NEW DELHI, MONDAY, JUNE 29, 2026/ ASHADHA 8, 1948
MINISTRY OF POWER
ORDER
New Delhi, the 23rd June, 2026
S.O. 3479(E). - Whereas M/s Bhadla Three SKP Green Ventures Private Limited having its registered address at 2A, Lord Sinha Road, First Floor, Middleton Row, Kolkata, West Bengal - 700071, India has applied for authorization under Section 164 of the Electricity Act, 2003 for laying of overhead transmission line under the transmission scheme "Transmission system for providing connectivity to M/s Bhadla Three SKP Green Ventures Private Limited for its 300 MW Renewable Power Park in Phalodi, Rajasthan."
And whereas, Ministry of Power, Government of India vide its letter No. 25-17/17/2026-POWER GRID (MoP) dated 12.01.2026 had granted prior approval under section 68(1) of the Electricity Act, 2003 for the overhead line covered under the transmission scheme “Transmission system for providing connectivity to M/s Bhadla Three SKP Green Ventures Private Limited for its 300 MW Renewable Power Park in Phalodi, Rajasthan.”
M/s Bhadla Three SKP Green Ventures Private Limited had published notice for transmission scheme in local newspapers Dainik Bhaskar (in Hindi) dated 17.01.2026, The Indian Express (in English) dated 19.01.2026 and in Weekly Gazette of India dated 14.02.2026 for the general public to make observations/representations on the proposed transmission route within two Months from the date of publication. Subsequently, M/s Bhadla Three SKP Green Ventures Private Limited has submitted an affidavit dated 17.06.2026 declaring that no observation/ representation was received within two months from the date of Publication in the Newspaper and official Gazette of Government of India.
M/s Bhadla Three SKP Green Ventures Private Limited had submitted an Undertaking dated 25.05.2026 stating that the route of the proposed overhead transmission line(s) is located outside the Revised Great Indian Bustard (GIB) Priority Area of Rajasthan, as referred to in the judgment of the Hon'ble Supreme Court of India dated 19.12.2025 in Writ Petition (Civil) No. 838 of 2019; the applicant has further undertaken to comply with all directions of the Hon'ble Supreme Court as contained in the said judgment as well as with any subsequent directions
(1)
2
THEGAZETTEOFINDIA : EXTRAORDINARY
[PART II—SEC. 3(ii)]
issued by the competent authorities in pursuance of the above order by the Hon'ble Supreme Court, and has also stated that the transmission line alignment has been optimized, in such a way that they share maximum common stretch to the extent possible.
And now the applicant has requested to confer upon him, all the powers under section 164 of the Electricity Act, 2003, which the telegraph authority possess under the Indian Telegraph Act, 1885 with respect to the placing of telegraph lines and posts for the purpose of a telegraph established or maintained by Government or to be so established or maintained for laying of electric lines under the transmission scheme “Transmission system for providing connectivity to M/s Bhadla Three SKP Green Ventures Private Limited for its 300 MW Renewable Power Park in Phalodi, Rajasthan." The following overhead line is covered under this scheme:
(i) Bhadla Three SKP Green Ventures Private Limited RE Power Park (located at Village Nokh, District Phalodi, Rajasthan) - Bhadla III (ISTS) Pooling Station 220 kV S/c line on D/c towers.
The transmission line covered under the above scheme will pass through, over, around and between the following villages, towns and cities of Rajasthan:
Sr. No | Name of the Villages | Tehsil/Taluka | District | State
1. | Nokh (Naukh), Gelwa ki Dhani, Campwala, Kalusingh Ki Dhani, Karansingh ki Dhani, Bikolai, Lakharam ki Dhani, Bikampur, Surjanram Ki Dhani, Pyau, Jiwansingh Ki Dhani, Ganpatsingh Ki Dhani | Bap | Phalodi | Rajasthan
Now, after careful consideration, Ministry of Power, Government of India, under section 164 of the Electricity Act, 2003, confers all the powers to M/s Bhadla Three SKP Green Ventures Private Limited for laying of above overhead transmission line, which telegraph authority possesses under the Indian Telegraph Act, 1885 with respect to placing of telegraph lines and posts for the purposes of a telegraph established or maintained, by Government or to be established or maintained subject to following terms and conditions for installing the above mentioned line, namely:
i. The approval is granted for 25 years.
[PART II—SEC. 3(ii)]
ii. The Applicant shall have to seek the consent of the concerned authorities, i.e., local bodies, Railways, National Highways, State Highways etc. before erection of proposed line.
iii. The Applicant shall have to follow regulations/codes of the Appropriate Commission regarding transmission, O&M, open access, etc., framed under Electricity Act, 2003.
iv. The Applicant shall operate the line after approval of Electrical Inspector / Chief Electrical Inspector of Central Government.
v. The approval is subject to compliance of the requirement of the provisions of the Electricity Act, 2003 and the rules made there under by the applicant.
vi. M/s Bhadla Three SKP Green Ventures Private Limited shall have to submit the requisite clearances to Central Electricity Authority after obtaining the same from concerned authorities like Civil Aviation, Defense etc., at the time of Electrical Inspection.
vii. In case, the route of above overhead lines (or some portion of the route of above overhead line) falls in the Revised Great Indian Bustard (GIB) area, the applicant has to comply with the directions of Hon'ble Supreme Court of India in its order dated 19.12.2025 in Writ Petition (Civil) No. 838 of 2019 and any other directions given by competent authorities in pursuance of the above order by Hon'ble Supreme Court.
[F. No. 25-16/59/2026-POWER GRID(MoP)]
M.V.N. VARA PRASAD, Under Secretary (PG)
MINISTRY OF POWER
ORDER
New Delhi, the 23rd June, 2026
S.O. 3479(E). - Whereas M/s Bhadla Three SKP Green Ventures Private Limited having its registered address at 2A, Lord Sinha Road, First Floor, Middleton Row, Kolkata, West Bengal - 700071, India has applied for authorization under Section 164 of the Electricity Act, 2003 for laying of overhead transmission line under the transmission scheme "Transmission system for providing connectivity to M/s Bhadla Three SKP Green Ventures Private Limited for its 300 MW Renewable Power Park in Phalodi, Rajasthan."
And whereas, Ministry of Power, Government of India vide its letter No. 25-17/17/2026-POWER GRID (MoP) dated 12.01.2026 had granted prior approval under section 68(1) of the Electricity Act, 2003 for the overhead line covered under the transmission scheme “Transmission system for providing connectivity to M/s Bhadla Three SKP Green Ventures Private Limited for its 300 MW Renewable Power Park in Phalodi, Rajasthan.”
M/s Bhadla Three SKP Green Ventures Private Limited had published notice for transmission scheme in local newspapers Dainik Bhaskar (in Hindi) dated 17.01.2026, The Indian Express (in English) dated 19.01.2026 and in Weekly Gazette of India dated 14.02.2026 for the general public to make observations/representations on the proposed transmission route within two Months from the date of publication. Subsequently, M/s Bhadla Three SKP Green Ventures Private Limited has submitted an affidavit dated 17.06.2026 declaring that no observation/ representation was received within two months from the date of Publication in the Newspaper and official Gazette of Government of India.
M/s Bhadla Three SKP Green Ventures Private Limited had submitted an Undertaking dated 25.05.2026 stating that the route of the proposed overhead transmission line(s) is located outside the Revised Great Indian Bustard (GIB) Priority Area of Rajasthan, as referred to in the judgment of the Hon'ble Supreme Court of India dated 19.12.2025 in Writ Petition (Civil) No. 838 of 2019; the applicant has further undertaken to comply with all directions of the Hon'ble Supreme Court as contained in the said judgment as well as with any subsequent directions
4
THEGAZETTEOFINDIA : EXTRAORDINARY
[PART II—SEC. 3(ii)]
issued by the competent authorities in pursuance of the above order by the Hon'ble Supreme Court, and has also stated that the transmission line alignment has been optimized, in such a way that they share maximum common stretch to the extent possible.
And now the applicant has requested to confer upon him, all the powers under section 164 of the Electricity Act, 2003, which the telegraph authority possess under the Indian Telegraph Act, 1885 with respect to the placing of telegraph lines and posts for the purpose of a telegraph established or maintained by Government or to be so established or maintained for laying of electric lines under the transmission scheme “Transmission system for providing connectivity to M/s Bhadla Three SKP Green Ventures Private Limited for its 300 MW Renewable Power Park in Phalodi, Rajasthan." The following overhead line is covered under this scheme:
(i) Bhadla Three SKP Green Ventures Private Limited RE Power Park (located at Village Nokh, District Phalodi, Rajasthan) - Bhadla III (ISTS) Pooling Station 220 kV S/c line on D/c towers.
The transmission line covered under the above scheme will pass through, over, around and between the following villages, towns and cities of Rajasthan:
Sr. No | Name of the Villages | Tehsil/Taluka | District | State
1. | Nokh (Naukh), Gelwa ki Dhani, Campwala, Kalusingh Ki Dhani, Karansingh ki Dhani, Bikolai, Lakharam ki Dhani, Bikampur, Surjanram Ki Dhani, Pyau, Jiwansingh Ki Dhani, Ganpatsingh Ki Dhani | Bap | Phalodi | Rajasthan
Now, after careful consideration, Ministry of Power, Government of India, under section 164 of the Electricity Act, 2003, confers all the powers to M/s Bhadla Three SKP Green Ventures Private Limited for laying of above overhead transmission line, which telegraph authority possesses under the Indian Telegraph Act, 1885 with respect to placing of telegraph lines and posts for the purposes of a telegraph established or maintained, by Government or to be established or maintained subject to following terms and conditions for installing the above mentioned line, namely:
i. The approval is granted for 25 years.
ii. The Applicant shall have to seek the consent of the concerned authorities, i.e., local bodies, Railways, National Highways, State Highways etc. before erection of proposed line.
iii. The Applicant shall have to follow regulations/codes of the Appropriate Commission regarding transmission, O&M, open access, etc., framed under Electricity Act, 2003.
iv. The Applicant shall operate the line after approval of Electrical Inspector / Chief Electrical Inspector of Central Government.
v. The approval is subject to compliance of the requirement of the provisions of the Electricity Act, 2003 and the rules made there under by the applicant.
vi. M/s Bhadla Three SKP Green Ventures Private Limited shall have to submit the requisite clearances to Central Electricity Authority after obtaining the same from concerned authorities like Civil Aviation, Defense etc., at the time of Electrical Inspection.
vii. In case, the route of above overhead lines (or some portion of the route of above overhead line) falls in the Revised Great Indian Bustard (GIB) area, the applicant has to comply with the directions of Hon'ble Supreme Court of India in its order dated 19.12.2025 in Writ Petition (Civil) No. 838 of 2019 and any other directions given by competent authorities in pursuance of the above order by Hon'ble Supreme Court.
[F. No. 25-16/59/2026-POWER GRID(MoP)]
M.V.N. VARA PRASAD, Under Secretary (PG)
Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064
and Published by the Controller of Publications, Delhi-110054.
SARVESH KUMAR Digitally signed by SARVESH
SRIVASTAVA
Date: 2026.07.03 23:12:11 +0530