Notification of the final Phasing Plan for implementation of flexible operation of coal-based thermal generating units under sub-regulation (2) of regulation 5 of the Central Electricity Authority (Flexible Operation of Coal based Thermal Generating Units) Regulations, 2023.

Detailed Summary

The Central Electricity Authority issued notification CEA-TH-14-21/5/2023-TRM Division dated 15th December 2023, finalizing the Phasing Plan required under sub-regulation (2) of regulation 5 of the Central Electricity Authority (Flexible Operation of Coal based Thermal Generating Units) Regulations, 2023, which were notified vide notification CEA-TH-17-13/4/2022-TETD Division dated 30th January 2023, after incorporating stakeholder comments; the annexed Phasing Plan requires utilities to modify units within stipulated phase durations, avail a maximum one-month shutdown period per unit, align shutdown periods with Annual Over Haul (AOH) schedules where possible, and coordinate with the respective Regional Power Committee, and identifies five phases including a Pilot Phase covering ten units totaling 5,850 MW across Central, State and Private sector generators (including NTPC, DVC, Neyveli Lignite, KPCL, GSECL, RRVUNL, WBPDC and CEPL) to be completed by March 2024, Phase I covering ninety-one units totaling 51,080 MW to be completed between July 2024 and June 2026, and Phase II covering one hundred units totaling 46,825 MW to be completed between July 2026 and June 2028, with unit-level details specifying organisation, project name, unit number, capacity, commissioning date, region and scheduled month across the National, Western, Southern, Eastern and North-Eastern power regions.

Full Text

EXTRAORDINARY PART III—Section 4 PUBLISHED BY AUTHORITY No. 834] NEW DELHI, FRIDAY , DECEMBER 15 , 2023/ AGRAHAYANA 24, 1945 CG-DL-E-18122023-250735 III. चरण - II IV. चरण - III -II 3 300 12/28/2011 नहीं उ. क्षे. CENTRAL E LECTRICITY AUTHORITY NOTIFICATION New Delhi, the 15th December, 2023 CEA -TH-14-21/5/2023 -TRM Division .—Whereas the Central Electricity Authority (Flexible Operation of Coal based Thermal Generating Units) Regulations, 2023 was notified by the Central E lectricity Authority vide notification no. CEA -TH-17-13/4/2022 -TETD Division dated 30th January, 2023; And whereas the sub -regulation (2) of regulation 5 of the said regulations requires that the implementation of the flexible operation of the Coal based t hermal generating Units shall be as per the Phasing Plan specified by the Authority from time to time; And whereas the phasing plan has been finalized after incorporating the comments from the stakeholders. The final phasing plan approved by the Authority is attached herein under at Annexure. Annexure (PHASING PLAN) 1. The utilities shall modify the units strictly within the duration stipulated under various phases in the Phasing Plan mentioned herein under. 2. The utilities shall avail the maximum shutdown per iod of one month as mentioned against each unit in the Phasing Plan. 3. As far as possible, the utilities shall match the shutdown period of upgradation/retrofits works for flexible operation with Annual Over Haul (AOH) period. 4. The utilities shall plan shutdo wn period of the units for upgradation/retrofits works for flexible operation in coordination with the respective Regional Power Committee (RPC). 5. The following five phases have been identified under the Phasing Plan including a Pilot Phase: I. PHASE - PILOT Duration: To be completed by March, 2024 Under this phase, the following 10 nos. of units of capacity 5850 MegaWatt (MW) in aggregate of various thermal power plants have been planned and identified for which the study, field tests, retrofits etc. have al ready been initiated for flexible operation. The upgradation/retrofitting for flexible operation to be completed before 31st March, 2024. PILOT PHASE (May, 2023 - March, 2024) Phase Sector Organisation Name of Project Unit No. Capacity (MW) Region Pilot Central NTPC MAUDA TPS 1 500 WR Pilot Central NTPC SIMHADRI 3 500 SR Pilot Central NTPC DADRI 6 490 NR Pilot Central DVC MEJIA TPS 8 500 ER Pilot Central NEYVELI LIGNITE NEYVELI NEW TPP 2 500 SR Pilot State KPCL YERMARUS TPS 1 800 SR Pilot State GSECL WANAKBORI TPP 6 800 WR Pilot State RRVUNL SURATGARH SCTPP 8 660 NR Pilot State WBPDC SAGARDIGHI TPS 3 500 ER Pilot Private CEPL MUTHIARA 2 600 SR Pilot Phase Total 10 5850 II. PHASE -I Duration: July, 2024 to June, 2026 Under this phase, the followi ng 91 Nos. of units of capacity 51080 MW in aggregate of various thermal power plants have been planned and identified for the upgradation/retrofitting for flexible operation including the study and field tests. This phase to be completed within 2 years i. e. from July, 2024 to June, 2026. PHASE 1 ( JULY , 2024 - JUNE , 2026) Year Month Phase Sector Organisation Name of Project Unit No. Capacit y (MW) Date of Commission ing Pit head Regio n 2024 November Phase 1 State UPRVUNL HARDUAGANJ TPS 10 660 1/29/2 022 N NR 2024 November Phase 1 Private GPGSL (GVK) GOINDWAL SAHIB 2 270 3/15/2016 N NR 2024 November Phase 1 State APPDCL DAMODARAM SANJEEVAIAH TPS 3 800 3/9/2023 N SR 2024 November Phase 1 State TSGENCO BHADRADRI TPP 4 270 1/9/2022 N SR 2024 November Phase 1 State TANGEDCO METTUR TPS -II 1 600 10/11/2012 N SR 2024 November Phase 1 Central NTPC GADARWARA TPP 2 800 2/16/2021 N WR 2024 November Phase 1 Private RKMPPL UCHPINDA TPP 3 360 9/12/2017 N WR 2024 November Phase 1 Central NTPC MAUDA TPS 3 660 3/28/2016 N WR 2024 November Phase 1 Private APL MUNDRA TPS 8 660 3/3/2012 N WR 2024 November Phase 1 Central DVC BOKARO TPS `A` EXP 1 500 3/22/2016 N ER November Total 10 5580 2024 December Phase 1 Central NTPC TANDA TPS 6 660 3/31/2021 N NR 2024 December Phase 1 Private GPGSL (GVK) GOINDWAL SAHIB 1 270 2/14/2016 N NR 2024 December Phase 1 Private ITPCL ITPCL TPP 2 600 4/18/2016 N SR 2024 December Phase 1 Private HNPC VIZAG TPP 2 520 3/30/2016 N SR 2024 December Phase 1 Central NTPC SIMHADRI 4 500 3/30/2012 N SR 2024 December Phase 1 Central NTPC LARA TPP 2 800 7/12/2020 N WR 2024 December Phase 1 Private RATTANINDI A NASIK (P) TPS 5 270 5/30/2017 N WR 2024 December Phase 1 Private APL RAIKHEDA TPP 2 685 3/28/2016 N WR 2024 December Phase 1 Private CGPL MUNDRA UMTPP 1 800 2/25/2012 N WR 2024 December Phase 1 Private IBPIL UTKAL TPP (IND BARATH) 1 350 2/25/2016 N ER December Total 10 5455 2025 January Phase 1 Central NTPC MEJA STPP 2 660 1/12/2021 N NR 2025 January Phase 1 Private SPPL Thoothukudi St IV 1 525 11/30/2021 N SR 2025 January Phase 1 State SCCL SINGARENI TPP 1 600 3/13/2016 N SR 2025 January Phase 1 Central NTECL VALLUR TPP 1 500 3/28/2012 N SR 2025 January Phase 1 Central NTPC KHARGONE STPP 2 660 3/24/2020 N WR 2025 Janua ry Phase 1 Private RATTANINDIA NASIK (P) TPS 4 270 5/19/2017 N WR 2025 January Phase 1 Private BALCO BALCO TPS 2 300 3/24/2016 N WR 2025 January Phase 1 Central DVC RAGHUNATHPU R TPP 2 600 1/18/2016 N ER January Total 8 4115 2025 Februrary Phase 1 State RRVUNL Suratgarh SCTPP 7 660 3/15/2020 N NR 2025 Februrary Phase 1 Central NTPC UNCHAHAR TPS 5 210 9/28/2006 N NR 2025 Februrary Phase 1 State TSGENCO BHADRADRI TPP 3 270 3/26/2021 N SR 2025 Februrary Phase 1 State KPCL BELLARY TPS 3 700 3/1/2016 N SR 2025 Februrary Phase 1 Central NTPC KHARGONE STPP 1 660 9/29/2019 N WR 2025 Februrary Phase 1 Private SKS BINJKOTE TPP 2 300 4/25/2017 N WR 2025 Februrary Phase 1 Private JHAPL SEIONI TPP 1 600 3/22/2016 N WR 2025 Februrary Phase 1 Central NTPC KUDGI STPP 1 800 12/25/2016 N SR February Total 8 4200 2025 March Phase 1 Central NTPC TANDA TPS 5 660 9/28/2019 N NR 2025 March Phase 1 State TSGENCO BHADRADRI TPP 2 270 12/7/2020 N SR 2025 March Phase 1 Private SEIL PAINAMPURAM TPP 2 660 9/3/2015 N SR 2025 March Phase 1 Private TRNE NAWAPARA TPP 2 300 4/18/2017 N WR 2025 March Phase 1 State MAHAGENCO CHANDRAPUR(MA HARASHTRA) STPS 9 500 3/21/2016 N WR 2025 March Phase 1 Private TSPL TALWANDI SABO TPP 3 660 3/29/2016 N NR 2025 March Phase 1 State CSPGCL MARWA TPS 2 500 7/15/2016 N WR 2025 March Phase 1 Private CGPL MUNDRA UMTPP 3 800 10/16/2012 N WR 2025 March Phase 1 State SCCL SINGARENI TPP 2 600 11/25/2016 N SR March Total 9 4950 2025 July Phase 1 State RRVUNL CHHABRA TPP 6 660 3/29/2019 N NR 2025 July Phase 1 State TSGENCO BHADRADRI TPP 1 270 6/5/2020 N SR 2025 July Phase 1 Central NTPL Thoothukudi (JV) TPP 2 500 7/9/2015 N SR 2025 July Phase 1 Central NTPC GADARWARA TPP 1 800 3/29/2019 N WR 2025 July Phase 1 Private RATTANINDIA NASI K (P) TPS 3 270 4/14/2017 N WR 2025 July Phase 1 Private SEIL SGPL TPP 1 660 11/12/2016 N SR 2025 July Phase 1 State MAHAGENCO KORADI TPS 9 660 3/15/2016 N WR July Total 7 3820 2025 November Phase 1 Central NTPC MEJA STPP 1 660 3/31/2018 N NR 2025 November Phase 1 State TSGENCO KOTHAGUDEM TPS (STAGE -7) 12 800 12/26/2018 N SR 2025 November Phase 1 State APPDCL DAMODARAM SANJEEVAIAH TPS 2 800 3/17/2015 N SR 2025 November Phase 1 State MPPGCL SHREE SINGAJI TPP 4 660 3/27/2019 N WR 2025 November Phase 1 Central NTPC SOLAPUR STPS 1 660 4/7/2017 N WR 2025 November Phase 1 Private RKMPPL UCHPINDA TPP 2 360 1/28/2016 N WR 2025 November Phase 1 Central NTECL VALLUR TPP 2 500 2/28/2013 N SR 2025 November Phase 1 Private CGPL MUNDRA UMTPP 2 800 7/17/2012 N WR 2025 November Phase 1 Private SPPL SHIRPUR TPP 1 150 9/28/2017 N WR November Total 9 5390 2025 December Phase 1 Central NTPC KUDGI STPP 3 800 3/12/2018 N SR 2025 December Phase 1 Central NTPL Thoothukudi (JV) TPP 1 500 3/10/2015 N SR 2025 December Phase 1 Private RKMPPL UCHPINDA TPP 4 360 3/20/2019 N WR 2025 December Phase 1 Central NTPC MAUDA TPS 4 660 3/18/2017 N WR 2025 December Phase 1 State TANGEDCO NORTH CHENNAI TPS 4 600 9/13/2013 N SR 2025 December Phase 1 Central NTPC LARA TPP 1 800 3/23/2018 N WR 2025 December Phase 1 Private RATTANINDIA AMARAVATI 5 270 3/12/2015 N WR December Total 7 3990 2026 January Phase 1 State RRVUNL CHHABRA TPP 5 660 4/4/2017 N NR 2026 January Phase 1 State APGENCO RAYALASEEMA TPS 6 600 3/12/2018 N SR 2026 January Phase 1 Private SEIL PAINAMPURAM TPP 1 660 2/7/2015 N SR 2026 January Phase 1 State MPPGCL SHREE SINGAJI TPP 3 660 11/18/2018 N WR 2026 January Phase 1 Private RATTANINDIA NASIK (P) TPS 2 270 2/15/2017 N WR 2026 January Phase 1 State TANGEDCO NORTH CHENNAI TPS 5 600 3/9/2013 N SR 2026 January Phase 1 Private APL MUNDRA TPS 9 660 3/9/2012 N WR 2026 January Phase 1 Private WPCL AKALTARA TPS 2 600 1/18/2018 N WR 2026 January Phase 1 Central NTPC MAUDA TPS 2 500 3/29/2013 N WR January T otal 9 5210 2026 Februrary Phase 1 Central NTPC UNCHAHAR TPS 6 500 3/31/2017 N NR 2026 Februrary Phase 1 State KPCL YERMARUS TPP 2 800 3/29/2017 N SR 2026 Februrary Phase 1 State APPDCL DAMODARAM SANJEEVAIAH TPS 1 800 8/28/2014 N SR 2026 Februrary Phase 1 Private APL MAHAN TPP 2 600 10/7/2018 N WR 2026 Februrary Phase 1 State MAHAGENCO KORADI TPS 10 660 12/28/2016 N WR 2026 Februrary Phase 1 Central NTPC SOLAPUR STPS 2 660 3/30/2019 N WR 2026 Februrary Phase 1 Private CGPL MUNDRA UMTPP 5 800 3/18/ 2013 N WR February Total 7 4820 2026 March Phase 1 Central NTPC KUDGI STPP 2 800 3/23/2017 N SR 2026 March Phase 1 Central NTECL VALLUR TPP 3 500 2/28/2014 N SR 2026 March Phase 1 Private SKS BINJKOTE TPP 1 300 3/28/2018 N WR 2026 March Phase 1 Private TRNE NAWAPARA TPP 1 300 8/14/2016 N WR 2026 March Phase 1 State MAHAGENCO PARLI TPS 8 250 3/30/2016 N WR 2026 March Phase 1 Private MBPMPL ANUPPUR TPP 2 600 3/30/2016 N WR 2026 March Phase 1 Private CGPL MUNDRA UMTPP 4 800 1/16/2013 N WR March Total 7 3550 TOTAL UNITS AND CAPACITY (Phase I) 91 51080 III. PHASE -II Duration: July, 2026 to June, 2028 Under this phase, the following 100 Nos. of units of capacity 46825 MW in aggregate of various thermal power plants have been planned and identif ied for the upgradation/retrofitting for flexible operation including the study and field tests. This phase to be completed within 2 years i.e. from July, 2026 to June, 2028. PHASE II (JULY,2026 - JUNE ,2028) Year Month Sector Organisation Name of Pr oject Unit No. Capacity (MW) Date of Commissioning Pit head Region 2026 July Private RKMPPL UCHPINDA TPP 1 360 10/28/2015 N WR 2026 July Private JPL TAMNAR TPP 1 600 1/7/2015 N WR 2026 July Private DBPCL BARADARHA TPS 1 600 2/23/2014 N WR 2026 July Private APL MAHAN TPP 1 600 2/24/2013 N WR 2026 July Private SEIL SGPL TPP 2 660 2/15/2017 N SR 2026 July Central NTPC NORTH KARANPURA STPP 1 660 1/18/2023 N ER 2026 July Private ADHUNIK MAHADEV PRASAD STPP 2 270 3/29/2013 N ER 2026 July Central NTPC BONG AIGAON TPP 3 250 3/23/2019 N NER July Total 8 4000 2026 August State GSECL SIKKA REP. TPS 4 250 9/25/2015 N WR 2026 August State MPPGCL SHREE SINGAJI TPP 2 600 10/15/2014 N WR 2026 August Private RATTANINDIA AMARAVATI TPS 2 270 2/17/2014 N WR 2026 August Private GMR ENERG GMR WARORA TPS 1 300 2/7/2013 N WR 2026 August State TSGENCO KAKATIYA TPS 2 600 12/31/2015 N SR 2026 August Central NPGCL NABINAGAR STPP 3 660 3/6/2022 N ER 2026 August Central NTPC MUZAFFARPUR TPS 4 195 3/24/2016 N ER 2026 August Private GMR ENERG KAMALANGA TPS 1 350 3/29/2013 N ER August Total 8 3225 2026 November Private MCCPL BANDAKHAR TPP 1 300 6/19/2015 N WR 2026 November Private APL TIRORA TPS 5 660 9/25/2014 N WR 2026 November State MPPGCL SATPURA TPS 11 250 12/25/2013 N WR 2026 November Private HNPC VIZAG TPP 1 520 12/27/2015 N SR 2026 November Central NTPC NABI NAGAR TPP 4 250 11/10/2021 N ER 2026 November Central DVC KODARMA TPP 2 500 2/15/2013 N ER 2026 November Central NTPC BONGAIGAON TPP 1 250 6/22/2015 N NER 2026 November State RRVUNL KALISINDH TPS 2 600 6/6/2015 N NR November Total 8 3330 2026 December Private BALCO BALCO TPS 1 300 6/4/2015 N WR 2026 December Private JPPVL NIGRI TPP 1 660 8/29/2014 N WR 2026 December State MPPGCL SHREE SINGAJI TPP 1 600 11/18/2013 N WR 2026 December Private ITPCL ITPCL TPP 1 600 9/19/2015 N SR 2026 December Central NTPC BARH I 1 660 10/30/2021 N ER 2026 December Central NTPC MUZAFFARPUR TPS 3 195 3/31/2015 N ER 2026 December Private ADHUNIK MAHADEV PRASAD STPP 1 270 11/19/2012 N ER 2026 December Private NPL RAJPURA TPP 2 700 7/6/2014 N NR December Total 8 3985 2027 January Private MBPMPL ANUPPUR TPP 1 600 4/20/2015 N WR 2027 January Private WPCL AKALTARA TPS 4 600 8/22/2014 N WR 2027 January Private DIPL DHARIWAL TPP 1 300 11/3/2013 N WR 2027 January Private CEPL MUTHIARA TPP 1 600 12/2/2014 N SR 2027 January Central NTPC NEW NABI NAGAR TPP 2 660 3/31/2021 N ER 2027 January Central NTPC BARH II 5 660 3/4/2015 N ER 2027 January Private MPL MAITHON RB TPP 2 525 3/31/2012 N ER 2027 January Private TSPL TALWANDI SABO TPP 1 660 6/17/2014 N NR January Total 8 4605 2027 February State MAHAGENCO KORADI TPS 8 660 3/30/2015 N WR 2027 February Private DIPL DHARIWAL TPP 2 300 5/28/2014 N WR 2027 February Private GMR ENERG GMR WARORA TPS 2 300 8/27/2013 N WR 2027 February Central NTPC NEW NABI NAGAR TPP 1 660 7/12/2019 N ER 2027 February Private HEL HALDIA TPP 2 300 2/16/2015 N ER 2027 February Central DVC DURGAPUR STEEL TPS 2 500 3/23/2012 N ER 2027 February State RRVUNL KALISINDH TPS 1 600 5/2/2014 N NR February Total 7 3320 2027 March State GSECL SIKKA REP. TPS 3 250 3/29/2015 N WR 2027 March Private VVL SALORA TPP 1 135 4/10/2014 N WR 2027 March Private WPCL AKALTARA TPS 3 600 8/13/2013 N WR 2027 March State MAHAGENCO BHUSAWAL TPS 5 500 3/30/2012 N WR 2027 March Private JITPL DERANG TPP 2 600 1/24/2015 N ER 2027 March Private LPGCL LALITPUR TPS 1 660 3/26/2016 N NR 2027 March Private NPL RAJPURA TPP 1 700 1/24/2014 N NR March Total 7 3445 2027 July State MAHAGENCO CHANDRAPUR(MAHA RASHTRA) STPS 8 500 3/29/2015 N WR 2027 July Private APL AVANTHA BHANDAR 1 600 3/31/2014 N WR 2027 July Private APL TIRORA TPS 3 660 6/10/2013 N WR 2027 July Private HEL HALDIA TPP 1 300 1/14/2015 N ER 2027 July State WBPDC SAGARDIGHI TPS 4 500 12/15/2016 N ER 2027 July Private TSPL TALWANDI SABO TPP 2 660 10/25/2015 N NR 2027 July Private APL KAWAI TPS 2 660 12/24/2013 N NR July Total 7 3880 2027 August Private JPL TAMNAR TPP 4 600 3/28/2015 N WR 2027 August Private VIP BUTIBORI TPP 1 300 3/31/2014 N WR 2027 August Private JPPVL BINA TPS 2 250 3/31/2013 N WR 2027 August Central NTPC NABI NAGAR TPP 3 250 2/26/2019 N ER 2027 August Central DVC RAGHUNATHPUR TPP 1 600 8/24/2014 N ER 2027 Augus t Private LPGCL LALITPUR TPS 2 660 1/8/2016 N NR 2027 August Private APL KAWAI TPS 1 660 5/28/2013 N NR August Total 7 3320 2027 November Private DBPCL BARADARHA TPS 2 600 3/24/2015 N WR 2027 November State CSPGCL MARWA TPS 1 500 3/30/2014 N WR 2027 November Private APL TIRORA TPS 2 660 3/25/2013 N WR 2027 November Central NTPC BARAUNI TPS 9 250 3/31/2018 N ER 2027 November Private JITPL DERANG TPP 1 600 4/10/2014 N ER 2027 November Private PPGCL PRAYAGRAJ TPP 2 660 9/6/2016 N NR 2027 November State UPRVUNL PARICHHA TPS 6 250 3/11/2013 N NR November Total 7 3520 2027 December Private RATTANINDIA AMARAVATI TPS 4 270 3/4/2015 N WR 2027 December Private JPL TAMNAR TPP 3 600 3/30/2014 N WR 2027 December Central NTPC BARAUNI TPS 8 250 1/11/20 18 N ER 2027 December State DPL D.P.L. TPS 8 250 3/31/2014 N ER 2027 December Central NTPC NABI NAGAR TPP 1 250 3/20/2016 N ER 2027 December Private PPGCL (Tata) PRAYAGRAJ TPP 3 660 5/22/2017 N NR December total 6 2280 2028 January Private JPPVL NIGRI TPP 2 660 2/27/2015 N WR 2028 January Private APL TIRORA TPS 4 660 3/23/2014 N WR 2028 January State MPPGCL SATPURA TPS 10 250 3/22/2013 N WR 2028 January Private HMEL Hiranmaye TPP 2 150 12/31/2017 N ER 2028 January Private GMR ENERG KAMALANGA TP S 3 350 3/21/2014 N ER 2028 January Private LPGCL LALITPUR TPS 3 660 4/1/2016 N NR January Total 6 2730 2028 February Private APL RAIKHEDA TPP 1 685 2/24/2015 N WR 2028 February Private JPL TAMNAR TPP 2 600 3/10/2014 N WR 2028 February Private IEPL BELA TPS 1 270 3/20/2013 N WR 2028 February Private HMEL Hiranmaye TPP 1 150 6/7/2017 N ER 2028 February Central NTPC BONGAIGAON TPP 2 250 3/22/2017 N NER 2028 February Private RATTANINDIA AMARAVATI TPS 1 270 3/25/2013 N WR 2028 February Central NTPC BARH II 4 660 11/20/2013 N ER February Total 7 2885 2028 March Private RATTANINDIA AMARAVATI TPS 3 270 1/29/2015 N WR 2028 March Private RATTANINDIA NASIK (P) TPS 1 270 2/25/2014 N WR 2028 March State GSECL UKAI TPS 6 500 3/5/2013 N WR 2028 March Central NTPC NABI NAGAR TPP 2 250 4/3/2017 N ER 2028 March Private PPGCL (Tata) PRAYAGRAJ TPP 1 660 12/25/2015 N NR 2028 March Private GMR ENERG KAMALANGA TPS 2 350 9/28/2013 N ER March Total 6 2300 TOTAL UNITS AND CAPACITY (Phase II) 100 4682 5 IV. PHASE -III Duration: July, 2028 to December, 2029 Under this phase, the following 101 Nos. of units of capacity 37215 MW in aggregate of various thermal power plants have been planned and identified for the upgradation/retrofitting for flexible opera tion including the study and field tests. This phase to be completed within a period of 18 months i.e. from July, 2028 to December, 2029. PHASE III ( JULY , 2028 - DEC, 2029) Year Month Sector Organisation Name of Project Unit No. Capacity (MW) Date o f Commissioning Pithead Region 2028 July Private RPSCL ROSA TPP Ph -II 3 300 12/28/2011 N NR 2028 July State UPRVUNL PARICHHA TPS 3 210 3/29/2006 N NR 2028 July Central NEYVELI LIGNITE NEYVELI NEW TPP 1 500 12/20/2019 Y SR 2028 July State APGENC O RAYALASEEMA TPS 4 210 11/20/2007 N SR 2028 July Private APL MUNDRA TPS 7 660 11/7/2011 N WR 2028 July Private JSWEL JSW RATNAGIRI TPP 1 300 8/24/2010 N WR 2028 July Private JPL OP JINDAL TPS 4 250 6/17/2008 N WR 2028 July Central NTPC DARLIPALI STPS 2 800 7/21/2021 Y ER 2028 July State WBPDC BAKRESWAR TPS 5 210 12/24/2007 N ER July Total 9 3440 2028 August State UPRVUNL HARDUAGANJ TPS 8 250 9/27/2011 N NR 2028 August State TSGENCO KOTHAGUDEM TPS (NEW) 11 500 6/26/2011 N SR 2028 August State APGENCO RAYALASEEMA TPS 3 210 1/25/2007 N SR 2028 August Private JSWEL JSW RATNAGIRI TPP 4 300 10/8/2011 N WR 2028 August Private APL MUNDRA TPS 3 330 8/2/2010 N WR 2028 August Central NSPCL BHILAI TPS 1 250 4/20/2008 N WR 2028 August Central NTPC DARLIPALI STPS 1 800 12/30/2019 Y ER 2028 August Private APL TIRORA TPS 1 660 9/11/2012 N WR 2028 August Central NTPC INDIRA GANDHI STPP 3 500 11/7/2012 N NR 2028 August State WBPDC SAGARDIGHI TPS 2 300 12/21/2007 N ER August Total 10 4100 2028 November State HPGCL RAJIV GANDHI TPS 2 600 10/1/2010 N NR 2028 November Private APL UDUPI TPP 2 600 4/16/2011 N SR 2028 November Central NEYVELI LIGNITE NEYVELI ( EXT) TPS 2 210 7/22/2003 Y SR 2028 November State MAHAGENCO KHAPARKHEDA TPS 5 500 8/5/2 011 N WR 2028 November Private WPCL WARDHA WARORA TPP 1 135 6/5/2010 N WR 2028 November Private JPL OP JINDAL TPS 3 250 3/6/2008 N WR 2028 November Central DVC DURGAPUR STEEL TPS 1 500 7/29/2011 N ER 2028 November Private JPPVL BINA TPS 1 250 8/12/2012 N WR 2028 November State DPL D.P.L. TPS 7 300 11/24/2007 N ER November Total 9 3345 2028 December Private RPSCL ROSA TPP Ph -I 2 300 6/26/2010 N NR 2028 December State APGENCO RAYALASEEMA TPS 5 210 12/31/2010 N SR 2028 December State KPCL RAICH UR TPS 7 210 12/11/2002 N SR 2028 December Private APL MUNDRA TPS 6 660 7/20/2011 N WR 2028 December State MAHAGENCO PARAS TPS 2 250 3/27/2010 N WR 2028 December Private JPL OP JINDAL TPS 2 250 2/10/2008 N WR 2028 December Central DVC KODARMA TPP 1 500 7/20/2011 N ER 2028 December Private JhPL(HR) MAHATMA GANDHI TPS 1 660 1/12/2012 N NR 2028 December State WBPDC SANTALDIH TPS 5 250 11/7/2007 N ER December Total 9 3290 2029 January State HPGCL RAJIV GANDHI TPS 1 600 3/31/2010 N NR 2029 Januar y Private APL UDUPI TPP 1 600 7/23/2010 N SR 2029 January Central NEYVELI LIGNITE NEYVELI ( EXT) TPS 1 210 10/21/2002 Y SR 2029 January Private JSWEL JSW RATNAGIRI TPP 3 300 5/6/2011 N WR 2029 January Private LANCO PATHADI TPP 2 300 3/25/2010 N WR 2029 January State CSPGCL DSPM TPS 2 250 12/11/2007 N WR 2029 January Private MPL MAITHON RB TPP 1 525 6/30/2011 N ER 2029 January Central NTPC SIMHADRI 2 500 8/24/2002 N SR 2029 January Central DVC MEJIA TPS 4 210 10/12/2004 N ER January Total 9 3495 2029 February Private RPSCL ROSA TPP Ph -I 1 300 2/10/2010 N NR 2029 February State KPCL RAICHUR TPS 8 250 6/26/2010 N SR 2029 February Private TAQA NEYVELI TPS(Z) 1 250 10/21/2002 N SR 2029 February Private WPCL WARDHA WARORA TPP 4 135 4/30/2011 N WR 2029 February Private APL MUNDRA TPS 2 330 3/17/2010 N WR 2029 February Private JPL OP JINDAL TPS 1 250 9/2/2007 N WR 2029 February State WBPDC SANTALDIH TPS 6 250 6/29/2011 N ER 2029 February Private RPSCL ROSA TPP Ph -II 4 300 3/28/2012 N NR 2029 February Private TATA PCL JOJOBERA TPS 3 120 2/1/2002 N ER February Total 9 2185 2029 March State PSPCL GH TPS (LEH.MOH.) 4 250 7/31/2008 N NR 2029 March State TSGENCO KAKATIYA TPS 1 500 5/27/2010 N SR 2029 March Private WPCL WARDHA WARORA TPP 3 135 1/21/2011 N WR 2029 March State MAHAGENCO PARLI TPS 7 250 2/10/2010 N WR 2029 March State MPPGCL SANJAY GANDHI TPS 5 500 6/18/2007 N WR 2029 March Private SEL STERLITE TPP 2 600 12/29/2010 N ER 2029 March Private EPGL SALAYA TPP 2 600 6/13/2012 N WR 2029 March State MAHAGENCO BHUSAWAL TPS 4 500 3/7/2012 N WR 2029 March State WBPDC BAKRESWAR TPS 4 210 3/21/2001 N ER March Total 9 3545 2029 July State HPGCL YAMUNA NAGAR TPS 2 300 3/29/2008 N NR 2029 July State APGENCO Dr. N.TATA RAO TPS 7 500 10/8/2009 N SR 2029 July Private APL MUNDRA TPS 5 660 12/26/2010 N WR 2029 July Private APL MUNDRA TPS 1 330 8/4/2009 N WR 2029 July State MAHAGENCO PARAS TPS 1 250 5/31/2007 N WR 2029 July Private SEL STERLITE TPP 1 600 10/14/2010 N ER 2029 July Central NTPC INDIRA GANDHI STPP 1 500 10/31/2010 N NR 2029 July State UPRVUNL HARDUAGANJ TPS 9 250 5/25/2012 N NR 2029 July Private TATA PCL JOJOBERA TPS 2 120 2/1/2001 N ER July Total 9 3510 2029 August State PSPCL GH TPS (LEH.MOH.) 3 250 1/3/2008 N NR 2029 August Private JSWEL TORANGALLU TPS(SBU -II) 2 300 8/24/2009 N SR 2029 August Private APL MUNDRA TPS 4 330 12/20/2010 N WR 2029 August Central NSPCL BHILAI TPS 2 250 7/12/2009 N WR 2029 August State CSPGCL DSPM TPS 1 250 3/30/2007 N WR 2029 August State KPCL BELLARY TPS 2 500 3/23/2012 N SR 2029 August Central NTPC INDIRA GANDHI STPP 2 500 11/5/2011 N NR 2029 August Private EPGL SALAYA TPP 1 600 2/22/2012 N WR 2029 August Central DVC MEJIA TPS 7 500 9/30/2010 N ER August Total 9 3480 2029 November State HPGCL YAMUNA NAGAR TPS 1 300 11/1/2007 N NR 2029 November Private JSWEL TORANGALLU TPS(SBU -II) 1 300 4/23/2009 N SR 2029 November Private JSWEL JSW RATNAGIRI TPP 2 300 12/9/2010 N WR 2029 November Private LANCO PATHADI TPP 1 300 6/4/2009 N WR 2029 November State MAHAGENCO PARLI TPS 6 250 2/16/2007 N WR 2029 November State OPGC IB VALLEY TPS 4 660 7/2/2019 Y ER 2029 November Private JhPL(HR) MAHATMA GANDHI TPS 2 660 4/11/2012 N NR 2029 November Central NTPC DADRI (NCTPP) 5 490 1/25/2010 N NR 2029 November State UPRVUNL PARICHHA TPS 5 250 5/24/2012 N NR 2029 November Private CESC BUDGE BUDGE TPS 3 250 9/29/2009 N ER November Total 10 3760 2029 December State UPRVUNL PARICHHA TPS 4 210 12/28/2006 N NR 2029 Decem ber State KPCL BELLARY TPS 1 500 12/3/2007 N SR 2029 December Private WPCL WARDHA WARORA TPP 2 135 10/10/2010 N WR 2029 December Private TATA PCL TROMBAY TPS 8 250 3/26/2009 N WR 2029 December State MAHAGENCO KHAPARKHEDA TPS 4 210 1/7/2001 N WR 2029 December State OPGC IB VALLEY TPS 3 660 7/2/2019 Y ER 2029 December Central NTPC SIMHADRI 1 500 2/22/2002 N SR 2029 December Private VIP BUTIBORI TPP 2 300 8/17/2012 N WR 2029 December State WBPDC SAGARDIGHI TPS 1 300 7/20/2008 N ER December Total 9 3065 TOTAL UNITS AND CAPACITY (Phase III) 101 37215 V. PHASE -IV Duration: January, 2030 to December, 2030 Under this phase, the following 191 Nos. of units of capacity 55767 MW in aggregate of various thermal power plants have been planned and identified for the upgradation/retrofitting for flexible operation including the study and field tests. This phase to be completed within a period of 12 months i.e. from January, 2030 to December, 2030. In case the utilities comprehend that 40% operation of units having age more than 40 years under this phase is not viable/possible, the utilities may opt for 2 -shift operation by suitable retrofits/study/tests. However the duration for the retrofits including the study/test of this phase shall be the same. PHASE IV ( JAN,2030 - DEC,2030) Year Month Sector Organisation Name of Project Unit No. Capacity (MW) Date of Commissioning Pit head Age as on 31.12.2029 Region 2030 January State UPRVUNL ANPARA TPS 7 500 3/6/2016 Y 13.8 NR 2030 January Central NTP C RIHAND STPS 3 500 1/31/2005 Y 24.9 NR 2030 January State PSPCL ROPAR TPS 6 210 3/30/1993 N 36.8 NR 2030 January State RRVUNL KOTA TPS 4 210 5/1/1989 N 40.7 NR 2030 January State PSPCL ROPAR TPS 3 210 3/31/1988 N 41.8 NR 2030 January Central NTPC SING RAULI STPS 5 200 2/26/1984 Y 45.9 NR 2030 January Central NTPC SINGRAULI STPS 1 200 2/14/1982 Y 47.9 NR 2030 January Central NTPC FARAKKA STPS 6 500 3/7/2011 Y 18.8 ER 2030 January Central NTPC TALCHER STPS 3 500 2/21/2003 Y 26.9 ER 2030 January State OPGC IB VALLEY TPS 1 210 6/2/1994 Y 35.6 ER 2030 January State WBPDC KOLAGHAT TPS 6 210 3/17/1991 N 38.8 ER 2030 January Central NTPC BARAUNI TPS 6 105 5/1/1983 N 46.7 ER 2030 January Central NTPC RAMAGUNDE M STPS 7 500 9/26/2004 Y 25.3 SR 2030 January State TANGEDCO NORTH CHENNAI TPS 2 210 3/27/1995 N 34.8 SR 2030 January Central NEYVELI LIGNITE NEYVELI TPS-II 7 210 6/19/1993 Y 36.6 SR 2030 January State APGENCO Dr. N.TATA RAO TPS 4 210 8/23/1990 N 39.4 SR 2030 January Central NEYVELI LIGNITE NEYVELI TPS-II 1 210 1/17/1988 Y 42.0 SR 2030 January Central NTPC RAMAGUNDE M STPS 3 200 12/13/1984 Y 45.1 SR 2030 January State TANGEDCO Thoothukudi TPS 1 210 7/9/1979 N 50.5 SR 2030 January Central NTPC VINDHYACHA L STPS 13 500 8/6/2015 Y 14.4 WR 2030 Januar y Central NTPC VINDHYACHA L STPS 12 500 3/22/2013 Y 16.8 WR 2030 January Central NTPC SIPAT STPS 5 500 8/13/2008 Y 21.4 WR 2030 January State MPPGCL SANJAY GANDHI TPS 3 210 2/28/1999 N 30.9 WR 2030 January State MPPGCL SANJAY GANDHI TPS 1 210 3/26/1993 N 36.8 WR 2030 January State MAHAGENCO KHAPARKHED A TPS 2 210 1/8/1990 N 40.0 WR 2030 January Central NTPC KORBA STPS 5 500 3/25/1988 Y 41.8 WR 2030 January State MAHAGENCO CHANDRAPUR (MAHARASHT RA) STPS 4 210 3/8/1986 N 43.8 WR 2030 January State GSECL WANAKBORI TPS 3 210 3/15/1984 N 45.8 WR 2030 January State MAHAGENCO KORADI TPS 6 210 3/30/1982 N 47.8 WR 2030 January Private TOR. POW. (UNOSUGEN) SABARMATI (D-F STATIONS) 1 120 10/12/1978 N 51.3 WR January Total 30 8685 2030 February State UPRVUNL ANPARA TPS 6 500 6/8/2015 Y 14.6 NR 2030 February State PSPCL GH TPS (LEH.MOH.) 2 210 10/16/1998 N 31.2 NR 2030 February Central NTPC DADRI (NCTPP) 3 210 3/23/1993 N 36.8 NR 2030 February Central NTPC UNCHAHAR TPS 2 210 3/22/1989 N 40.8 NR 2030 Februa ry Central NTPC TANDA TPS 1 110 3/21/1988 N 41.8 NR 2030 February Central NTPC SINGRAULI STPS 4 200 11/2/1983 Y 46.2 NR 2030 February State UPRVUNL OBRA TPS 12 200 3/28/1981 N 48.8 NR 2030 February Central NTPC KAHALGAON TPS 7 500 7/31/2009 Y 20.4 ER 2030 February Private CESC BUDGE BUDGE TPS 2 250 3/6/1999 N 30.8 ER 2030 February State TVNL TENUGHAT TPS 1 210 4/14/1994 N 35.7 ER 2030 February Central NTPC FARAKKA STPS 3 200 8/6/1987 Y 42.4 ER 2030 February State KPCL RAICHUR TPS 6 210 7/22/1999 N 30.5 SR 2030 February State APGENCO RAYALASEEM A TPS 2 210 2/25/1995 N 34.9 SR 2030 February Central NEYVELI LIGNITE NEYVELI TPS-II 6 210 10/30/1992 Y 37.2 SR 2030 February State TANGEDCO METTUR TPS 4 210 3/27/1990 N 39.8 SR 2030 February State TANGEDCO METTUR TPS 2 210 12/1/1987 N 42.1 SR 2030 February Central NTPC RAMAGUNDE M STPS 2 200 5/29/1984 Y 45.6 SR 2030 February Private SPL SASAN UMTPP 6 660 3/19/2015 Y 14.8 WR 2030 February State CSPGCL KORBA -WEST TPS 5 500 3/22/2013 Y 16.8 WR 2030 February State MPPGCL AMARKANTA K EXT TPS 3 210 6/15/2008 Y 21.6 WR 2030 February State GSECL WANAKBORI TPS 7 210 12/31/1998 N 31.0 WR 2030 February State MAHAGENCO CHANDRAPUR (MAHARASHT RA) STPS 6 500 3/11/1992 N 37.8 WR 2030 February Central NTPC VINDHYACHA L STPS 4 210 12/26/1989 Y 40.0 WR 2030 February State GSECL WANAKBORI TPS 6 210 11/18/1987 N 42.1 WR 2030 February State MAHAGENCO CHANDRAPUR (MAHARASHT RA) STPS 3 210 5/3/1985 N 44.7 WR 2030 February Private TATA PCL TROMBAY TPS 5 500 1/25/1984 N 46.0 WR 2030 February State GSECL WANAKBORI TPS 1 210 3/23/1982 N 47.8 WR February Total 27 7470 2030 March Central NTPC RIHAND STPS 6 500 10/17/2013 Y 16.2 NR 2030 March Central NTPC TANDA TPS 4 110 2/20/1998 N 31.9 NR 2030 March Central NTPC DADRI (NCTPP) 2 210 12/18/1992 N 37.1 NR 2030 March Central NTPC TANDA TPS 2 110 3/11/1989 N 40.8 NR 2030 March State UPRVUNL ANPARA TPS 3 210 3/12/1988 Y 41.8 NR 2030 March State RRVUNL KOTA TPS 2 110 7/13/1983 N 46.5 NR 2030 March State UPRVUNL OBRA TPS 9 200 1/26/1 980 N 50.0 NR 2030 March Central NTPC KAHALGAON TPS 6 500 3/16/2008 Y 21.8 ER 2030 March Private CESC BUDGE BUDGE TPS 1 250 9/16/1997 N 32.3 ER 2030 March Central NTPC KAHALGAON TPS 2 210 3/17/1994 Y 35.8 ER 2030 March Central NTPC FARAKKA STPS 2 200 12/24/1986 Y 43.0 ER 2030 March Private JSWEL TORANGALLU TPS(SBU -I) 2 130 5/16/1999 N 30.6 SR 2030 March State APGENCO Dr. N.TATA RAO TPS 6 210 2/24/1995 N 34.9 SR 2030 March State TANGEDCO Thoothukudi TPS 4 210 2/11/1992 N 37.9 SR 2030 March Central NTPC RAMAGUNDE M STPS 6 500 10/16/1989 Y 40.2 SR 2030 March Central NEYVELI LIGNITE NEYVELI TPS-II 3 210 3/29/1987 Y 42.8 SR 2030 March Central NTPC RAMAGUNDE M STPS 1 200 10/27/1983 Y 46.2 SR 2030 March Private SPL SASAN UMTPP 5 660 8/24/2014 Y 15.4 WR 2030 March Central NTPC VINDHYACHA L STPS 11 500 6/14/2012 Y 17.6 WR 2030 March Central NTPC SIPAT STPS 4 500 5/27/2007 Y 22.6 WR 2030 March State GSECL GANDHI NAGAR TPS 5 210 3/17/1998 N 31.8 WR 2030 March State GSECL GANDHI NAGAR TPS 4 210 7/20/1991 N 38.5 WR 2030 March State MAHAGENCO KHAPARKHED A TPS 1 210 3/26/1989 N 40.8 WR 2030 March Central NTPC VINDHYACHA L STPS 1 210 10/10/1987 Y 42.3 WR 2030 March State CSPGCL KORBA -WEST TPS 3 210 3/26/1985 Y 44.8 WR 2030 March Central NTPC KORBA STPS 2 200 10/31/1983 Y 46.2 WR 2030 March State MAHAGENCO NASIK TPS 5 210 1/30/1981 N 49.0 WR March Total 27 7190 2030 July Central NTPC RIHAND STPS 5 500 5/25/2012 Y 17.6 NR 2030 July State PSPCL GH TPS (LEH.MOH.) 1 210 12/29/1997 N 32.0 NR 2030 July State PSPCL ROPAR TPS 5 210 3/29/1992 N 37.8 NR 2030 July State PSPCL ROPAR TPS 4 210 1/29/1989 N 40.9 NR 2030 July Central NTPC SINGRAULI STPS 7 500 11/24/1987 Y 42.1 NR 2030 July Central NTPC SINGRAULI STPS 3 200 3/28/1983 Y 46.8 NR 2030 July State UPRVUNL OBRA TPS 10 200 1/14/1979 N 51.0 NR 2030 July Central NTPC KAHALGAON TPS 5 500 3/31/2007 Y 22.8 ER 2030 July State TVNL TENUGHAT TPS 2 210 10/10/1996 N 33.2 ER 2030 July Central NTPC FARAKKA STPS 5 500 2/16/1994 Y 35.9 ER 2030 July Central NTPC FARAKKA STPS 1 200 1/1/1986 Y 44.0 ER 2030 July State KPCL RAICHUR TPS 5 210 1/31/1999 N 30.9 SR 2030 July State TANGEDCO NORTH CHENNAI TPS 1 210 10/25/1994 N 35.2 SR 2030 July Central NEYVELI LIGNITE NEYVELI TPS - II 5 210 12/31/1991 Y 38.0 SR 2030 July State APGENCO Dr. N.TATA RAO TPS 3 210 10/5/1989 N 40.3 SR 2030 July Central NEYVELI LIGNITE NEYVELI TPS-II 2 210 2/6/1987 Y 42.9 SR 2030 July State TANGEDCO Thoothukudi TPS 3 210 4/16/1982 N 47.7 SR 2030 July Private SPL SASAN UMTPP 3 660 5/21/2014 Y 15.6 WR 2030 July Central NTPC SIPAT STPS 3 660 6/2/2012 Y 17.6 WR 2030 July Central NTPC VINDHYACHA L STPS 10 500 3/8/2007 Y 22.8 WR 2030 July State MAHAGENCO CHANDRAPUR (MAHARASHT RA) STPS 7 500 10/1/1997 N 32.3 WR 2030 July State MAHAGENCO CHANDRAPUR (MAHARASH T RA) STPS 5 500 3/22/1991 N 38.8 WR 2030 July Central NTPC KORBA STPS 6 500 2/26/1989 Y 40.9 WR 2030 July Central NTPC KORBA STPS 4 500 5/31/1987 Y 42.6 WR 2030 July State GSECL UKAI TPS 5 210 1/30/1985 N 44.9 WR 2030 July State CSPGCL KORBA -WEST TPS 2 210 6/21/1983 Y 46.6 WR 2030 July State MAHAGENCO NASIK TPS 4 210 7/10/1980 N 49.5 WR July Total 27 9150 2030 August Private LAPPL ANPARA C TPS 2 600 11/15/2011 Y 18.1 NR 2030 August State UPRVUNL ANPARA TPS 5 500 7/4/1994 Y 35.5 NR 2030 August Central NTPC DADRI (NCTPP) 1 210 12/21/1991 N 38.1 NR 2030 August Central NTPC UNCHAHAR TPS 1 210 11/21/1988 N 41.1 NR 2030 August State UPRVUNL ANPARA TPS 2 210 2/28/1987 Y 42.9 NR 2030 August State RRVUNL KOTA TPS 1 110 1/17/1983 N 47.0 NR 2030 Augus t State UPRVUNL HARDUAGANJ TPS 7 105 3/31/1978 N 51.8 NR 2030 August Central NTPC TALCHER STPS 6 500 2/6/2005 Y 24.9 ER 2030 August Central NTPC KAHALGAON TPS 4 210 3/18/1996 Y 33.8 ER 2030 August State WBPDC KOLAGHAT TPS 5 210 12/28/1993 N 36.0 ER 2030 August State WBPDC KOLAGHAT TPS 3 210 12/16/1985 N 44.1 ER 2030 August Private JSWEL TORANGALLU TPS(SBU -I) 1 130 1/15/1999 N 31.0 SR 2030 August State KPCL RAICHUR TPS 4 210 9/29/1994 N 35.3 SR 2030 August State TANGEDCO Thoothukudi TPS 5 210 3/31/199 1 N 38.8 SR 2030 August Central NTPC RAMAGUNDE M STPS 5 500 3/26/1989 Y 40.8 SR 2030 August State TANGEDCO METTUR TPS 1 210 1/4/1987 N 43.0 SR 2030 August State TANGEDCO Thoothukudi TPS 2 210 12/17/1980 N 49.1 SR 2030 August Private SPL SASAN UMTPP 4 660 3/25/2014 Y 15.8 WR 2030 August Central NTPC SIPAT STPS 2 660 12/24/2011 Y 18.0 WR 2030 August Central NTPC VINDHYACHA L STPS 9 500 7/27/2006 Y 23.4 WR 2030 August Private APL DAHANU TPS 2 250 3/29/1995 N 34.8 WR 2030 August Central NTPC VINDHYACHA L STPS 6 210 2/1/1991 Y 38.9 WR 2030 August Central NTPC VINDHYACHA L STPS 3 210 2/3/1989 Y 40.9 WR 2030 August State GSECL WANAKBORI TPS 5 210 9/23/1986 N 43.3 WR 2030 August Private TOR. POW. (UNOSUGEN) SABARMATI (D-F STATIONS) 2 121 12/31/1984 N 45.0 WR 2030 August Central NTPC KORBA STPS 1 200 2/28/1983 Y 46.9 WR 2030 August State MAHAGENCO NASIK TPS 3 210 4/26/1979 N 50.7 WR August Total 27 7776 2030 Novembe r Private LAPPL ANPARA C TPS 1 600 11/12/2011 Y 18.1 NR 2030 Novembe r Central NTPC DADR I (NCTPP) 4 210 3/24/1994 N 35.8 NR 2030 Novembe r Central NTPC TANDA TPS 3 110 3/28/1990 N 39.8 NR 2030 Novembe r State RRVUNL KOTA TPS 3 210 9/25/1988 N 41.3 NR 2030 Novembe r Central NTPC SINGRAULI STPS 6 500 12/23/1986 Y 43.1 NR 2030 Novembe r Central NTPC SINGRAULI STPS 2 200 11/25/1982 Y 47.1 NR 2030 Novembe r State UPRVUNL OBRA TPS 11 200 12/31/1977 N 52.0 NR 2030 Novembe r Central NTPC TALCHER STPS 5 500 5/13/2004 Y 25.7 ER 2030 Novembe r State OPGC IB VALLEY TPS 2 210 10/22/1995 Y 34.2 ER 2030 Novembe r Central NTPC FARAKKA STPS 4 500 9/25/1992 Y 37.3 ER 2030 Novembe r Central NTPC BARAUNI TPS 7 105 3/31/1985 N 44.8 ER 2030 Novembe r State TSGENCO KOTHAGUDE M TPS (NEW) 10 250 2/28/1998 N 31.9 SR 2030 Novembe r State APGENCO Dr. N.TATA RAO TPS 5 210 3/31/1994 N 35.8 SR 2030 Novembe r Central NEYVELI LIGNITE NEYVELI TPS-II 4 210 3/30/1991 Y 38.8 SR 2030 Novembe r State TANGEDCO METTUR TPS 3 210 3/22/1989 N 40.8 SR 2030 Novembe r State KPCL RAICHUR TPS 2 210 3/2/1986 N 43.9 SR 2030 Novembe r State APGENC O Dr. N.TATA RAO TPS 2 210 10/10/1980 N 49.3 SR 2030 Novembe r Private SPL SASAN UMTPP 2 660 12/18/2013 Y 16.0 WR 2030 Novembe r Central NTPC SIPAT STPS 1 660 6/27/2011 Y 18.5 WR 2030 Novembe r State MAHAGENCO KHAPARKHED A TPS 3 210 5/31/2000 N 29.6 WR 2030 Novembe r Private APL DAHANU TPS 1 250 1/6/1995 N 35.0 WR 2030 Novembe r Central NTPC VINDHYACHA L STPS 5 210 3/31/1990 Y 39.8 WR 2030 Novembe r Private TOR. POW. (UNOSUGEN) SABARMATI (D-F STATIONS) 3 121 9/28/1988 N 41.3 WR 2030 Novembe r State CSPGCL KOR BA-WEST TPS 4 210 3/13/1986 Y 43.8 WR 2030 Novembe r State CSPGCL KORBA -WEST TPS 1 210 3/30/1984 Y 45.8 WR 2030 Novembe r State GSECL WANAKBORI TPS 2 210 1/15/1983 N 47.0 WR 2030 Novembe r State GSECL UKAI TPS 4 200 3/28/1979 N 50.8 WR November Total 27 7586 2030 December Central NTPC RIHAND STPS 4 500 9/24/2005 Y 24.3 NR 2030 December State UPRVUNL ANPARA TPS 4 500 7/19/1993 Y 36.5 NR 2030 December Central NTPC RIHAND STPS 2 500 7/5/1989 Y 40.5 NR 2030 December Central NTPC RIHAND STPS 1 500 3/31/1988 Y 41.8 NR 2030 December State UPRVUNL ANPARA TPS 1 210 3/24/1986 Y 43.8 NR 2030 December State UPRVUNL OBRA TPS 13 200 7/21/1982 N 47.5 NR 2030 December Central NTPC TALCHER STPS 4 500 10/25/2003 Y 26.2 ER 2030 December Central NTPC KAHALGAON TPS 3 210 3/24/1995 Y 34.8 ER 2030 December Central NTPC KAHALGAON TPS 1 210 3/31/1992 Y 37.8 ER 2030 December State WBPDC KOLAGHAT 4 210 1/24/1984 N 46.0 ER TPS 2030 December State TANGEDCO NORTH CHENNAI TPS 3 210 2/24/1996 N 33.9 SR 2030 December State APGENCO RAYALASEEM A TPS 1 210 3/31/1994 N 35.8 SR 2030 December State KPCL RAICHUR TPS 3 210 3/30/1991 N 38.8 SR 2030 December Central NTPC RAMAGUNDE M STPS 4 500 6/26/1988 Y 41.5 SR 2030 December State KPCL RAICHUR TPS 1 210 3/29/1985 N 44.8 SR 2030 December State APGENCO Dr. N.TATA RAO TPS 1 210 11/1/1979 N 50.2 SR 2030 December Private SPL SASAN UMTPP 1 660 5/30/2013 Y 16.6 WR 2030 December Central NTPC KORBA STPS 7 500 11/25/2010 Y 19.1 WR 2030 December State MPPGCL SANJAY GANDHI TPS 4 210 11/23/1 999 N 30.1 WR 2030 December State MPPGCL SANJAY GANDHI TPS 2 210 3/27/1994 N 35.8 WR 2030 December State GSECL GANDHI NAGAR TPS 3 210 3/20/1990 N 39.8 WR 2030 December Central NTPC VINDHYACHA L STPS 2 210 7/23/1988 Y 41.5 WR 2030 December State GSECL WANAKBORI TPS 4 210 3/9/1986 N 43.8 WR 2030 December Central NTPC KORBA STPS 3 200 3/17/1984 Y 45.8 WR 2030 December State MAHAGENCO BHUSAWAL TPS 3 210 9/18/1982 N 47.3 WR 2030 December State GSECL UKAI TPS 3 200 1/21/1979 N 51.0 WR December Total 26 7910 TOTAL UNITS AND CAPACITY (Phase IV) 191 55767 RAKESH KUMAR, Secy. [ADVT. -III/4/Exty./ 617/2023 -24] Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi -110064 and Published by the Controller of Publications, Delhi -110054 .

Never miss important gazettes

Create a free account to save gazettes, add notes, and get email alerts for keywords you care about.

Sign Up Free