The Central Electricity Authority publishes the Central Electricity Authority (Technical Standards for Construction of Electrical Plants and Electric Lines) Amendment Regulations, 2025, to amend the 2022 Regulations.

Detailed Summary

The Central Electricity Authority (CEA) issued the Central Electricity Authority (Technical Standards for Construction of Electrical Plants and Electric Lines) Amendment Regulations, 2025, on October 9, 2025 (F No. CEA-TH-17/1/2021-TETD Division), which came into force upon publication in the Official Gazette on October 10, 2025. These regulations amend the Central Electricity Authority (Technical Standards for Construction of Electrical Plants and Electric Lines) Regulations, 2022, originally published on December 23, 2022 (Notification No. CEA-TH-17/1/2021-TETD Division). The amendment process involved a public notice on May 1, 2025, inviting objections and suggestions as per sub-section (3) of section 177 of the Electricity Act, 2003 (36 of 2003) and sub-rule (2) of rule 3 of the Electricity (Procedure for Previous Publication) Rules, 2005. Key changes include the insertion of two provisos into sub-regulation (4) of regulation 84, requiring Authority approval for Right-of-Way (RoW) values differing from SCHEDULE-VII due to changes in conductor configuration, type, or new technological options, with the Authority issuing separate orders for such cases. Furthermore, the entire SCHEDULE-VII is substituted with new tables specifying detailed RoW widths for various voltage levels (e.g., 765kV, ±800kV HVDC, 400kV, 220kV, 132kV, 110kV, 66kV), configurations, ACSR and HTLS conductor types (CFCC, ACSS, GAP), terrain conditions (Normal route, Forest, Urban/Populated area, Approach section near substation), and structure types (Lattice and Pole Structures). Notes clarify terms like D/C and S/C, sag calculation temperatures for specific conductors (CFCC at 180°C, ACSS at 250°C, GAP at 210°C), parameters considered for RoW width, and the contextual understanding of terrain types.

Full Text

REGD. No. D. L.-33004/99 The Gazette of India CG-DL-E-13102025-266889 EXTRAORDINARY PART III—Section 4 PUBLISHED BY AUTHORITY No. 670] NEW DELHI, FRIDAY, OCTOBER 10, 2025/ASVINA 18, 1947 CENTRAL ELECTRICITY AUTHORITY NOTIFICATION New Delhi, the 9th October, 2025 F No. CEA-TH-17/1/2021-TETD Division. — Whereas public notice advertising the draft of the Central Electricity Authority (Technical Standards for Construction of Electrical Plants and Electric Lines) Amendment Regulations, 2025, was published in six newspaper dailies, as required by sub-section (3) of section 177 of the Electricity Act, 2003 (36 of 2003) read with sub-rule (2) of rule 3 of the Electricity (Procedure for Previous Publication) Rules, 2005, for inviting objections and suggestions from all persons likely to be affected thereby, within the period of thirty days, from the date on which the copies of the said draft regulations were made available to the public; And whereas copy of the public notice as advertised in the newspapers and the said draft regulations were made available to the public on the website of the Central Electricity Authority on 01st May, 2025; And whereas the objections and suggestions were received from the public on the said draft regulations were considered by the Central Electricity Authority; Now, therefore, in exercise of the powers conferred under clause (e) of sub-section (2) of section 177 of the Electricity Act, 2003 (36 of 2003) read with clause (b) of section 73 of the said Act, the Central Electricity Authority hereby makes the following regulations to amend the Central Electricity Authority (Technical Standards for Construction of Electrical Plants and Electric Lines) Regulations, 2022, namely: 1. Short title and commencement.- (1) These regulations may be called the Central Electricity Authority (Technical Standards for Construction of Electrical Plants and Electric Lines) Amendment Regulations, 2025. (2) They shall come into force on the date of their publication in the Official Gazette. 2. In the Central Electricity Authority (Technical Standards for Construction of Electrical Plants and Electric Lines), 2022 (hereinafter referred to as the said regulations), in sub-regulation (4) of regulation 84, the following provisos shall be inserted, namely: - ""Provided that if the considered Right-of-Way values are different from the specified Right-of-Way values in SCHEDULE-VII, due to change in conductor configuration or conductor type or due to use of new technological options, the same shall be referred to the Authority for approval before implementation: Provided further that the Authority, after due consideration, shall issue a separate order in that regard for each of such cases."" 3. In the said regulations, in the SCHEDULE-VII for SCHEDULE-VII, the following SCHEDULE shall be substituted, namely:- "SCHEDULE-VII (See sub-regulation (4) of regulation 84) Table 1 Right-of-Way (RoW) for normal route, forest area, urban area, populated area and approach section near substation for Lattice Structures with ACSR conductor | Voltage level | Configuration | Conductor type | Terrain | Design Span(m) | String Type | Right-of-Way (RoW) width(m) | |:--------------|:--------------|:---------------|:-------------------------------------------------------------------------|:---------------|:--------------------------------|:----------------------------| | 765kV D/C | Vertical | ACSR ZEBRA | Normal route without constraint | 400 | "I" String "V" String Tension String | 67 | | | | | Forest | 300 | "V" String Tension String | 56 | | | | | Urban area or populated area or approach section near substation | 250 | "V" String Tension String | 54 | | 765kV S/C | Vertical/Delta| ACSR BERSIMIS | Normal route without constraint | 400 | "I" String "V" String Tension String | 64 | | | | | Forest | 300 | "V" String Tension String | 54 | | | | | Urban area or populated area or approach section near substation | 250 | "V" String Tension String | 52 | | 765kV S/C | Horizontal | ACSR BERSIMIS | Normal route without constraint | 400 | "I" String "V" String Tension String | 74 | | | | | Forest | 300 | "V" String Tension String | 65 | | | | | Urban area or populated area or approach section near substation | 250 | "V" String Tension String | 62 | | ±800kV HVDC | Horizontal | ACSR Lapwing | Normal route without constraint or Forest or Urban area | 400 | "Y" String | 69 | | ±500kV HVDC | Horizontal | ACSR Lapwing | Normal route without constraint or Forest or Urban area | 400 | "V" String | 52 | | 400kV D/C | Vertical | ACSR MOOSE | Normal route without constraint | 400 | "I" String "V" String Tension String | 46 | | | | | Forest | 300 | "V" String Tension String | 40 | | | | | Urban area or populated area or approach section near substation | 250 | "V" String Tension String | 38 | | 400kV S/C | Horizontal/ | ACSR MOOSE | Normal route without constraint | 400 | "I" String "V" String Tension String | 52 | | | Vertical | | Forest | 300 | "V" String Tension String | 47 | | | | | Urban area or populated area or approach section near substation | 250 | "V" String Tension String | 44 | | 1200kV | Horizontal | ACSR Moose | Normal route without constraint or Forest or Urban area | 400 | "V" String | 89 | | 220kV D/C | Vertical | ACSR ZEBRA | Normal route without constraint | 350 | "I" String "V" String Tension String | 32 | | | | | Forest | 300 | "V" String Tension String | 28 | | | | | Urban area or populated area or approach section near substation | 200 | "V" String Tension String | 24 | | 132kV D/C | Vertical | ACSR PANTHER | Normal route without constraint | 320 | "I" String "V" String Tension String | 25 | | | | | Forest | 200 | "V" String Tension String | 21 | | 110 kV D/C | Vertical | ACSR PANTHER | Normal route without constraint | 305 | "I" String "V" String Tension String | 22 | | | | | Forest | 200 | "V" String Tension String | 19 | | | | | Urban area or populated area or approach section near substation | 150 | "V" String Tension String | 17 | | 66 kV | Vertical | ACSR PANTHER | Normal route without constraint | 250 | "I" String "V" String Tension String | 18 | | | | | Forest | 150 | "V" String Tension String | 14 | | | | | Urban area or populated area or approach section near substation | 100 | "V" String | 13 | Table 2 Right-of-Way (RoW) for Normal Route, Forest Area, Urban Area or Populated Area or Approach Section near Substation for Pole Structures with ACSR conductor | Voltage Level | Configuration | Conductor type | Terrain | Design Span (m) | String Type | Right-of-Way (ROW) width (m) | |:--------------|:--------------|:---------------|:-------------------------------------------------------------------------|:----------------|:------------------------|:-----------------------------| | 765 kV S/C | Vertical DELTA| ACSR BERSIMIS | Normal route without constraints | 250 | Tension String "I" String | 52 | | | | | Forest area Urban area or Populated area or approach section near substation | 250 | Tension String "V" String | 46 | | 400 kV D/C | Vertical | ACSR MOOSE | Normal route without constraint | 250 | Tension String "I" String | 36 | | | | | Forest area Urban area or Populated area or approach section near substation | 250 | Tension String "V" String | 31 | | 220 kV D/C | Vertical | ACSR ZEBRA | Normal route without constraint | 350 | Tension String "I" String | 31 | | | | | Forest area | 250 | Tension String "I" String "V" String | 26 | | | | | Urban area or Populated area or approach section near substation | 200 | Tension String "I" String | 24 | | 132 kV D/C | Vertical | ACSR Panther | Normal route without constraint | 325 | "V" String Tension String "I" String | 25 | | | | | Forest area | 200 | Tension String "I" String | 20 | | | | | Urban area or Populated area or approach section near substation | 150 | "V" String Tension String "I" String | 18 | | 110 kV D/C | Vertical | ACSR Lynx | Urban area or Populated area or approach section near substation | 150 | "V" String Tension String "I" String | 16 | Table 3 Right-of-Way (RoW) for Normal Route, Forest Area, Urban Area or Populated Area or Approach Section near Substation for Pole Structures with HTLS conductor | Voltage Level | Configuration | Conductor type | Terrain | Design Span (m) | String Type | Right-of-Way (RoW) width (m) | |:--------------|:--------------|:------------------|:-------------------------------------------------------------------------|:----------------|:------------------------|:-----------------------------| | 400 kV D/C | Vertical | CFCC Dia:31.77mm | Normal route without constraint | 250 | Tension String "I" String | 34 | | | | | Forest area Urban area or Populated area or approach section near substation | 250 | Tension String "V" String | 29 | | 400kV D/C | Vertical | ACSS Dia:37.77mm | Normal route without constraint | 250 | Tension String "I" String | 39 | | | | | Forest area Urban area or Populated area or approach section near substation | 250 | Tension String "V" String | 33 | | 400kV D/C | Vertical | GAP Dia:29.9mm | Normal route without constrain | 250 | Tension String "I" String | 37 | | | | | Forest area Urban area or Populated area or approach section near substation | 250 | Tension String "V" String | 31 | | 220kV D/C | Vertical | CFCC Dia:28.14mm | Normal route without constraint | 350 | Tension String "I" String "V" String | 26 | | | | | Forest area | 250 | Tension String "I" String "V" String | 23 | | | | | Urban area or Populated area or approach section near substation | 200 | Tension String "I" String "V" String | 22 | | 220kV D/C | Vertical | ACSS Dia:28.04mm | Normal route without constraint | 350 | Tension String "I" String "V" String | 33 | | | | | Forest area | 250 | Tension String "I" String "V" String | 27 | | | | | Urban area or Populated area or approach section near substation | 200 | Tension String "I" String "V" String | 25 | | 220kV D/C | Vertical | GAP Dia:27.1mm | Normal route without constraint | 350 | Tension String "I" String "V" String | 31 | | | | | Forest area | 250 | Tension String "I" String "V" String | 26 | | | | | Urban area or Populated area or approach section near substation | 200 | Tension String "I" String "V" String | 24 | | 132 kV D/C | Vertical | CFCC Dia:21 mm | Normal route without constraint | 320 | Tension String "I" String "V" String | 22 | | | | | Forest area | 200 | Tension String "I" String "V" String | 18 | | | | | Urban area or Populated area or approach section near substation | 150 | Tension String "I" String "V" String | 17 | | 132 kV D/C | Vertical | ACSS Dia:20.5 mm | Normal route without constraint | 320 | Tension String "I" String "V" String | 26 | | | | | Forest area | 200 | Tension String "I" String "V" String | 21 | | | | | Urban area or Populated area or approach section near substation | 150 | Tension String "I" String "V" String | 19 | | 132 kV D/C | Vertical | GAP Dia:20.60mm | Normal route without constraint | 320 | Tension String "I" String "V" String | 25 | | | | | Forest area | 200 | Tension String "I" String "V" String | 20 | | | | | Urban area or Populated area or approach section near substation | 150 | Tension String "I" String "V" String | 19 | | 66 kV D/C | Vertical | CFCC Dia: 21 mm | Normal route without constraint | 250 | "I" string “V” String Tension String | 16 | | | | | Forest | 150 | "V" String Tension String | 13 | | | | | Urban or Populated on approach section near substation | 100 | “V” String Tension String | 12 | | 66 kV D/C | Vertical | ACSS Dia: 20.5 mm | Normal route without constraint | 250 | "I" string "V" String Tension String | 20 | | | | | Forest | 150 | "V" String Tension String | 16 | | | | | Urban or Populated on approach section near substation | 100 | "V" String Tension String | 14 | | 66 kV D/C | Vertical | GAP Dia: 20.6 mm | Normal route without constraint | 250 | "I" string "V" String Tension String | 21 | | | | | Forest | 150 | "V" String Tension String | 14 | | | | | Urban or Populated on approach section near substation | 100 | "V" String Tension String | 13 | Table 4 Right-of-Way (RoW) for Normal Route, Forest Area, Urban Area or Populated Area or approach Section near Substation for Lattice Tower Structures and HTLS conductor | Voltage level (kV) | Configuration | Conductor type | Terrain | Design Span (m) | String Type | Right-of-Way (ROW) width (m) | |:-------------------|:--------------|:------------------|:-------------------------------------------------------------------------|:----------------|:------------------------|:-----------------------------| | 400 kV D/C | Vertical | CFCC Dia:31.77mm | Normal route without constraint | 400 | "I" string "V" String Tension String | 43 | | | | ACSS Dia:37.77mm | Normal route without constraint | 400 | "I" string "V" String Tension String | 50 | | | | GAP Dia:29.9 mm | Normal route without constraint | 400 | "I" string "V" String Tension String | 48 | | | | CFCC Dia:31.77mm | Forest | 300 | “V” String Tension String | 38 | | | | ACSS Dia:37.77mm | Forest | 300 | "V" String Tension String | 43 | | | | GAP Dia:29.9mm | Forest | 300 | "V" String Tension String | 41 | | | | CFCC Dia:31.77mm | Urban or Populated on approach section near substation | 250 | "V" String Tension String | 35 | | | | ACSS Dia:37.77mm | Urban or Populated or approach section near substation | 250 | "V" String Tension String | 40 | | | | GAP Dia:29.9mm | Urban or Populated or approach section near substation | 250 | "V" String Tension String | 38 | | 220 kV D/C | Vertical | CFCC Dia:28.14mm | Normal route without constraint | 350 | "I" string "V" String Tension String | 27 | | | | ACSS Dia:28.04mm | Normal route without constraint | 350 | "I" string "V" String Tension String | 33 | | | | GAP Dia:27.1mm | Normal route without constraint | 350 | "I" string "V" String Tension String | 31 | | | | CFCC Dia:28.14mm | Forest | 300 | "V" String Tension String | 24 | | | | ACSS Dia:28.04mm | Forest | 300 | "V" String Tension String | 30 | | | | GAP Dia:27.1mm | Forest | 300 | "V" String Tension String | 28 | | | | CFCC Dia:28.14mm | Urban or Populated or approach section near substation | 250 | "V" String Tension String | 23 | | | | ACSS Dia:28.04mm | Urban or Populated or approach section near substation | 250 | "V" String Tension String | 27 | | | | GAP Dia:27.1mm | Urban or Populated or approach section near substation | 250 | "V" String Tension String | 26 | | 132 kV D/C | Vertical | CFCC Dia:21 mm | Normal route without constraint | 320 | "I" string "V" String Tension String | 22 | | | | ACSS Dia:20.5 mm | Normal route without constraint | 320 | "I" string "V" String Tension String | 27 | | | | GAP Dia:20.60mm | Normal route without constraint | 320 | "I" string "V" String Tension String | 26 | | | | CFCC Dia:21 mm | Forest | 200 | "V" String Tension String | 19 | | | | ACSS Dia:20.5 mm | Forest | 200 | "V" String Tension String | 22 | | | | GAP Dia:20.60mm | Forest | 200 | "V" String Tension String | 21 | | | | CFCC Dia:21 mm | Urban or populated or approach section near substation | 150 | "V" String Tension String | 18 | | | | ACSS Dia:20.5 mm | Urban or populated or approach section near substation | 150 | "V" String Tension String | 20 | | | | GAP Dia:20.60mm | Urban or populated or approach section near substation | 150 | "V" String Tension String | 19 | | 66 kV D/C | Vertical | CFCC Dia: 21 mm | Normal route without constraint | 250 | "I" string “V” String Tension String | 16 | | | | ACSS Dia: 20.5 mm | Normal route without constraint | 250 | "I" string "V" String Tension String | 20 | | | | GAP Dia: 20.6 mm | Normal route without constraint | 250 | "I" string "V" String Tension String | 21 | | | | CFCC Dia: 21 mm | Forest | 150 | "V" String Tension String | 13 | | | | ACSS Dia: 20.5 mm | Forest | 150 | "V" String Tension String | 16 | | | | GAP Dia: 20.6 mm | Forest | 150 | "V" String Tension String | 14 | | | | CFCC Dia:21 mm | Urban or Populated on approach section near substation | 100 | “V” String Tension String | 12 | | | | ACSS Dia: 20.5 mm | Urban or Populated or approach section near substation | 100 | "V" String Tension String | 14 | | | | GAP Dia: 20.6 mm | Urban or Populated or approach section near substation | 100 | "V" String Tension String | 13 | Note: (a) D/C: double circuit; S/C: single circuit; (b) for Carbon Fiber Composite Core (CFCC), Sag is calculated at 180 °C; for Aluminum Conductor Steel Supported (ACSS), Sag is calculated at 250 °C; for Gap-type Aluminum Conductor Steel Reinforced (GAP conductor), Sag is calculated at 210 °C. (c) during the process of determining Right-of-Way (RoW) width, all the electrical clearances and safety parameters including minimum live metal clearance, ground clearance, surface gradient, corona loss, Radio Interference Voltage (RIV), Audible Noise and minimum mid-span separation between earth wire and conductor, Electromagnetic Field (EMF i.e. induced voltages etc.) exposure limits and design consideration for tower structure, shall be as per relevant standards and Central Electricity Authority regulations. (d) in the above Tables, the terms, “Forest”, “Urban”, “Populated", and "Approach Section Near Substation" shall be understood in the context of extreme difficulty in the availability of transmission corridor [Right-of-Way (RoW) corridor] for laying transmission lines. (e) pole structure may be in any shape. It may be generally considered as a tapered hollow circular or hexagonal or octagonal or multiple-side steel tube or pipe and it includes both mono pole structure and twin-pole structure.". RAKESH KUMAR, Secy. [ADVT.-III/4/Exty./404/2025-26] Note: The principal regulations were published in the Gazette of India, Extraordinary, Part III, Section 4, vide notification No. CEA-TH-17/1/2021-TETD Division, dated the 23rd December, 2022. Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064 and Published by the Controller of Publications, Delhi-110054. GORAKHA NATH Digitally signed by GORAKHA YADAVA NATH YADAVA Date: 2025.10.13 16:18:19 +05'30'

Never miss important gazettes

Create a free account to save gazettes, add notes, and get email alerts for keywords you care about.

Sign Up Free