MINISTRY OF RAILWAYS
(Central Railway)
CORRIGENDUM
Mumbai, the 27th June, 2024
(IN REGARD TO E-GAZETTE NOTIFICATION NO. 2443DATED 09.06.2023, THE PARA MENTIONED
BELOW SHOULD BE TREATED AS CORRECTED DETAILS IN PREVIOUS NOTIFICATION)
S.O. 2479(E). Whereas, by the notification of the Government of India, in the Ministry of Railways
(Railway Board), number, S.O 5422 (E) dated the 30th November, 2022 published in Gazette of India,
Extraordinary, Part II, section 3 Sub-section (ii), dated the 5th December, 2022 (hereinafter referred to as the said
notification) and issued under sub-section (1) of section 20 A of the Railway Act, 1989 (24 of 1989) and Railway
(Amendment) Act, 2008(11th of 2008) (hereinafter referred to as the said Act), the Central Government declared its
intention to acquire the land specified in the schedule annexed to the said notification for the purpose of execution,
maintenance, management and operation of Special Railway Project, namely Solapur – Tuljapur – Osmanabad
New Line in the district of Osmanabad in the State of Maharashtra.
And whereas, the substance of the said notification was published in daily newspapers namely "Dainik
Ekmat dated 30th November 2022” and “Dainik Kulswamini Sandesh" Dated 16th December, 2022" under sub
section (4) of section 20A of the said Act;
And whereas in 3 villages, total 36 objections were received and the same have been disposed by the
competent Authority;
And whereas, in pursuance of sub-section 20 E of the said Act, the competent authority has submitted its
report to the Central Government;
Now therefore, upon receipt of the report of the Competent Authority and in exercise of the powers conferred
by sub-section (1) of section 20 E of the said Act, the Central Government hereby declares that the lands specified in
the schedule annexed hereto shall be acquired for the aforesaid purpose;
And further, in pursuance of sub-section (2) of section 20 E of the said Act, the Central Government hereby
declares that on publication of this notification in the official Gazette, the land specified in the schedule annexed
hereto shall vest absolutely in the Central government free from all encumbrances.
SCHEDULE
Brief description of the land to be acquired, with or without structures, falling within the Special Railway Project
Solapur - Tuljapur – Osmanabad New Line in 3 villages in Tuljapur Taluka under Competent Authority for Land
Acquisition and Sub-Divisional Officer, Osmanabad in the State of Maharashtra.
+-------+------------+----------------+-----------+------------------------------------+---------+------------+---------------------+--------------------+
| Sr. | LAQ | Village | Taluka | Name of Land Holder as per 7/12 | Gat | Land | Total | Land to be |
| No. | Case No. | Name | | | No. | Tenure | area as per | acquired |
| | | | | | | System | 7/12 (Ha) | (Sq.M.) |
+=======+============+================+===========+====================================+=========+============+=====================+====================+
| 1 | 22.07.21 | Tuljapur Rural | Tuljapur | Rajendra alias Rajkumar Baburao | 104 | 1 | 9.57 | 277.47 |
| | | | | Deshmane, | | | | |
| | | | | Arun Baburao Deshmane | | | | |
+-------+------------+----------------+-----------+------------------------------------+---------+------------+---------------------+--------------------+
| 2 | 22.07.21 | Tuljapur Rural | Tuljapur | Shankar Dhenu Rathod | 40/1 | 1 | 2.13 | 90.00 |
+-------+------------+----------------+-----------+------------------------------------+---------+------------+---------------------+--------------------+
| | | | | Total | | | | 367.47 |
+-------+------------+----------------+-----------+------------------------------------+---------+------------+---------------------+--------------------+
[F. No.: G197/2024/GOM/SUR-TGP-UMD/20E/June-Corrigendum]
AVANISH KUMAR PANDAY, Chief Administrative Officer (Construction)