Kalyanpur (GIS) (HVDC) [LCC] terminal station (4x1500 MW) along with associated interconnections with 400 kV HVAC Switchyard & all associated equipment (incl. filters)/bus extension, etc. (2x1500MW Poles on each 400kV bus section) | • 1x330 MVAr, 765 kV bus reactor- 2 Nos. (7x110 MVAR single phase Reactors including one spare Unit for bus /line reactors) (1 on Sec-I & 1 on Sec-II)
• +400MVAr STATCOM with 400kV bay - 2 No. (1 on Sec-I & 1 on Sec-II) | • 765 kV Bus reactor bay – 2 Nos.
• 125 MVAr, 420 kV reactor- 2 Nos. (1 on Sec-I & 1 on Sec-II)
• 400 kV Reactor bay- 2 Nos.
• 220kV BC Bay-2 No.
• 400 kV line bay - 1 No. (for interconnection of RE Project at Sec-I)
• 220kV line bays - 12 Nos. (for interconnection of RE Projects, 6 on Sec-I & 6 on Sec-II)
2. | Kalyanpur (GIS) – Jamnagar (GIS) 765 kV D/c line | 95 km
3. | 2 Nos. 765 kV line bays at Jamnagar (GIS) S/s | 765 kV line bays – 2 Nos. (GIS)
4. | Kalyanpur (GIS) – Saurashtra (near Rajkot) (GETCO) 765 kV D/c line | 225km.
5. | 330MVAr Switchable line reactors on each circuit at Kalyanpur (GIS) end of Kalyanpur (GIS) - Saurashtra (near Rajkot) (GETCO) 765 kV D/c line (with NGR bypass arrangement) | • 330 MVAr, 765 kV switchable line reactor- 2 Nos. | • Switching equipment for 765 kV line reactor- 2 Nos.
6. | 2 Nos. 765 kV line bays at Saurashtra (near Rajkot) (GETCO) S/s | • 765 kV line bays – 2 Nos.
7. | Installation of Synchronous Condenser (+300/-200MVAr) (Minimum) & Short circuit contribution at PCC of 1200MVA (Minimum) at Kalyanpur (GIS)- 2 Nos. Value of Inertia (MW-s) shall be defined in RfP document. | • Synchronous Condenser along with associated 400kV Bay-2 Nos. (one on each Sec-I & II)
8. | Creation of 220kV switchyard along with Installation of 3x500MVA, 400/220kV ICTS at Jamnagar (GIS) S/s | • Creation of 220kV Bus Section-I | • 220kV BC Bay – 1 No. | • 400/220 kV, 500 MVA ICT – 3 Nos. (on 400kV & 220kV Sec-I) | • 400 kV ICT bays – 1 No. (2 Nos. ICTs to be terminated in 2 nos. GIS bays being implemented as part of Diameter completion at Jamnagar S/s under "Network Expansion scheme in Gujarat for drawl of about 3.6 GW load under Phase-I in Jamnagar area” scheme) | • 220kV ICT bays - 3 Nos.
9. | 4 nos. 220kV line bays for RE interconnection | 220kV line bays – 4 Nos.
Note: |
➤ TSP of Jamnagar S/s shall provide space for above scope of work at Sl. 3, 8 & 9 on free of cost |
17
basis
➤ GETCO shall provide space for above scope of work at Sl. 6 on free of cost basis
➤ Bay(s) required for completion of diameter (GIS) in one-and-half breaker scheme shall also be executed by the TSP.
➤ Above Syncons (at Sl. 7) shall be considered as ‘transmission asset' similar to STATCOM & SVC for its tariff mechanism.
4.. Transmission system for Integration of Power from RE Projects in Lakadia REZ in Gujarat-Phase II (7500MW)
Tentative implementation timeframe: 36 Months
BPC: REC Power Development and Consultancy Limited
Scope:
Sl. No. | Scope of the Transmission Scheme | Capacity/km
1. | Establishment of 765/400 kV, 6x1500MVA & 10x500MVA, 400/220kV Lakadia-II (Near Chitrod) with 2x330 MVAR 765kV bus reactor and 2x125 MVAR 400kV bus reactor. [765kV, 400kV & 220kV levels to be established in two sections with Sectionaliser arrangement. The 220kV Sectionaliser shall be kept normally open and may be closed under contingency condition. The 400kV and 765kV Sectionaliser shall be kept normally closed. The bus operation may be reviewed after proposed HVDC implementation as per requirement of Grid operator. (3x1500MVA 765/400kV ICTS, 5x500MVA 400/220kV ICTs, 1x330MVA 765kV BR & 1x125MVAr 420kV BR shall be on Sec-I & 3x1500MVA 765/400kV ICTS, 5x500MVA 400/220kV ICTS, 1x330MVA 765kV BR & 1x125MVAr 420kV BR shall be on Sec-II)] | • 765/400 kV, 1500 MVA ICT – 6 Nos. (19x500 MVA single phase units including one spare ICT Unit) | • 400/220 kV ICTs - 10 Nos. (5 on Sec-I & 5 on Sec-II) | • 765 kV ICT bays – 6 Nos. | • 400 kV ICT bays – 16 Nos. | • 220kV ICT bays – 10 Nos. | • 1x330 MVAr, 765 kV bus reactor- 2 Nos. (7x110 MVAR single phase Reactors including one spare Unit for bus /line reactor) (1 on Sec-I & 1 on Sec-II) | • 765 kV Bus reactor bay – 2 Nos. | • 765kV line bays: 8 nos. (4 Nos. on Sec-I (2 for Halvad D/c & 2 for Ahmedabad D/c) and 4 Nos. on Sec-II (2 for Kandla D/c and 2 for Vataman)) | • 765 kV Sectionaliser bay: 1 -set | • 400 kV Sectionaliser bay: 1- set | • 220 kV Sectionaliser bay: 1- set | • 220kV BC-2 No. | • 220kV TBC-2 No. | • 125 MVAr, 420 kV reactor- 2 Nos. (1 on Sec-I & 1 on Sec-II) | • 400 kV Reactor bay- 2 Nos. | • 400 kV line bays - 3 Nos. (2 nos. on Section-I & 1 No. on Sec-II for interconnection of RE Projects) | • 220 kV line bays - 15 Nos. (7 nos. on Sec-I & 8 nos. on Sec-II for interconnection of RE Projects)
Future provision (space for): |
➤ 765 kV line bays along with switchable line reactors - 6 Nos. (2 Nos. on Sec-I & 4 Nos. on Sec-II) |
➤ 765 kV Bus Reactor along with bay: 2 Nos. (1 on Sec-I & 1 on Sec-II) |
➤ 400 kV line bays along with switchable line reactors- 7 Nos. (3 on Sec-I & 4 on Sec-II) + 4 Nos. 400kV bays (2 nos. on each section) for HVDC Interconnection |
➤ 420 kV, 125MVAr Bus Reactor along with bays: 2 Nos. (1 on Sec-I & 1 on Sec-II) |
➤ 220 kV line bays: 2 No. on Sec-I & 1 Nos. on Section-II |
➤ Establishment of 6000 MW, ± 800 kV Lakadia-II (HVDC) [LCC] terminal station (4x1500 MW) along with associated interconnections with 400 kV HVAC Switchyard & all associated equipment (incl. filters)/bus extension, etc. (2x1500MW poles on each 400kV section) |
18
THE GAZETTE OF INDIA: EXTRAORDINARY
[PART II-SEC. 3(ii)]
➤ Synchronous Condenser (+300/-200MVAr) along with 400kV bay – 2 Nos. (1 on Sec-I & 1 on Sec-II) | Synchronous Condenser along with associated 400kV Bay-2 Nos. (one each on Sec-I & II)
2. | Installation of Synchronous Condenser (+300/-200MVAr) (Minimum) & Short circuit contribution at PCC of 1200MVA (Minimum) at Lakadia-II – 2 Nos. Value of Inertia (MW-s) shall be defined in RfP document. |
3. | LILO of Halvad – Kandla 765kV D/c line at Lakadia-II | LILO route length ~22km. (88ckm)
4. | Lakadia-II – Ahmedabad 765kV D/c line | 190 km (380 ckm)
5 | 2 Nos. 765 kV line bays at Ahmedabad S/s for Lakadia-II – Ahmedabad 765kV D/c line | 765 kV line bays – 2 Nos. (AIS)
6 | 765kV, 330MVAr Switchable line reactors on each circuit at Ahmedabad end of Lakadia-II – Ahmedabad 765kV D/c line | • 330 MVAr, 765 kV switchable line reactor- 2 Nos. | • 765 kV Switchable Line Reactor Bay - 2 Nos. | • 110MVAr spare single phase reactor at Ahmedabad S/s is already available and same shall be used for subject Sw LR.
7 | Lakadia-II – Vataman 765kV D/c line (220km.) | 220 km (440 ckm)
8 | 2 Nos. 765 kV line bays at Vataman S/s for Lakadia-II – Vataman 765kV D/c line | 765 kV line bays – 2 Nos. (AIS)
9 | 765kV, 240MVAr Switchable line reactors on each circuit at both ends of Lakadia-II – Vataman 765kV D/c line | • 240 MVAr, 765 kV switchable line reactor- 4 Nos. (2 for Lakadia-II end and 2 for Vataman end) | • 765 kV switchable Line Reactor Bay - 4 Nos (2 for Lakadia-II end and 2 for Vataman end) | • 80MVAr spare single-phase reactor at Lakadia-II for above 240MVAr Sw LR. | • 80MVAr spare single-phase reactor at Vataman S/s is already available and same shall be used for subject Sw LR.
Note: |
➤ TSPs of Ahmedabad S/s & Vataman S/s to provide space for above scope of work in their respective substations (free of cost) |
➤ Above Syncons (at Sl. No. 2) shall be considered as ‘transmission asset' similar to STATCOM & SVC for its tariff mechanism. |
5. Common Transmission System for evacuation of power from Lakadia (Phase-II: 7.5GW), Jam Khambhaliya (Phase-II: 5.5GW) and Jamnagar (Phase-I: 1GW) - Part-A
Tentative implementation timeframe: 36 Months
BPC: Power Finance Corporation Limited (PFC)
Scope:
Sl. No. | Scope of the Transmission Scheme | Capacity/km
1. | Augmentation of transformation capacity at South Olpad (GIS) S/s by 1x1500MVA, 765/400kV (3rd) ICT | • 765/400 kV, 1500 MVA ICT – 1 No. | • 765 kV ICT bays – 1 No. (GIS) (Being constructed as a part of diameter completion under Khavda Ph-IV Part-C Scheme) | • 400 kV ICT bays – 1 No. (GIS)
2. | Vadodara(GIS) – Halvad 765kV D/c line to be | 250 km (500 ckm)
19
terminated into Lakadia - Halvad 765kV D/c line (near Halvad S/s) so as to form Lakadia – Vadodara (GIS) 765kV D/c line | (Length of complete Lakadia – Vadodara (GIS) 765kV D/c line after implementation of above line section between Vadodara and Halvad is expected to be around 350km.)
3. | 765kV line bays at Vadodara (GIS) end for termination of Lakadia - Vadodara 765kV D/c line (formed as per details above at Sl. 2) | • 765kV line bays – 2 nos. (GIS) | (being constructed as a part of diameter completion under “Transmission System for Evacuation of Power from potential renewable energy zone in Khavda area of Gujarat under Phase-IV (7 GW): Part B”. Line side equipment for termination of the line at these bays to be implemented under the subject transmission scheme)
4. | 765kV, 240MVAr Switchable line reactors on each circuit at Vadodara (GIS) end of Lakadia – Vadodara (GIS) 765kV D/c line (formed as per details above at Sl. 2) | • 240 MVAr, 765 kV switchable line reactor- 2 Nos. | • 765 kV switchable Line Reactor Bay- 2 Nos. (being constructed as a part of diameter completion under "Transmission System for Evacuation of Power from potential renewable energy zone in Khavda area of Gujarat under Phase-IV (7 GW): Part B") | • 80MVAr, 1-Ph spare reactor at Vadodara S/s is already available and same shall be utilized for subject switchable LR.
5. | 765kV, 330MVAr Switchable Mid-point reactors at the bypass point at Halvad Switching Station on Lakadia – Vadodara (GIS) 765kV D/c line (refer Note d) | • 330 MVAr, 765 kV switchable line reactor- 2 Nos. | • 765 kV switchable Line Reactor Bay - 2 Nos. | • 110MVAr spare single phase reactor at bypass point near Halvad S/s
Note: |
a) Bay(s) required for completion of diameter (GIS) in one-and-half breaker scheme shall also be executed by the TSP. |
b) TSP of South Olpad S/s to provide space for above scope of work as Sl. 1 (Free of cost) |
c) TSP of Vadodara (GIS) to provide space for above scope of work as Sl. 3 & 4 (Free of cost) |
d) As the provision for 765kV, 330MVAr switchable mid-point reactor at the bypass point at Halvad Switching Station on Lakadia – Vadodara (GIS) 765kV D/c line was not envisaged while allocating space for future scope at Halvad Switching Station under the “Transmission Scheme for evacuation of additional 7GWE of RE power from Khavda RE Park under Phase III Part A" project (under implementation by Halvad Transmission Ltd-AESL), the reactor shall be installed at Halvad Switching Station by utilizing the space reserved for other transmission elements, which will be specified in the RfP document. |
6. Common Transmission System for evacuation of power from Lakadia (Phase-II: 7.5GW), Jam Khambhaliya (Phase-II: 5.5GW) and Jamnagar (Phase-I: 1GW) - Part-B
Tentative implementation timeframe: 36 Months
BPC: REC Power Development and Consultancy Limited
Scope:
Sl. No. | Scope of the Transmission Scheme | Capacity /km
1. | Establishment of 765/400 kV, 3x1500MVA & 400/220kV, 3x500MVA Nasik S/s (towards South of Nasik) with 2x330 MVAR 765kV bus reactor and 2x125 MVAR 400kV bus reactor. | • 765/400 kV, 1500 MVA ICT – 3 Nos. (10x500 MVA single phase units including one spare ICT Unit) | • 400/220 kV ICTs - 3 Nos.
Future provision (space for): |
20
THE GAZETTE OF INDIA: EXTRAORDINARY
[PART II-SEC. 3(ii)]
➤ 765/400 kV, 1500MVA ICT along with bays- 3 Nos. (on Sec-II) | • 765 kV ICT bays - 3 Nos.
➤ 765 kV line bays along with switchable line reactors - 10 Nos. (4 Nos. on Sec-I & 6 Nos. on Sec-II) | • 400 kV ICT bays -6 Nos.
➤ 765 kV, 330MVAr Bus Reactor along with bay: 2 Nos. (on Sec-II) | • 220kV ICT bays - 3 Nos.
➤ 765 kV Sectionaliser bay: 1 -set | • 765 kV Line bays – 2 Nos.
➤ 400 kV Sectionaliser bay: 1- set | • 1x330 MVAr, 765 kV bus reactor- 2 Nos. (7x110 MVAR single phase Reactors including one spare Unit for bus /line reactor)
➤ 400/220 kV, 500MVA ICT along with bays - 7 Nos. (2 on Sec-I & 5 on Sec-II) | • 765 kV Bus reactor bay - 2 Nos.
➤ 400 kV line bays along with switchable line reactors- 10 Nos. (4 on Sec-I & 6 on Sec-II) | • 220kV BC-1 No.
➤ 420 kV, 125MVAr Bus Reactor along with bays: 2 Nos. (on Sec-II) | • 220kV TBC – 1 No.
➤ 220 kV Sectionaliser bay: 1- set | • 125 MVAr, 420 kV reactor- 2 Nos.
➤ 220kV BC & TBC-1 No. each | • 400 kV Reactor bay- 2 Nos.
➤ 220 kV line bays: 2 No. on Sec-I & 8 Nos. on Section-II | • 400 kV line bays - 2 Nos. | • 220 kV line bays - 6 Nos. (for MSETCL 220kV lines: Adwadi 220kV D/c, Nasik GCR 220kV D/c & Nasik OCR 220kV D/c)
2. | South Olpad (GIS) – Nasik 765kV D/c line (240km.) | • 240 km (480 ckm)
3. | 2 Nos. 765 kV line bays at South Olpad (GIS) S/s (Sec-II) for South Olpad – Nasik 765kV D/c line | • 765 kV line bays – 2 Nos. (GIS) (Sec-II) along with 1 Set of 765kV sectionaliser so as to establish 765kV Sec-II.
4. | 765kV, 240MVAr Switchable line reactors on each circuit at both ends of South Olpad – Nasik 765kV D/c line | • 240 MVAr, 765 kV switchable line reactor- 4 Nos. (2 for South Olpad end and 2 for Nasik end) | • 765 kV switchable Line Reactor Bay - 4 Nos. (2 for South Olpad end and 2 for Nasik end) | • 80MVAr spare single-phase reactor at Nasik for above 240MVAr switchable LR. | • 80MVAr spare single-phase reactor at South Olpad S/s is already available and same shall be used for subject switchable LR.
5. | Nasik - Pimpalgaon (MSETCL) 400kV D/c line (Quad ACSR/AAAC/AL59 moose equivalent) (Line to be routed from near Sinner TPP / Raymond i.e. from eastern side of Nasik). | 80km. (160ckm)
6. | 2 Nos. 400 kV line bays at Pimpalgaon S/s for Nasik - Pimpalgaon (MSETCL) 400kV D/c line (Quad ACSR/AAAC/AL59 moose equivalent) | 400 kV line bays – 2 Nos.
Note: |
a) Bay(s) required for completion of diameter (GIS) in one-and-half breaker scheme shall also be executed by the TSP. |
b) TSP of South Olpad(GIS) to provide space for above scope of work (Free of cost) |
21
c) MSETCL to provide space for above scope of work at Pimpalgaon S/s (Free of cost)
d) MSETCL to implement 220kV downstream system from Nasik S/s in matching time-frame.
7. Common Transmission System for evacuation of power from Lakadia (Phase-II: 7.5GW), Jam Khambhaliya (Phase-II: 5.5GW) and Jamnagar (Phase-I: 1GW) - Part-C
Tentative implementation timeframe: 36 Months
BPC: Power Finance Corporation Limited (PFC)
Scope:
Sl. No. | Scope of the Transmission Scheme | Capacity/km
1. | Establishment of 765/400 kV, 2x1500MVA & 400/220kV, 3x500MVA Alephata S/s with 2x330 MVAR 765kV bus reactor and 2x125 MVAR 400kV bus reactor. [765kV & 400kV Bus sectionalisers to be kept normally closed. May be opened based on Grid conditions] | • 765/400 kV, 1500 MVA ICT – 2 Nos. (7x500 MVA single phase units including one spare ICT Unit) (1 on Sec-I & 1 on Sec-II) | • 400/220 kV ICTs - 3 Nos. (on Sec-I) | • 765 kV ICT bays – 2 Nos. | • 400 kV ICT bays -5 Nos. | • 220kV ICT bays - 3 Nos. | • 765 kV Line bays - 6 Nos. (4 on Sec-I: Nasik D/c, Pune (Shikrapur) & Padghe S/c & 2 on Sec-II: Pune (Shikrapur) & Aurangabad) | • 1x330 MVAr, 765 kV bus reactor- 2 Nos. (7x110 MVAR single phase Reactors including one spare Unit for bus /line reactor) (1 on Sec-I & 1 on Sec-II) | • 765 kV Bus reactor bay – 2 Nos. | • 220kV BC-1 No. | • 220kV TBC – 1 No. | • 125 MVAr, 420 kV reactor- 2 Nos. (1 on Sec-I & 1 on Sec-II) | • 400 kV Reactor bay- 2 Nos. | • 400 kV line bays - 2 Nos. (on Sec-I) | • 220 kV line bays - 4 Nos. (for MSETCL 220kV lines: Alephata(M) 220kV D/c & Bridgestone 220kV D/c) | • 765 kV Sectionaliser bay: 1 -set | • 400 kV Sectionaliser bay: 1- set
Future provision (space for): |
➤ 765/400 kV, 1500MVA ICT along with bays- 4 Nos. (2 on Sec-I & 2 on Sec-II) |
➤ 765 kV line bays along with switchable line reactors - 6 Nos. (2 Nos. on Sec-I & 4 Nos. on Sec-II) |
➤ 765 kV, 330MVAr Bus Reactor along with bay: 2 Nos. (1 on Sec-I & 1 on Sec-II) |
➤ 400/220 kV, 500MVA ICT along with bays - 7 Nos. (2 on Sec-I & 5 on Sec-II) |
➤ 400 kV line bays along with switchable line reactors- 10 Nos. (4 on Sec-I & 6 on Sec-II) + 4 nos. 400kV bays (2 nos. on each section) for HVDC Interconnection |
➤ 420 kV, 125MVAr Bus Reactor along with bays: 2 Nos. (1 on Sec-I & 1 on Sec-II) |
➤ 220 kV Sectionaliser bay: 1- set |
➤ 220kV BC & TBC – 1 No. each |
➤ 220 kV line bays: 4 No. on Sec-I & 8 Nos. on Section-II |
➤ Establishment of 6000 MW, ± 800 kV Alephata (HVDC) [LCC] terminal station (4x1500 MW) along with associated interconnections with 400 kV HVAC Switchyard & all associated equipment (incl. filters)/bus extension, etc. (2x1500MW poles on each 400kV section) |
2. | Alephata - Lonikand-I 400kV D/c line (Quad ACSR/AAAC/AL59 moose equivalent) (~70km.) | 70 km (140 ckm)
3. | 2 Nos. 400 kV line bays at Lonikand-I (MSETCL) S/s for Alephata - Lonikand-I 400kV D/c line | 400 kV line bays – 2 Nos.
4. | LILO of Aurangabad – Pune (Shikrapur) (GIS) 765kV S/c line and Padghe (GIS) – Pune (Shikrapur) (GIS) 765kV S/c line at Alephata S/s (LILO route length ~ 20km.) | LILO route length – 20 km. (80ckm)
5. | Nasik - Alephata 765kV D/c line (~100km.) | 100 km (200 ckm)
6. | 2 Nos. 765kV bays at Nasik for Nasik – Alephata 765kV D/c line | 765 kV Line bays – 2 Nos.
22
THE GAZETTE OF INDIA : EXTRAORDINARY
[PART II-SEC. 3(ii)]
Note-1:
a) TSP of Nasik S/s to provide space for above scope of work as Sl. 6 (Free of cost)
b) MSETCL to provide space for above scope of work as Sl. 3 (Free of cost)
c) MSETCL to implement 220kV downstream system from Alephata S/s in matching time-frame.
Note-2:
a) 240MVAr line reactor at Pune(GIS) end of Pune(GIS) – Aurangabad 765kV line is already switchable. Since length of the line will reduce after the LILO at Alephata (Pune(GIS) – Alephata), NGR Bypassing along with Inter tripping scheme would need to be implemented to avoid parallel resonance phenomena due to overcompensation on the short line. NGR bypassing also helps in utilization of switchable LR as Bus Reactor when line is out of service. As confirmed by POWERGRID vide e-mail dated 02.12.2024, NGR bypass arrangement in 240MVAr line reactor at Pune(GIS) end of 765kV Pune(GIS) – Aurangabad line is available. Hence, only Inter tripping scheme to trip switchable LR along with main line breaker would need to be enabled after implementation of LILO, which shall be ensured by TSP in coordination with POWERGRID.
After the LILO, Alephata – Aurangabad line length is expected to be ~190-200km, Alephata – Padghe: ~140km. & Alephata – Pune(GIS): ~70km. The lengths are tentative and subject to change.
b) Alephata – Pune(West) 765kV D/c line has been proposed by MSETCL it its master plan for 2030. Same may be implemented by MSETCL along with associated bays at both ends as per requirement. Line shall be terminated at 765kV Sec-II of Alephata S/s.
c) After implementation of Alephata – Lonikand-I 400kV D/c line by TSP under subject scheme and Pune(East)(Karjat-II) S/s – Lonikand-II 400kV D/c line by MSETCL under In-STS scheme, 400kV interconnector between Lonikand-I and Lonikand-II may be kept normally open (for fault level control) and may be closed based on requirement of Grid Operation. TSP to sensitize MSETCL after completion of above lines.
8. The appointment of the Bid Process Coordinator is subject to the conditions laid down in the Guidelines issued by Ministry of Power in this regard, amended from time to time.
9. BPCs shall ensure RoW optimization as per the CEA's Committee report dated 24.09.2024 for calculation of reduction of Right of Way (RoW) Width through Technological Options.
10. Monopole tower structures, insulated cross arms and other RoW corridor optimization measures to be adopted in urban/ semi-urban /forest areas.
11. Monopole tower structures to be used where RoW issues are anticipated, while lattice towers shall be used in other sections.
12. Further, the route must be finalised after validation on PM Gati Shakti portal and physical survey.
[F. No. 34-15/3/2026-Trans]
NAOREM INDRAKUMAR SINGH. Under Secy. (Transmission)
Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064