4851 DG/2024
DELHI ELECTRICITY REGULATORY COMMISSION
NOTIFICATION
Delhi, the 2nd August, 2024
Delhi Electricity Regulatory Commission (Net Metering for Renewable Energy) (First Amendment)
Regulations, 2024
No. F. F3(629)/Tariff-Engg./DERC/2020-21/6910/808.—The Delhi Electricity Regulatory Commission, in
exercise of the powers conferred under Section 181 read with Section 61(h), Section 86 (1) (e) of the Electricity Act,
2003, Regulation 16 of DERC (Net Metering for Renewable Energy) Regulations, 2014 and all other powers enabling
it in this behalf, hereby amends the following Regulation in DERC (Net Metering for Renewable Energy) Regulations,
2014 (hereinafter referred to as "the Principal Regulations"):
1.0 Short Title and Commencement:
(1) These Regulations may be called the Delhi Electricity Regulatory Commission (Net Metering for Renewable
Energy) (First Amendment) Regulations, 2024.
(2) These Regulations shall come into force from the date of their publication in the official Gazette.
2.0 Addition in Regulation 5 (3) of Principal Regulations:
2.1 New provisos added to Sub-regulation (3) of Regulation 5 of the Principal Regulations as under:
"Provided that the Technical feasibility of Renewable Energy System upto 10 kW is exempted from technical
feasibility studies on the same supply type (Voltage level- 1ph,3ph, etc.) and any commensurate enhancement
of Sanctioned Load of the consumer, as may be required, shall be carried out by Distribution Licensee.
Provided further that any upgradation in Distribution Infrastructure including DT capacity to
facilitate the installation of Renewable Energy System upto 10 kW shall be carried out by Distribution
Licensee and shall be allowed as pass through in Aggregate Revenue Requirement (ARR) subject to prudence
check by the Commission.
Provided also that Technical feasibility of Renewable Energy System above 10 kW shall be
completed by Distribution Licensee within fifteen (15) days from the date of receipt of application complete
in all aspects."
By Order and in The Name of Lt. Governor
National Capital Territory of Delhi
RAJESH DANGI, Secretary
Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064
and Published by the Controller of Publications, Delhi-110054.
GORAKHA
Digitally signed by GORAKHA
NATH YADAVA Dabe 2024.08.05 16:32:56+0530
Login to read full text