No. 4630] NEW DELHI, TUES DAY , NOVEMBER 7, 2023/ KARTIKA 16, 1945
CG-DL-E-07112023-249941
2.
MINISTRY OF POWER
NOTIFICATION
New Delhi, the 7th November , 2023
S.O. 4829 (E).— In exercise of the powers conferred by sub -para 3.2 of Para 3 of the Guidelines circulated
under Section 63 of the Electricity Act , 2003 (no. 36 of 2003), the Central Government, on recommendations of 15th
meeting of National Committee on Transmission, hereby appoints the following Bid -Process Coordinators (BPCs) for
the Transmission Schemes, as shown against the name of the Transmi ssion Schemes: -
Sl.
No. Name & Scope of the Transmission Scheme Bid Process
Coordinator
1.
Transmission system strengthening for interconnections of Bhadla -III & Bikaner -
III complex
Tentative Implementation Timeframe: 24 months from date of SPV Transfer
Scope:
Sl.
No. Scope of the Transmission Scheme
1 Bhadla -III – Bikaner -III 765 kV D/c line along with 240 MVAr switchable
line reactor for each circuit at Bhadla -III end (line length~150 km) as well
as associ ated 2 Nos. of 765kV line bay(s) at each at Bhadla -III & Bikaner -
III end
Note:
i. Developer of Bhadla -III PS to provide space for two nos. of 765 kV line
bays along with space for two nos. of switchable line reactors
ii. Developer of Bikaner -III PS to prov ide space for two nos. of 765 kV line
bays PFC Consulting
Limited
iii. The line lengths mentioned above are approximate as the exact length
shall be obtained after the detailed survey.
2.
Network Expansion scheme in Gujarat for drawl of about 3.6 GW load under
Phase -I in Jamnagar area
Tentative Implementation Time: 24 months from date of SPV transfer
Scope:
1. Establishment of 2x1500 MVA 765/400
kV Jamnagar (GIS) PS with 2x330
MVAR 765 kV bus reactor and 2x125
MVAR 420 kV bus reactor.
Future Provisions : Space for
•
o 765/400 kV ICT along with bays - 4
no.
o 765 kV line bays along with
switchable line reactors – 10 nos.
o 765 kV Bus Reactor along with bay:
2 no.
o 765 kV Sectionaliser bay: 1 -set
o 400 kV line bays along with
switchabl e line reactor – 8 nos.
o 400/220 kV ICT along with bays -6
nos.
o 420 kV Bus Reactor along with bay:
2 no.
o 400 kV Sectionalization bay: 1 - set
o 220 kV line bays: 14 nos.
o 220 kV Sectionalization bay: 1 set
o 220 kV BC: 1 no.
o 80MVAR 1 -ph spare reactor unit 765/400 kV, 1500 MVA ICT -2
Nos.
765 kV ICT bays - 2 Nos.
400 kV ICT bays - 2 Nos.
330 MVAR 765 kV bus reactor -
2 Nos.
125 MVAR 420 kV bus reactor -
2 Nos.
765 kV reactor bay - 2 Nos.
765 kV line bay - 2 Nos.
400 kV reactor bay - 2 Nos.
400 kV line bay - 10 Nos.
500 MVA, 765/400 kV 1 -Ph
Spare ICT -1 No.
110 MVAR, 765 kV, 1 -ph
reactor (spare unit for line/bus
reactor) -1 No.
2. Halvad – Jamnagar 765 kV D/c line Route length: 170 km
3. 2 nos. of 765 kV line bays at Halvad for
termination of Halvad – Jamnagar 765 kV
D/c line 765 kV line bays – 2 Nos. (for
Halvad end)
4. 330 MVAr switchable line reactors on
each ckt at Jamnagar end of Halvad –
Jamnagar 765 kV D/c line (with NGR
bypass arrangement) 330 MVAr, 765 kV
switchable line reactor - 2 Nos.
Switching equipments
for 76 5 kV line reactor - 2 Nos.
5. LILO of Jam Khambhaliya PS – Lakadia
400 kV D/c (triple snowbird) line at
Jamnagar. LILO route length: 5 km.
6. 50 MVAr, 420 kV switchable line
reactors on each ckt at Jamnagar end of
Jamnagar – Lakadia 400kV D/c line (wit h
NGR bypass arrangement) 50 MVAr, 420 kV
switchable line reactor - 2 Nos.
Switching equipments
for 400 kV line reactor - 2 Nos.
7. Jamnagar – Jam Khambhaliya 400 kV D/c
(Quad ACSR/AAAC/AL59 moose
equivalent) line Route Length~ 50 km.
8. 2 nos. of 400kV line bays at Jam
Khambhaliya for termination of Jamnagar
– Jam Khambhaliya 400kV D/c (Quad
ACSR/AAAC/AL59 moose equivalent)
line
400 kV line bays (GIS)
– 2 Nos. (for Jam Khambhaliya
end)
9. LILO of CGPL – Jetpur 400kV D/c (triple
snowbird) line at Jamnag ar. LILO route length: 65 km. PFC Consulting
Limited
10. 80MVAr, 420kV switchable line reactors
on each ckt at Jamnagar end of Jamnagar
– CGPL 400kV D/c line (with NGR
bypass arrangement) 80 MVAr, 420 kV
switchable line reactor - 2 Nos.
Switching equipments
for 400 kV line reac tor- 2 Nos.
11. LILO of both ckts of Kalavad – Bhogat
400kV D/c line (Twin AL -59) at Jam
Khambhaliya PS LILO route length: 10
km.
12. 4 nos. of 400kV line bays at Jam
Khambhaliya for LILO of both ckts of
Kalavad – Bhogat 400kV D/c line 400 kV line bays (GIS)
– 4 Nos. (for Jam Khambhaliya
end)
13. ±400 MVAr STATCOM with 3x125
MVAr MSC & 2x125 MVAr MSR at
Jamnagar 400kV Bus section ±400 MVAr
STATCOM (with MSC/MSR)
400 kV bay – 2 no. (1
no. for STATCOM and 2nd for
Dia. completion)*
* The TSP shall imple ment one complete diameter (GIS) consisting of 2 main
bays & 1 Tie bay in one and half breaker scheme
Note:
i. Bay(s) required for completion of diameter (GIS) in one -and-half breaker
scheme shall also be executed by the TSP.
ii. TSP (JKTL) shall enable Inter -tripping scheme on Jamnagar – Jam
Khambhaliya 400 kV D/c line (for tripping of the 63 MVAR switchable line
reactor at Jam Khambhalya PS end along with the main line breaker)
after commissioning of the above system.
iii. TSP of the present scheme shall implement Inter -tripping scheme on
Jamnagar – Lakadia 400 kV D/c line (for tripping of the 50MVAR
switchable line reactor at Jamnagar end along with the main line breaker)
after commissioning of the above system.
iv. The line lengths mentioned above are approximate as t he exact length
shall be obtained after the detailed survey.
2. The appointment of the Bid Process Coordinator is subject to the conditions laid down in the Guidelines issued
by Ministry of Power in this regard, ame nded from time to time.
[F. No. 15/3/2018 -Trans -Part(5)]
BIHARI LAL , Under Secy . (Transmission)
1.
2.
NOTIFICATION
New Delhi, the 7th November , 2023
S.O. 4830(E). — In exercise of the powers conferred by sub - para 3.2 of the Guidelines circulated under
Section 63 of the Electricity Act, 2003 (no. 36 of 2003), the Central Government had notified/ modified scope of
following transmission schemes for implementation under Tariff Based Competitive Bidding (TBCB) vide Gazette
Notification men tioned below table:
Sl.
No. Name of the Scheme Gazette Notification by which Scheme
was notified
1. Transmission Scheme for Solar Energy Zone in Bidar (2500
MW), Karnataka S.O. 386(E) dated 24.01.2020
[F.No.15/3/2018 -Trans -Part(1) and
further modified by S.O. 1486(E) dated
29.03.2023 [F.No. 15/3/2018 -Trans -
Part(2)]
2. Transmission System for evacuation of power from REZ in
Rajasthan (20 GW) under Phase -III Pat D S.O. 5032(E) dated 03.12.2021
[F.No.15/3/2018 -Trans -Part(1)
3. Transmission System for evacua tion of power from REZ in
Rajasthan (20 GW) under Phase -III Part I S.O. 235(E) dated 13.01.2023
[F.No.15/3/2018 -Trans -Part(1)
4. Transmission Scheme for integration of Renewable Energy Zone
(Phase -II) in Koppal -II (Phase -B) in Karnataka S.O. 855(E) dated 23.02.2023
[F.No.15/3/2018 -Trans -Part(2)
2. Now, the Central Government has decided to modify the scope of above mentioned four schemes after
examining the recommendations of the 15th meeting of National Committee on Transmission (NCT). As such, the
scopes of schemes are hereby modified as under:
Sl.SL.
No. Name of Transmission Scheme and its Revised Scope
1.
Transmission Scheme f or Solar Energy Zone in Bidar (2500 MW), Karnataka
Revised scope of the Transmission Scheme:
Sl.
No. Revised Scope of the Transmission Scheme Capacity/Km
1. Establishment of 765/400 kV 3x1500 MVA,
400/220 kV 5x500 MVA pooling station at
suitable borde r location near Bidar with 765 kV
(1x240 MVAR) and 400 kV (1x125 MVAR) Bus
Reactor
765 kV Future Provision
i. Space for future 765/400 kV ICT along
with associated bay: 1 no.
ii. Space for future 765 kV Bus Reactor
along with associated bay: 1 no.
iii. Space for add itional future line bays with
SLR: 8 nos.
iv. Space for additional future 765/400 kV
ICT along with associated bay: 2 nos.
400 kV Future Provision
i. Space for future line bay: 8 nos.
ii. Space for future 765/400 kV ICT bay:
1 no.
iii. Space for future 400/220 kV ICT a long
with associated bay: 2 nos.
iv. Space for additional future line bay with
SLR: 2 nos.
v. Space for additional future 765/400 kV
ICT bay: 2 nos.
vi. Space for additional future 400/220 kV
ICT along with associated bay: 4 nos.
220 kV Future Provision
i. Space for fut ure 400/220 kV ICT bays: 2
nos.
ii. Space for future line bays: 4 nos.
iii. Space for additional future 400/220 kV ICT
bays: 4 nos.
iv. Space for additional future line bay: 6 nos.
v. Space for additional future 220 kV Bus
Sectionalizer: 2 sets
vi. Space for additional fut ure 220 kV TBC bay:
2 nos.
vii. Space for additional future 220 kV BC bay:
2 nos. 765/400 kV, 1500 MVA, ICTs – 3 Nos.
(10x500 MVA including 1 spare unit)
500 MVA, 400/220 kV ICT – 5 Nos.
765 kV ICT bays – 3 Nos.
400 kV ICT bays – 8 Nos.
220 kV ICT bays – 5 No s.
765 kV line bays – 2 Nos.
220 kV line bays – 8 Nos.
765 kV, 240 MVAr Bus reactor – 1 No.
(3x80 MVAr)
765 kV Bus reactor bays – 1 No.
125 MVAr, 420 kV Bus reactor – 1 No.
420 kV Bus reactor bay – 1 No.
220 kV Bus sectionalizer – 1set.
220 kV Bus coupler b ays – 2 Nos.
220 kV Transfer Bus Coupler bays – 2
Nos.
2. Bidar PS – Maheshwaram (PG) 765 kV D/C line Route Length – 242 km
3. 2 nos. of 765 kV line bays at Maheshwaram (PG)
GIS substation for termination of Bidar PS –
Maheshwaram (PG) GIS 765 kV D/C line 765 kV line bays (GIS) – 2
4. 765 kV, 1x240 MVAR Switchable Line Reactor
for each circuit at Bidar PS end & Maheshwaram
(PG) end of Bidar PS - Maheshwaram (PG) GIS
765 kV D/C line 240 MVAr, 765 kV line reactor – 4
Nos. [7x80 MVAr at Bidar PS an d
7x80 MVAr at Maheshwaram (PG),
including 1 spare unit for both Bus
Reactor & Line Reactor]
Switching equipments for 765 kV
reactor – 2 Nos. each at Bidar PS &
Maheshwaram.
Note: POWERGRID shall provide space for 2 no. of 765 kV line bays with provision for 240 MVAr
SLR at Maheshwaram (PG) substation for termination of Bidar PS – Maheshwaram (PG) 765 kV
D/c line
2.
Transmission System for evacuation of power from REZ in Rajasthan (20 GW) under Ph ase-III Part
D-Phase I
Revised Scope of the Transmission Scheme:
Sl.
No. Scope of the Transmission Scheme Capacity/ Km
1. Sikar -II – Khetri 765 kV D/c line Length – 90 km
2. Sikar -II – Narela 765 kV D/c line along with 240
MVAr Switchable line reac tor for each circuit at
each end of Sikar -II – Narela 765 kV D/c line
Length – 260 km
Switching equipment for 765 kV,
240 MVAR Switchable line
reactor –4 nos.
765kV, 240 MVAr Switchable
line reactor - 4 nos.
3. 765 kV line bays at Sikar –II for Sikar -II – Khetri
765 kV D/c line and Sikar -II – Narela 765 kV D/c
line 765 kV line bays – 4 nos.
4. 2 nos. of 765 kV line bays at both Khetri and Narela
S/s 765 kV line bays – 4 nos.
Note:
i. Developer of Sikar -II S/s to provide space for 4 nos. of 765 kV line ba ys at Sikar -II S/s
along with space for two nos. of switchable line reactors
ii. Developer of Narela S/s to provide space for 2 nos. of 765 kV line bays along with space for
switchable line reactors at Narela S/s
iii. Powergrid to provide space for two nos. of 765 kV line bays at Khetri substation
iv. The line lengths mentioned above are approximate as the exact length shall be obtained after
the detailed survey.
3. Transmission System for evacuation of power from REZ in Rajasthan (20 GW) under Phase -III Part I
Modi fied scope of the Scheme: Revised commissioning schedule is 48 months for Bipole -I and 54 months
for Bipole -2
4. Transmission Scheme for integration of Renewable Energy Zone (Phase -II) in Koppal -II (Phase -B) in
Karnataka
Modified Scope of the Scheme: Implementation schedule of Transmission Scheme is reduced from 36
months to 24 months.
3. Bid Process Co -ordinators for above scheme will remain unchanged, as per original notification.
[F. No. 15/3/2018 -Trans -Part(5)]
BIHARI LAL, Under Secy . (Transmission )