CENTRAL ELECTRICITY AUTHORITY
NOTIFICATION
New Delhi, the 5th March, 2025
F. No. CEA-PS-12-13/3/2022-PSPA-II Division.—1. In exercise of the powers conferred by Para 3.2 of the
Tariff Based Competitive Bidding Guidelines for Transmission Services framed under Section 63 of the Electricity Act,
2003 (no. 36 of 2003) and Ministry of Power office order dated 28.10.2021, National Committee on Transmission
(NCT) headed by Chairperson, Central Electricity Authority had notified following transmission scheme for
implementation under Tariff Based Competitive Bidding (TBCB) vide Gazette Notification mentioned in below table:-
+-----+-----------------------------------------------+-------------------------------------------------------------+
| Sr. | Name of Transmission Scheme | Gazette Notification by which Transmission Scheme |
| No. | | was |
| | | notified |
+=====+===============================================+=============================================================+
| 1 | Augmentation of transformation | Dated 23.01.2024 [F. No. CEA-PS-12-13/3/2022-PSPA- |
| | capacity at Bhuj-II PS (GIS) | II Division] |
+-----+-----------------------------------------------+-------------------------------------------------------------+
2. Now, the National Committee on Transmission (NCT) has approved the implementation of the above scheme
under Regulated Tariff Mechanism mode in the 27th meeting held on 06.02.2025. As such, the above scheme
including its scope is hereby de-notified.
RAKESH KUMAR, Secy.