Full Text
EXTRAORDINARY
PART I —Section 1
PUBLISHED BY AUTHORITY
No. 63] NEW DELHI, WEDNE SDAY , MARCH 13, 2024 /PHALGUNA 23, 1945
CG-DL-E-15032024-253060
MINISTRY OF COMMERCE AND INDUSTRY
(Department for Promotion of Industry and Internal Trade)
NOTIFICATION
New Delhi, t he 9th March, 20 24
F. No. P -44015/1/2023 -DBA -II: The Government of India is pleased to announce the Uttar Poorva
Transfor mative Industrialization Scheme (UNNATI), 2024, for the North -Eastern Region.
1. Scheme Title: This Scheme will be called Uttar Poorva Transformative Industrialization Scheme (UNNATI),
2024.
2. Coverage: The Scheme wil l cover all 8 North -Eastern States, na mely Arunachal Pradesh, Assam, Manipur,
Meghalaya, Mizoram, Nagaland, Sikkim, and Tripura.
3. Commencement and Duration of the Scheme: It will be effective from 09.03.2024 and will remain in force up to and
inclusive o f 08.03.2034 and 8 more years for meet ing committed liabilities.
4. Brief about the Scheme: UNNATI, 2024 is designed to strengthen the Industrial Eco -System in the North East
and attract New Investment. The Scheme is divided into two parts i.e Part A and P art B
4.1. Part A: Part A provides inc entives to eligible new industrial units and those undergoing substantial expansion.
Part A will have three components namely Capital Investment Incentive (CII), Central Interest Subvention (CIS),
and Manufacturing & S ervices Linked Incentive (MSLI)
4.2. P art B: Part B is for developing an industrial eco -system throu gh activities such as (i) Project Monitoring Unit
(PMU) and Project Implementation Unit (PIU); (ii) Third Party Evaluation and Impact Assessment; and (iii) Portal
Development (aligned with Natio nal Single Window System, NSWS), Capacity Building workshops, IEC and
others as decided by the Steering Committee
5. Application period for registration : Registration shall commence from 09.03.2024 and will continue ti ll 31.03.2026
subject to the guideline s issued in this regard. Notwithstanding the permissible perio d of registration till 31.03.2026,
further grant of registration and receipt of application in the portal under the scheme will be stopped prior to this per iod if
the projected financial liabili ty of the units that are granted registration reaches 115% of the total financial outlay of the
scheme. Further, details for registration will be issued separately in registration guidelines of the scheme.
5.1. Merely applying for registration will not entitle any applicant to claim incentives under this scheme. Further
details for claiming incentives shall be provided in the claim guidelines of this scheme.
5.2. No unit will have the right to register under this scheme or claim the benefits unless it is specifically approved by the
competent authority as laid out in the guidelines.
5.3. The registration will be granted by the competent authority as laid out in the guidelines, which will, inter alia ,
consider the prima facie eligibility of the unit and availability of approved fu nds.
5.4 All units willing to avail of incentive(s) under this scheme have to apply for registration through the online
portal.
6. Grant of registration: All registration applications shal l be disposed of by 30.09.2026 unless otherwise
extended.
7. Definitions:
7.1. ‘Ap proved Funds’ means financial outlay allocated under Parts A and B of this Scheme.
7.2. ‘Arm’s length price’ as defined under the provisions of the Income Tax Act,1961.
7.3 (a) ‘Unit’ means any industrial manufacturing entity or service sector enterprise registered under Goods &
Service Tax Act, 2017 excluding the Industrial Unit in which Government has more than 50% stake/shareholding.
7.3 (b) ‘New Unit’
i. For the manufacturin g sector, a unit registered under this scheme on or after 09.03.2024 but not
later than 30.09.2026. Such a unit has to commence commercial production within 4 years from the
date of grant of registration.
ii. For the Service sector, a unit registered under th is scheme on or after 09.03.2024 but not later than
30.09.2026 . Such a unit has to commence commercial operation within 4 years from the da te of grant of
registration.
iii. A new unit will be required to fulfill the following conditions:
➢ It is not formed by sp litting up, or reconstruction of a business already in existence.
➢ It is not formed by transfer to the new unit of plant or machinery previously used for any other
purpose.
➢ It has not relocated from elsewhere and/or is not an existing unit reopened under a new name and
style.
iv. New unit must have a new GSTIN and unit cannot use a GSTIN of any existing unit
Provided that heritage property not in use before 09.03.2024 is restored thereafter for commercial or
hospitality or tourism services on a commercial basis, it will also be considered as a new unit as per eligibility
conditions to be further elaborated in de tailed guidelines.
7.3 (c) ‘Existing Unit’ means a unit that has commenced commercial production/operation prior to
09.03.2024 and having a valid GST Iden tification Number (GSTIN) in the concerned State of North -Eastern
Region.
7.3 (d) ‘Substantial expansion’ means an additional investment of a minimum of twenty -five percent (25%) of
the total amount of investment already made in an existing unit in plant a nd machinery (for manufact uring sector) or
construction of building and other durable physical assets (for service sector).
The additional investment should increase production capacity/enhancement of Services or diversification and should
not be a mere re placement of existing plan t and machinery.
7.4 (a) ‘Manufacturing unit’ means a unit that carries out the processing of raw material or inputs in any
manner that results in the emergence of a new product having a distinct name, character, and use. The
term ―m anufacturing unit shall be construed accordingly.
7.4 (b) ‘Services unit’ includes Hotels & Hospitality, Tourism (Homestays, Adventure, Health Tourism, Eco -Tourism
& MICE). E ducation (Vocational & Digital/e -learning). Bio -tech, Fin -tech & Financial Serv ices. Healthcare
(Secondary & Tertiary). IT -ITeS, BPO. EV Charging Stations and Tech -oriented start -ups/units providing services in
the field of education, Primary Healthcare, a nd Agriculture.
7.4 (c) ‘Commencement of Commercial Production (Manufacturing S ector)’ means starting manufacturing
of finished goods on a commercial basis which is preceded by trial production and installation of complete plant
and machinery for manufactu ring finished products in commercial quantity and all raw materials,
consumable s, etc. required for manufacture are available.
7.4 (d) ‘Commencement of Commercial Operation (Service Sector)’ means starting of operation/delivering of
services on a commercia l basis.
7.5. ‘Raw material’ means materials or substances used by any unit to produce or manufacture the finished goods.
7.6. ‘Finished Good’ means the goods produced and supplied by an industrial unit and for which it is
registered under the Scheme.
7.7. ‘Plant and Machinery’ in case of Manufacturing units shall cover industrial pl ant and machinery as erected at
the site, which is newly purchased from the open market at an arm’s length price. It excludes
relocated/recycled/refurbished plants and machinery. The details of core and non -core components of Plant &
Machinery shall be pro vided in the guidelines.
7.8. ‘Building and other durable physical assets’ in the case of ser vice sector units shall cover new buildings and
other durable physical assets for a service sector unit where purchases have been made following an a rm’s length
pricing. The details of durable physical assets shall be provided in the guidelines.
7.9. ‘Zon e A and Zone B Districts’ means Zone A (Industrially Advanced Districts) and Zone B (Industrially
Backward Districts) based on NER Districts SDG Index prepared by NITI Aayog, UNDP and Ministry of
Development of North Eastern Region. The list shall be provi ded by the Steering committee in consultation with
NITI Aayog and State Governments of NER.
8. Eligibility for availing incentives:
8.1. All units eligible under t he Manufacturing and Service sector will be granted incentive(s) under this scheme
as defined under respective incentives.
8.2. Manufacturing sector units with a minimum investment of Rs. 1.0 crore in plant & machinery will be
eligible for incentives under this scheme. For calculation of any incentive under the scheme the eligible value
shall be determined based on the investment made in Plant & Machinery in manufacturing sector. The scheme
shall not apply to the units that manufacture the products listed i n the Negative list in Annexure –I.
8.3. Service sector units with a minimum investment of Rs. 50 Lakh in building and other durable physical
assets will be eligible for incentives under this scheme. For calculation of any incentive under the scheme the
eligible value shall be determined based on the investment made in building and other durable physical assets.
The scheme shall be applicable only for services listed in th e Positive list in Annexure -II.
8.4. For Micro Industries the minimum investment limit shall be ₹50 lakhs for both manufacturing and service
sector.
8.5. For Micro industries (defined as per MSME industry norms), the Plant & Machinery calculation will
include the cost of building construction as well.
8.6. All eligible units have to commenc e commercial production/operation within 4 years from the date of grant
of registration. The unit shall be allowed to sell or supply* the finished goods produced/manufact ured in the
intermediate phases. It is envisaged that certain units may install plant & machinery in phases. Thus, there will be
a provision of phased commencement of production (maximum 3 phases), but the incentives will only flow after
the final commence ment of production. The date of commencement of commercial production after the
comple tion of all phases shall not be later than 4 years from the date of registration under the scheme.
(*Supply means supply of goods and services as defined under GST Act, 2 017)
8.7. The final invoice for procurement of Plant & Machinery or for construction o f building and durable
physical assets must be on or after 09.03.2024 to be considered eligible under the scheme.
8.8. The maximum eligible benefit to one unit from all s cheme components is Rs. 250 crores.
8.9. (a) Cost of Plant and Machinery (in manufactu ring sector) that is essential for manufacturing of
finished goods but excludes the cost of land, consumables, disposables or any other item charged to revenue.
8.9. (b) Cost of construction of Building and procurement of other durable physical assets for the service sector unit
that are basic to running that particular unit in the service sector but excludes cost of land, consumables,
disposables or any other item charged to revenue.
8.10. Units availing benefits under other schemes of the Government of I ndia will not be eligible for same
incentives under this Scheme. However, the eligible value of Plant & Machinery (Manufacturing Sector) or
construction of building and durable physical assets (Service sector) for claiming other eligible incentives under
UNNAT I will be calculated by Department of Industries of the concerned State Government.
8.11. The beneficiary of this scheme has to furnish an undertaking to abide by the terms and conditions of the scheme.
The format of undertaking shall be provided in regis tration guideline.
8.12. Eligibility under this scheme will be subject to verification of investment (core and non -core) in plant and
machinery (in the manufacturing sector) and cost of construction of building and other durable physical assets (in the
service sector). However, th e incentive will be eligible only for core segment in both manufacturing and service
sector. Details will be laid down in the guidelines.
9. Nodal agency
The North -Eastern Development Financial Corporation Ltd. (NEDFi) will be the nodal agency for the disbursal of
incentives under various components of the scheme. The nodal agency will release incentives only through e -transfer
to the designated bank accounts of eligible units.
10. Gove rnance and Implementation Mechanism
10.1 The s cheme will be implemented under the supervision of the Government of India i.e. the Department for
Promotion of Industry & Internal Trade (DPIIT) and implement through State machinery with the support
of Projec t Monitoring Unit (PMU) and Project Impl ementa tion Unit (PIU)
10.2 Committees constituted for governance and implementation of this scheme, along with their Power and
function, are as follows:
10.2.1. The Steering Committee:
a) Constitution
i. Secretary, DPIIT a s Chairperson
ii. Representative of Ministry of De velopment of North -Eastern Region
iii. Representative of the Ministry of Environment, Forest and Climate Change
iv. Representative of the Ministry of Micro, Small, and Medium Enterprises
v. Representative of NITI AAYOG
vi. Representative of CBIC
vii. Additional Secretary and F inancial Advisor (AS&FA), DPIIT
viii. Chief Secretary/Principal Secretary of all North -Eastern States
ix. Joint Secretary, DPIIT, in charge of North -East Region Schemes Section
x. Special members can be invited from various Ministries if required
b) Power and funct ions:
i. The Steering Committee will monitor the smooth implementation and issue detailed guidelines for
execution, and issue clarifications whenever interpretational issues arise.
ii. The Committee will decide on the proposals for implementation, monitoring and IT sup port as per needs and
contingencies under the administrative cost component.
iii. The Committee shall also utilize the services of the Central Board of Indirect Tax and Customs (CBIC) and
Central Board of Direct Tax (CBDT) and shall periodically invite a ppropri ate officers like jurisdictional
Chief Commissioners of GST, Income Tax, and Commissioner of GST as Special Invitees, for seeking their
inputs with particular emphasis on preventing fraudulen t or non -genuine claims.
iv. The Committee will get done inspe ctions to prevent misuse of the Scheme through the engagement of an
independent third party or empanelment of qualified personnel for verification.
v. The detailed guidelines on eligibility under the s ervice sector (including Homestays, Adventure Tourism,
Eco-Touris m, Waste Management, and Vocational Education) shall be issued by the Steering Committee.
vi. Decision -making on the proposals for Part B of the Scheme.
vii. The Committee shall be authorized to amen d the categorization of districts into Zone A and Zone B.
However , this amendment in Zone A and Zone B categorization shall be in consultation with the North -
Eastern States.
viii. The outlay for Part A and Part B is fungible and can be done at the discretion of the Steering Committee
with the approval of the Department of Exp enditure.
ix. 60% of the outlay of Part A is earmarked to the states and can be changed between the states at the
discretion of the Steering Committee with the approval of the Department of Expen diture, under exceptional
circumstances and with reasonabl e justi fication.
10.2.2. The State Level Committee:
a) Constitution:
i. Chief Secretary of the state as Chairperson
ii. Sr. most State Secretary, Department of Industries
iii. Sr. most State Secretary, Department of Finance
iv. Representative of DPIIT (not below the rank of Under S ecretary)
v. Any other member(s) representing the relevant sectors related to the projects under consideration may be
nominated by the Chief Secretary as Special Invitee(s)
b) Power and functions: The State Level Committee will also monitor the overall im plement ation of the Scheme
and put in place proper checks and balances for ensuring transparency and efficiency in processing and approval
of claims under the Scheme to avoid, inter -alia, duplicatio n of release of any incentive under the Scheme. Details
of furthe r delegation of powers for granting registration of unit, processing and sanction of claims will be worked
out while preparing the detailed guidelines of the scheme.
10.2.3. Project Manageme nt Unit (PMU) and Project Implementation Unit (PIU):
Proje ct Mana gement and monitoring shall be done by DPIIT by deputing its own officers as well as independent third -
party random checks to ensure compliance with all notifications and guidelines under the scheme. An appropriate
Project Management Agency (PMA) sh all be appointed at DPIIT level to assist them in project management ensuring
timely implementation and smooth monitoring and evaluation of the project. 100% grant will be provided by
Government of India towards expenditure incurred on PMA as per provision in the scheme i.e. up to 0.4 % of total
outlay. Similarly, there will be a PIU appointed for each state by DPIIT and DPIIT will bear the costs up to 0.6% of
the sanctioned outlay. The respective st ates have to bear any cost beyond the sanctioned outlay (w hich wo uld be
divided on a similar basis as earmarked funds), if any, from their own resources. The major roles and responsibilities
of PMU & PIU are at Annexure - III.
11. Incentives under the Scheme:
Subject to eligibility, the following incentives are provide d under this scheme:
i. Capital Investment Incentive (CII)
ii. Capital Interest Subvention (CIS)
iii. Manufacturing & Services linked incentive (MSLI)
11.1.1 Capital Investment Incentive (CII):
a) Eligibility:
The following units will be eligible to avail of th is incen tive:
i. New units, as well as Expanding units will be eligible to avail of this incentive in both Zone A and Zone B.
ii. An applicant (with the same name and GST number) c an get incentives on maximum of one unit or
application under this scheme in each s tate
b) All eligible units located in Zone A District in the States of North -Eastern Region will be provided Capital
Investment Incentive @30% of the eligible investment made i n plant and machinery (for the manufacturing
sector) or for construction of buildin g and in stallation of other durable physical assets (for services sector) with a
maximum limit of Rs. 5.00 crore. For those sectors where GST is not applicable, the maximum limit of this
incentive will be Rs. 10.00 crore.
c) All eligible units located in Zone B categ ory blocks in the States of North -Eastern Region will be provided
Capital Investment Incentive @50% of the eligible investment made in plant and machinery (for manuf acturing),
or for construction of building and installation of other durable physic al asset s (for services sector) with a
maximum limit of Rs.7.50 crore. For those sectors where GST is not applicable, the maximum limit of this
incentive will be Rs. 10.00 c rore.
d) A new unit registered under the scheme will not be eligible to avail of the b enefit u nder substantial expansion. A
unit can avail of this incentive only once under the scheme.
e) Physical verification of the units is mandatory before availing of this in centive.
f) Detailed procedures for availing of the incentive shall be laid down in the guide lines.
11.1.2 Capital Interest Subvention (CIS):
(a) Eligibility:
(i) New units, as well as Expanding units of both the manufacturing and service sectors will be eligible to
avail this incentive.
(ii) Interest on loan up to the principal amount of Rs. 250cro re for inv estment in eligible plant and machinery
(manufacturing sector) or Building and all other durable physical assets (for service sector) shall be eligible
for Capital Interest subvention. If the total principal amount of the loan (loan being defined as a whol e and not as
per draw -down amount in each tranche) is more than Rs.250 crore, then interest on the loan amount e xceeding
Rs. 250 crore would not be eligible for Capital Interest Subvention.
(iii) The Capital Interest Subvention would be eligible on th e amount di sbursed and not on the principal amount
sanctioned for the term loan.
(b) All eligible units located in Zone A category blocks in the States of North -Eastern Region can avail of Capital
Interest Subvention at the annual rate of interest of 3% fo r a maximum of 7 consecutive years from any date after
the date of application for registration under th is scheme. However, disbursement of the eligible amount under this
incentive shall begin only after the commencement of commercial production.
(c) All e ligible uni ts located in Zone B category blocks in the States of North -Eastern Region can avail of Capit al
Interest Subvention at the annual rate of interest of 5% for a maximum of 7 consecutive years from any date after
the date of application for registr ation under this scheme. However, disbursement of the eligible amount under this
incentive shall begin o nly after the commencement of commercial production.
(d) This incentive is applicable on the loans availed from Scheduled Commercial Banks or Financial Institution s
registered by Reserve Bank of India.
(e) Detailed procedure for availing of the incentive s hall be laid down in the guidelines.
11.1.3 Manufacturing & Services Linked Incentive (MSLI):
(a) Eligibility: Only New units having a valid GST Identi fication Num ber (GSTIN) will be eligible for benefit under
this incentive.
(b) The upper limit of incent ive under this component shall be 75% (for ZoneA) and 100% (for ZoneB) of the eligible
value of investment made in plant and machinery (for manufacturin g sector) or construction of building and other
durable physical assets (for services sector).
(c) All eligible units of ZoneA & Zone B will be granted a Manufacturing & Services linked incentive (MSLI) equal
to 100% of the Net payment of GST , i.e. GST P aid less Inp ut Tax Credit, for a maximum period of 10 years from
the date of commencement of commerc ial production/operation or till the validity of the scheme whichever is earlier.
However, GST paid on exported goods or services will not be counted toward s eligible i ncentive amounts under this
component.
(d) The amount of incentive paid in a financial y ear will be one -tenth of the total amount of eligible incentive under this
component subject to full payment of GST as per GST return filed for the claim pe riod.
(e) In case the Net GST paid by any unit in a financial year is more than one -tenth of the tot al amount of eligible
incentive, the balance can be carried forward to the subsequent financial year(s). Further, if the unit cannot claim the full
eligible amount of i ncentives in the first 3 years, the same can be carried forward to subsequent years. How ever, this
will not be carried forward beyond the eligible period of 10 years or beyond the scheme's validity, whichever is earlier.
(f) Detailed procedure s for availi ng of the incentive shall be laid down in the guidelines.
12. Process of application for registration, claiming incentives, approval and disbursal of claims:
These shall be prescribed in the detailed guidelines to be issued separately.
13. Proc essing/ scru tiny of claims:
13.1. Claims filed under the scheme will be pre -scrutinized by a recognized independent audit agency to be appointed
by DPIIT.
13.2. NEDFi will undertake pre -scrutiny of 10% of claims before disbursement of incentives.
13.3. All concerned Ministries/Departments of Government of India must amend their respective Acts/Rules/
Notification etc. and issue necessary instructions for effecting these decisions.
14. Rights of the Governments:
14.1. In case any unit availing incentives und er this sch eme goes out of product ion/ operation permanently or
changes the location of the whole or any part of a unit or disposes of a substantial part of its total fixed capital
investment within 10 years after the date of commencement of production/ op eration, th en the unit will not be eligible to
claim any incentive with effect from the date it goes out of production/ operation or changes its location.
Further, all such units will be liable to refund the entire grant or incentive availed if it goes out of product ion/
operation permanently or changes the location of the whole or any part of a unit or disposes of a substantial part of its
total fixed capital investment within 5 years after the date of commencement of production/ operation.
14.2. If it is established that a unit has obtained incentive(s) by misrepresenting/suppressing an essential fact,
furnishing of false information, the unit has to refund the entire grant or inc entive availed with interest of 15% per
annum. It will also be liable for cri minal proce edings.
14.3. Concealment of input supplies or routing of third party or malpractices of similar kinds will render unit
liable for forfeiture of further claims and reco very of all previous incentive(s) paid with interest @15% per annum.
14.4. The incentive (s) will be released through digital payment and Nodal agency will collect all information required
by the DBT Mission in respect of beneficiary units. The nodal agency shall take an affidavit cum indemnity bond in
this regard from the authorize d signatory of the beneficiary unit.
14.5. The Nodal agency shall furnish a Certificate of Utilization of the incentive(s) in Form12(C) of General
Financial Rules, 2017 in respect of disbursements to the DPIIT within 3 months from the date of receipt of th e last
installment/full amount.
15. No interest on account of delay in incentive payment can be claimed by the unit .
16. Minis ter in charge is authorized for making modification in the scheme as deemed necessary for
implementation of the scheme within the broad conto urs.
BALAMURUGAN D., Jt. Secy.
Annexure -I
Negative List: For the Manufacturing Sector
The following manufacturing industries will not be eligible for benefits under Uttar Poorva Transformative
Industrializati on Scheme (UNNATI), 2024 for the North -Eastern Region:
i. All goods falling under Chapter 24 of the Central GST Tariff Act, 2017 which pertains to tobacco and
manufactured tobacco substitutes.
ii. Pan Masala as covered under Chapter 24 of the Central GST Tariff A ct, 2017.
iii. Plastic carry bags of less than 20 mi crons as specified by Ministry of Environm ent and Forests Notification
No. S.O. 705(E) dated 02.09.1999 and S.O. 698(E) dated 17.6.2003 and any subsequent amendments.
iv. Goods falling under Chapter 27 of the Firs t Schedule to the Central Excise Tariff Act, 19 85 (5 of 1986)
produced by Petroleum or Ga s refineries.
v. Plantation, Refineries and Power Generating Units (that are fossil -fuel based).
vi. Units not complying with environmental standards or not having applicable Environmental Clearance from
M/o Environment & Forests and Climate Change or State Envir onmental Impact Assessment Authority
(SEIAA) or not having requisite consent to establish and operate from the concerned Central Pollution
Control Board/State Pollutio n Control Board.
vii. Low-value addition activities in goods such as preservation during stora ge, cleaning, operations, packing,
repacking or re -labelling, sorting, alteration of retail sale price etc. excluding high -value packaging and
processing.
viii. Cement Indus try
ix. Arms & Ammunition
x. Any other industry or act ivity placed in negative list through a separate notification as and when considered
necessary by the Steering Committee
Annexure -II
Positive List: For Service Sector
The following service sector industries , details of which wil l be given in the guideline s, will be eligible for benefits under
Uttar Poorva Transformative Industrialization Scheme (UNNATI), 2024 for the North -Eastern Region:
Service Sector Positive List
1 Hotels & Hospitality
2 Tourism (Home stays, Adventure, Health Tourism, Eco -Tourism & MI CE)
3 Education (Vocational & Digital/e -learning)
4 Bio-tech
5 Fin-tech & Financial Services
6 Healthcare (Secondary & Tertiary)
7 IT-ITeS
8 BPO
9 EV Charging Stations
Tech -oriented start -ups/units providing services in the field of:
a. Educa tion
b. Primary healthcare
c. Agriculture
11 Any other industry or activity placed in positive list through a separate notification as and when considered
necessary by the Steering Committ ee
Annexure -III
Roles & Responsibilities of PMU & PIU
Role & Responsib ilities of PMU will primarily include:
▪ Deploy resources at DPIIT, New Delhi for effective implementation of the scheme.
▪ Capturing, analysis of data and preparation of reports for tracking status of t he scheme.
▪ Financial review to track progress of the sche me on behalf of DPIIT.
▪ Coordinate with techni cal design & development agency and provide inputs for maintenance of online
platform and creation/maintenance of dashboard for the scheme.
▪ Evaluation of implementation of various components of the scheme at re gular intervals.
▪ Monitoring of physical and fi nancial progress for each approved component and monitor the same on a
periodical basis.
▪ Coordinate with State government, NEDFi (disbursing agency) and PIU for effective implementation of the
scheme at ground level.
▪ Screening of Documents & Claims and phy sical inspection on behalf of DPIIT for randomly picked up cases,
as and when required based on direction of DPIIT.
▪ Capacity building activities at centr al and state level.
▪ Any other function specially assigned by DPIIT.
Role & Responsibilities of PIU wil l primarily include:
• Deploy resources at states for effective implementation of the scheme.
• Assist the concerned state government departments in assessme nt & appraisal of applications based on
various parameter s as per the requirements of the scheme, which may include:
o Project report
o Land papers (Revenue papers regarding ownership/rent deed duly registered by the
registering authority/ lease deed in case of government land)
o Bank loan sanction letter
o Appraisal report of the bank/financial institution
o Certificate of mandatory/obligatory registration/approval from the concerned department,
as applicable.
• Assist the concerned state department and other stak eholders in undertaking steps necessary for eval uation of
specific applications and obtaining the final decision of the Competent Authority for forwarding the
cases/applications to DPIIT for grant of registration and disbursement of incentives.
• Assist the concerned state government departments in verify ing the i nformation filed in the registration and
claim applications.
• Undertake development of implementation plan in coordination with the state government departments to
collate and disseminate information regarding the scheme, related guidelines, regist ration an d claim process.
• Coordinate with Nodal officers of concerned departments at state level for sector specific projects.
• Understanding training requirements of various stakeholders at the state level in cluding government officials,
agencies and inves tors.
• End-to-end organizing & management of knowledge sharing workshops with the state government officials
at district level, potential investors and applicants.
• Assisting PMU team at central level in creati on of knowledge and training collaterals.
• Hold a wareness workshops for investors at district level.
• Identify key bottlenecks in application and claim process at state and district level. Assist officials at
district/DIC level in resolution of challenges an d bottlenecks encountered during appraisal of ap plication s.
• Periodically organise camps at districts/DIC level to fast -track application and claim processes.
• Carrying out the necessary activities for Investment Promotion.
• Any other function specially assi gned by DPIIT.
Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi -110064