Full Text
REGD. No. D. L.-33004/99
The Gazette of India
CG-DL-E-11022025-260836
EXTRAORDINARY
PART I-Section 1
PUBLISHED BY AUTHORITY
No. 37]
NEW DELHI, THURSDAY, FEBRUARY 6, 2025/MAGHA 17, 1946
No. 42-26/1/2022-RCM-Part (3).—
MINISTRY OF POWER
RESOLUTION
New Delhi, the 6th February, 2025
TARIFF BASED COMPETITIVE BIDDING GUIDELINES FOR PROCUREMENT OF STORAGE
CAPACITY/STORED ENERGY FROM PUMPED STORAGE PLANTS
PART A: SCOPE
1. Background
1.1. The National Framework for Promotion of Energy Storage Systems (ESS) 2023 aims at facilitating India's
Energy Transition and to enhance the energy security as the country shifts from fossil to non-fossil fuel
sources, driven primarily by Renewable Energy (RE). As part of its action plan to combat Climate Change,
India plans to have 500 GW of non-fossil fuel-based electricity installed capacity by 2030, so that the non-
fossil and cleaner fuel-based sources comprise 50% of the installed capacity mix by 2030. However, the
variability of RE-caused by factors such as Time of day, Weather conditions, Seasonal changes, and
Geographic location-poses challenges to these goals. Renewable sources such as solar, wind, and run-of-the-
river Hydro are not available on 24x7 basis. Energy Storage Systems (ESS) address this by storing excess
energy and supplying it when needed, Improving Grid Stability, Enabling Peak Shifting, and Enhancing
Renewable Energy integration.
1.2. The National Electricity Plan 2023 foresees a need of approximately 74 GW/411 GWh of ESS by 2031-32,
including 27 GW/175 GWh from Pumped Storage Plants (PSP) and 47 GW/236 GWh from Battery Energy
Storage Systems (BESS).
1.3. Usage of ESS provides benefits like reduced peak deficits, lower peak tariffs, carbon emissions reduction, and
deferred capital expenditure on transmission and distribution. ESS also enables energy arbitrage, providing
advantages for both the grid and consumers.
1.4. The Guidelines for the procurement and utilization of Battery Energy Storage Systems (BESS) are already in
place, but there are no separate guidelines for Pumped Storage Plants (PSP). Considering the distinct
requirements of PSP in aspects such as land acquisition, permits and clearances, project timelines and
performance parameters, separate guidelines for PSPs here-in are being formulated to address the specific
nuances of PSP technologies.
2. Objectives
The following are the objectives of these Guidelines.
2.1. To promote the development of Pumped Storage Plants (PSPs).
2.2. To provide a transparent, fair, standardized procurement framework based on open competitive bidding with
appropriate risk-sharing between various stakeholders.
3. Applicability
3.1. These Guidelines are issued under Section 63 of the Electricity Act, 2003, for procurement of storage capacity/
stored energy from Pumped Storage Plants (PSPs) through competitive bidding.
3.2. The provisions of these Guidelines shall be applicable on the following entities:
a. Developers,
b. Procurers (End Procurers or Intermediary Procurers)
3.3. These Guidelines are applicable for the procurement of storage capacity or stored energy by the Procurers from
existing, under-construction or new PSP projects.
4. Definitions
The terms used in these Guidelines will have the following meanings:
a. "Act" shall mean the Electricity Act, 2003, including subsequent amendments and clarifications issued
thereof.
b. "Actual Commencement of Supply Date (ACSD)” in relation to the contracted storage capacity shall mean
the date corresponding to the actual date of commencement of storage capacity for pumping or generation of
energy.
c. "Affiliate" in relation to a Company shall mean an entity that controls, is controlled by, or is under the
common control with, such Company. The expression 'control' shall mean the ownership, directly or
indirectly, of more than 50% of the voting shares of such Company or right to appoint majority Directors.
d. "Annual Availability” shall be as defined in the RfS.
e. "Appropriate Commission” shall have the same meaning as defined in the Act.
f. "Appropriate Government” shall have the same meaning as defined in the Act.
g. "Bidding Agency" shall refer to the organization issuing the tender documents and carrying out the
evaluation and selection process under these Guidelines.
h. "Bid Documents” shall consist of RfS Document, PSPA and PSSA to be prepared by the Bidding Agency in
line with these Guidelines.
i. "Composite Tariff Model” shall mean a model in which the Procurer contracts for power or energy from
storage-based system for a specified time. In either of these contracts, the energy for storage including losses
in conversion is arranged by the Developer.
j. "Delivery Point” shall mean any point as specified in the RfS Document where the PSP is delivering power.
k. "Effective Date of PPA” shall mean the date of signing of PPA.
1. "End Procurer” shall mean the final purchaser of storage capacity or stored energy from the Intermediary
Procurer or the Pumped Storage Plant Developer, as the case may be, and shall include the distribution
licensees.
m. "Financial Closure” or “Project Financing arrangements” shall mean arrangement of necessary funds by
the Developer towards 100% project cost either by way of commitment of funds by the Company from its
internal resources (through a resolution passed by the Board of Directors) and/or tie up of funds through a
bank/financial institution by way of sanction of a loan or firm commitment letter agreeing to finance.
n. "Infrastructure Sector” means sectors notified by the Department of Economic Affairs in its Gazette
Notification no. 13/1/2017-INF dated 14th November, 2017, and as amended from time to time.
o. "Intermediary Procurer” shall mean an agency, including a trading licensee that acts as an intermediary
between the End Procurer(s) and the Developer(s). This agency shall be responsible for aggregating storage
capacity or stored energy purchased from different Developers, and subsequently selling it to the End
Procurer(s). In cases where the trading licensee purchases storage capacity or stored energy from the
Developer(s) and sells it to one or more distribution licensees, the trading licensee shall be deemed to be the
Intermediary Procurer, and the distribution licensees shall be deemed to be the End Procurer(s) for the
purpose of these Guidelines. So long as the Intermediary Procurer follows these Guidelines, the End
Procurer(s) shall be deemed to have followed these Guidelines.
p. "Payment on Order Instrument" shall mean a Letter of Undertaking (LOU) issued by an agency
authorized by the Government of India or a State Government. This LOU shall guarantee to pay the Procurer
(beneficiary) a specified amount in case of failure of the Developer to meet the obligations under the tender
documents or contract. The LOU shall be issued on terms and conditions similar to that of a Bank Guarantee
provided by any public sector bank.
q. "Procurer” shall mean the End Procurer or an Intermediary Procurer, as the context may require.
r. "Pumped Storage Plants (PSPs)” or “Projects” shall mean a hydro power plant, either on-stream or off-
stream, that stores energy by pumping water from a lower stream/ reservoir to a upper reservoir and generates
electricity by releasing it back through a turbine-generator.
S. "Pumped Storage Plant Developer (PSPD)” or “Developer” shall mean an entity that owns or operates a
PSP. The PSP can provide storage capacity or stored energy from various sources, under these guidelines.
t. "Pumped Storage Purchase Agreement” or “PSPA” or “Power Purchase Agreement” or “PPA” shall
mean an agreement between either the Intermediary Procurer or the End Procurer and the Developer
outlining the terms for purchasing storage capacity or stored energy from the Pumped Storage Plant (PSP).
The agreement can be based on a Tolling Tariff, Composite Tariff, or any other applicable model.
u. "Pumped Storage Sale Agreement” or “PSSA” or “Power Sale Agreement" or "PSA" shall mean an
agreement between the Intermediary Procurer and the End Procurer to facilitate the purchase of storage
capacity or stored energy under the Tolling Tariff or Composite Tariff or any other model. The PSA (or
PSSA) contain the relevant terms from the corresponding Pumped Storage Purchase Agreement (PSPA) or
Power Purchase Agreement (PPA) to enable a "back-to-back" contracting between the Developer and the
End Procurer.
v. "Request for Selection” or “RfS” or “Tender" or "Bid Document" shall mean the tender documents
issued by the Bidding Agency, including Pumped Storage Purchase Agreement (PSPA) and Pumped Storage
Sale Agreement (PSSA) as applicable, for procurement of storage capacity or stored energy through a
competitive bidding process under these Guidelines.
w. "Scheduled Commencement of Supply Date (SCSD)" in relation to the contracted storage capacity shall
mean the date corresponding to the scheduled date of commencement of storage capacity for pumping or
generation of energy as indicated in the RfS.
x. "Tolling Tariff Model” shall mean a model in which the Procurer contracts the storage capacity. The energy
for storage is provided by the Procurer and the same is off taken by the Procurer at a different time after
accounting for losses.
y. The term “Contract” in these Guidelines shall mean Pumped Storage Purchase Agreement or Power
Purchase Agreement or Pumped Storage Sale Agreement or Power Sale Agreement.
Z. The term "Supply" in these Guidelines shall mean supply of stored energy or contracted PSP capacity.
5. Clarification and Modification to Guidelines
5.1. The Procurer shall seek prior approval of the Appropriate Commission for deviations from the process defined
in the Guidelines before the initiation of the bidding process itself. However, for the purpose of clarity, if the
Procurer while preparing the Bid Documents and other Project Agreements, provides detailed provisions that
are consistent with these Guidelines, such detailing shall not be considered as deviations from these Guidelines.
5.2. In the event of any ambiguity, difficulty, or need for modification in interpreting or implementing these
Guidelines, the Ministry of Power shall have the authority to provide clarification.
6. Applicable Laws and Regulations
6.1. All activities/ procurement being undertaken under these Guidelines will be subject to applicable laws, rules,
orders, guidelines and regulations issued by the Appropriate Government and Regulatory Commissions.
PART B: BID
A. GENERAL CONDITIONS OF BID
1. BID/RFS Documentation
1.1. The Procurer shall prepare the bid documents in accordance with set Guidelines. The principles outlined in
these Guidelines shall suitably be detailed in the Standard Bid Documents.
1.2. The Procurer shall invite the bidders to participate in the RfS prepared in accordance with these Guidelines. In
case of bids initiated or already in progress before the notification of these Guidelines, the provisions outlined
in the relevant tender or bid documents shall prevail.
1.3. The Bidding Agency will specify suitable technical and financial eligibility criteria for the bidders, in the
tender documents.
1.4. The procurer may specify in the bid documents if the Project should be established at a site designated by the
Procurer or at a site chosen by the Developer. If the Procurer does not specify the Project site in the bid
documents, the Developer has liberty to choose its own site. Where the location/site/ land is specified by the
Procurer, the details thereof shall be indicated clearly in the bid documents.
1.5. The RfS shall outline the responsibilities of each party regarding the acquisition of necessary clearances,
permits, licenses, land arrangements, etc, including the milestones related to land acquisition, connectivity, and
other project requirements. The RfS shall specify the penalties for non-compliance with such
milestones/requirements and the regular reporting requirements by the Developer.
2. Bid Process
2.1. The procurer shall call for the bids adopting a single stage, two part (Separate Technical Bid & Financial Bid),
bidding process to be conducted preferably through electronic mode (e-bidding).
2.2. The technical bid shall be opened first and the financial bids of only those bidders who qualified in the
technical bid evaluation stage, shall be opened. The Procurer may choose to conduct an e-reverse auction (e-
RA) for selection of bidders, which shall be specifically mentioned in the notice inviting bids and the bid
document. E-procurement platforms with a successful track record, adequate safety, security and
confidentiality shall be used.
2.3. The Procurer shall publish the RfS notice in at least two national newspapers and/or its own website and/or the
Central/State Public Procurement Portal to accord wide publicity.
2.4. The Procurer shall provide opportunity for pre-bid conference to the prospective bidders and shall provide
written interpretation of the tender documents to any bidder which shall also be made available to all other
bidders. All the concerned parties shall rely solely on the written communication. Any clarification or revision
of the bidding documents shall be uploaded on the website of the Procurer for information. In the event of the
issuance of any revision or amendment of the bidding documents, the bidders shall be granted with a period of
at least 7 days there from, for submission of bids.
3. Mode of Procurement
The mode of procurement shall be as specified in the Special Conditions of Bid.
4. Indicative Timelines for Bid Process
4.1. The indicative timelines for different activities of bid process shall be as specified in the Special Conditions of
Bid.
4.2. The Procurer may specify different timelines as per the specific requirements in the RfS document. If the
Procurer gives extended time for any of the events in the bidding process, on account of delay in achieving the
activities required to be completed before that event, or any other reason, such extension of time shall not in
any way be construed as deviation from these Guidelines.
5. Bid Structure
5.1. Bidding Parameter: Allotment of contract shall be based on a Tariff Based Competitive Bidding process. The
Bidding Agency may specify in the RfS, any of the bidding parameters specified in the Special Conditions of
Bid, depending on the project specifics outlined in the RfS.
5.2. The Tariff shall be quoted at the delivery point to be specified in the RfS. In case of Composite Tariff Model,
all the charges and losses till the Delivery Point shall be borne by the Developer, unless otherwise specified in
the RfS. For the Tolling Tariff Model, the responsibility for the charges and losses till the Delivery Point shall
be as specified in the RfS.
5.3. The minimum bid capacity of projects shall be as specified in the Special Conditions of Bid.
5.4. The Procurer may also define the maximum capacity to be allotted to a single bidder, considering factors like
economies of scale, land availability, competition, and market development. The Procurer may allow the
Developer to set up a higher capacity in projects developed in Mode-1 and in such case the Procurer shall have
the first right of refusal to contract the additional capacity/energy.
5.5. Bid Responsiveness
The bid shall be evaluated only if it is responsive and satisfies conditions, inter-alia:
a. Bidder or any of its Affiliate should not be a wilful defaulter to any lender;
b. The Bidder and any of its Affiliate including any Consortium Member and any of its Affiliate, their
directors should not have been barred by any government agency or an authority in India, or by the
government of the jurisdiction of the Bidder or Members where they are incorporated or the jurisdiction of
their principal place of business, or by any international financial institution such as the World Bank
Group, Asian Development Bank, African Development Bank, Inter-American Development Bank, Asian
Infrastructure Investment Bank etc. or by the United Nations or by any of its agencies as on the date of bid
submission.
5.6. Eligibility and Qualification Criteria
a. Formation of consortium by the bidders shall be permitted, in the case of, the consortium shall identify a lead
member which shall be the contact point for all correspondences during the bid process. The Procurer may
specify technical and financial criteria, and lock in requirements for the lead member of the consortium.
b. General Eligibility Criteria: Bidders participating in the tenders issued under these Guidelines should fall
under either of the following categories:
i. A Company under the Companies Act, 2013.
ii. A Foreign Company under the respective nation's laws.
iii. Alternative Investment Funds (AIF) as registered under SEBI. “AIF” shall be as defined by SEBI.
iv. A Consortium comprising of above entities.
The aforementioned categories would be subject to the relevant Acts, Rules, Guidelines, Orders and
Policy documents of the Government of India, as amended from time to time.
c. Technical Eligibility Criteria: To encourage competition by way of increased participation and to ensure
proper implementation of the Projects, the Procurer may specify additional Technical Eligibility Criteria as
specified in the Special Conditions of Bid. Such criteria should be set after an assessment of the number of
project developers - that are expected to meet the criteria so that an adequate level of competition is
achieved. The cut-off date for meeting the Technical Eligibility Criteria should generally be kept as the last
date of bid submission.
d. Financial Eligibility Criteria:
i. Net-worth/Assets under Management (AUM) or Investible Funds:
a. The Procurer shall specify that a Bidder must meet the net-worth requirement as specified in the
Special Conditions of Bid.
b. A Bidder who is a SEBI registered Alternative Investment Funds (AIF) must demonstrate a
cumulative value of Assets under Management (AUM), as specified in the RfS. The net-worth
of an AIF will be calculated as per the Companies Act, 2013 and the value of AUM will be
calculated in accordance with the applicable SEBI (AIF) Regulations and certified by the AIF's
Statutory Auditor.
c. The net-worth of a Consortium Bidder shall be calculated as the combined net-worth of the
Consortium members, along with the net-worth of Affiliates that undertake to contribute equity
funding and provide Performance Guarantee (PG) if any of the Consortium member fails to
meet the obligations as per the RfS.
d. A Bidder (excluding AIF) can qualify based on the financial capability of their Affiliates.
Further, in case of a Bidder who is part of a Bidding Consortium, any member can fulfil the
criteria based on its Affiliate's financial capability. However, in both these cases, the Affiliates
must commit to provide the required equity funding and Performance Guarantee (PG) if the
Bidder fails to do so in accordance with the RfS document. Further, the affiliate(s) shall
maintain their status of Affiliate (as per the definition mentioned in these Guidelines) informed
in the bid, until the Actual Commencement of Supply Date (ACSD) of the project.
ii. Liquidity: It is necessary that the Bidder has sufficient cash flow/internal accruals to manage the
fund requirements for the Project. The Procurer may stipulate suitable parameters such as annual
turnover, Profit Before Depreciation, Interest and Tax (PBDIT), internal resource generation, bidding
capacity etc.
5.7. The quoted tariff shall be exclusive of GST. The developer will be obligated to undertake measures to reduce
GST incidence by availing Input Tax Credit (ITC) or any other tax refund, exemption, or benefit under
applicable tax laws. The final impact of GST shall be reimbursed by the Procurer on production of supporting
documents adjusting for the benefits.
6. Technical Requirements
6.1. The Procurer shall specify the Technical Requirements in the Bid Documents as per the Special Conditions of
Bid.
6.2. The Procurer will encourage the use of proven and operational technologies to reduce technology risks and
ensure timely project commissioning. The specific technical standards applicable to the types of energy storage
projects covered by these Guidelines will be outlined in the bidding documents. These standards will be
regularly updated to align with the latest guidelines, notifications, and industry standards.
6.3. The technical Parameters of PSP, PSP Characterization and Performance Parameters are mentioned in
Appendix-I.
7. Contractual Guarantees
7.1. The Developer shall provide the following instruments to the Procurer in terms of the RfS and the Contract.
7.2. Earnest Money Deposit (EMD)
a. Procurer shall specify the quantum of the Earnest Money Deposit (EMD) as per the Special Conditions of
Bid.
b. The EMD for all the successful bidders shall be valid at least up to the Effective Date of PPA. Thereafter,
EMD will be released and replaced by the Performance Guarantee (PG) in case of successful bidders. For
the remaining bidders, the EMD shall be released after issuance of Letter of Award within the number of
days specified in the Special Conditions of Bid.
c. Forfeiture of EMD or debarring etc., as defined in these Guidelines, shall be undertaken in the event of
failure of the successful bidder to execute the PPA within the stipulated time period.
d. EMD shall be submitted in the form of
i. Bank Guarantee
OR
ii. Payment on Order instrument/Letter of Undertaking
OR
iii. Insurance Surety Bonds which would be paid unconditionally similar to a Bank Guarantee
OR
iv. Any other approved instrument approved by Ministry of Finance, Government of India.
7.3. Performance Guarantee (PG)
a. A Procurer will fix the Performance Guarantee (PG) as per the Special Conditions of Bid.
b. A PG shall be submitted at the time of signing of the PPA in the form of:
i. Bank Guarantee
OR
ii. Payment on Order instrument / Letter of Undertaking to be furnished by the bidders to be used
to pay in case a Developer defaults in terms of PPA
OR
iii. Insurance Surety Bonds which would be paid unconditionally similar to a Bank Guarantee
OR
iv. Any other approved instrument approved by Ministry of Finance, Government of India.
c. In addition to other remedies, this PG can be encashed to recover any damages/dues of the Developer in
terms of the PPA. The damages/dues recovered by the Intermediary Procurer by encashing the PG, upon
the default of the Developer under the PPA, shall be credited to the Procurer.
d. The PG will be returned, after deducting any liquidated damages, to the Developer within 'D' days of the
Actual Commencement of Supply Date (ACSD) of the full contracted capacity or the last part of
contracted capacity accepted by the Procurer. However, the Procurer/Intermediary Procurer may extend
this period up to a maximum of 'M' months from the ACSD, which will be clearly specified in the
Bidding Documents. 'D' and 'M' are specified in the Special Conditions of Bid. In the case of partial
commissioning of the contracted capacity, the PG corresponding to the part commissioned contracted
capacity shall be released after deducting any liquidated damages, within the time specified in the Bidding
Documents.
e. As an alternative to encashing the PG, the Procurer/Intermediary Procurer may allow the Developer to
furnish the requisite amount through Demand Draft/electronic payment against the release of the relevant
PG without any encashment.
f. A Procurer may release the Bank Guarantee submitted by the Developer if the Developer is able to replace
the same with an alternative PG as per these Guidelines, issued by any agency notified by the Government
of India or State Government, to pay in case a Developer defaults in terms of PPA.
g. Compliance of FDI Laws by foreign bidders: In case, a Foreign Company is selected as the successful
bidder, it shall comply with all the laws and provisions related to Foreign Direct Investment in India.
8. Submission and Evaluation of Bids
8.1. The bidders may be required to submit non-refundable processing fee and/or success fee, as specified in the
RfS.
8.2. The bidders shall be required to submit separate technical and price bids. The bidders shall also be required to
furnish necessary bid-guarantee in the form of an EMD along with the bids.
8.3. The Procurer shall constitute a committee for evaluation of the bids called Evaluation Committee, with at least
three members, including at least one member with expertise in financial matters/ bid evaluation. The
evaluation committee should satisfy itself that the price of the selected offer is reasonable and consistent with
the requirement. The evaluation committee shall have the right to reject all price bids if the rates quoted are not
aligned with the prevailing market prices.
8.4. The technical bids shall be evaluated to ensure that the bids submitted meet the eligibility criteria set out in the
RfS document on all evaluation parameters. Only the bids that meet the evaluation criteria set out in the RfS
shall be considered for further evaluation on the price bids.
8.5. To ensure competitiveness, the minimum number of qualified Bidders should be two. If the number of
qualified bidders is less than two, even after three attempts of bidding, and the Procurer still wants to continue
with the bidding process, the same may be done with the consent of the Appropriate Commission.
8.6. The price bid shall be rejected, if it contains any deviation from the bid conditions. No clarifications shall
normally be requested from bidders at this stage.
8.7. Bid Evaluation shall be carried out in terms of parameters as mentioned in the RfS through ranking of Bids in
ascending order of the Bidding Parameter. The Bidding Agency may carry out electronic reverse auction for
award of Projects.
8.8. The detailed procedure for evaluation of the bid and selection of the successful bidder(s) shall be provided in
the RfS.
8.9. After the conclusion of bidding process, the Evaluation Committee constituted for evaluation of bids shall
critically evaluate the bids and certify as appropriate that the bidding process and the evaluation has been
conducted in conformity with the provisions of these Guidelines.
B. SPECIAL CONDITIONS OF BID
The clauses in the Special Conditions correspond to and must be read in conjunction with the clauses in the General
Conditions within the respective part of the document.
3. Mode of Procurement
The mode of procurement may be either of the following:
a. Mode 1 - Procurement from a PSP developed on a site identified by the Procurer: The Procurer may
choose to locate the Project at a site pre-specified and identified in the bidding documents. Where the site
belongs to the Government or a Government entity, to ensure inter-generational equity in the utilisation of
such site, the development shall be on “Build Own Operate Transfer (BOOT)” basis for a period of 25 to 40
years, which shall be specified in the RfS. In BOOT mode of implementation, the project will be transferred
after the end of term of the agreement to an entity identified by the State Government at a pre specified
amount to be specified in the RfS.
The Procurer shall issue a Detailed Project Report (DPR) made in accordance with the provisions of the
relevant Guidelines along with the bid.
Further, to de-risk the project, the procurer shall form a Special Vehicle (SPV) which shall undertake all
pre-feasibility activities. These activities include applying for and initiating the process of securing all
clearances including environmental clearance, forest clearance, land procurement, and other statutory
clearances as may be applicable. The SPV shall be incorporated as a wholly owned subsidiary of the
procurer entity with a minimum shareholding of Rs. 1 lakh under the Companies Act. The SPV
incorporated by the procurer would be transferred to the successful bidder at a cost equivalent to the sum
total of the par value of shareholding in the company and the expenditure incurred by the procurer in
operation of SPV, which shall be pre-specified in the RfS.
b. Mode 2 - Procurement from a PSP developed on a site identified by the Bidder or an already
commissioned PSP or under development PSP: In this case Supply will be from a PSP developed on a
site identified by the bidder or from an already commissioned or under development PSP. In this case the
development may be on "Build-Own-Operate (BOO)" basis for a period of 15 to 40 years, which shall be
specified in the RfS. PSP Developers may self-identify potential sites where a PSP can be constructed or
offer storage from already commissioned or under development projects. The PSP Developer shall obtain
the statutory clearances including concurrence under Section 8 of the Electricity Act, environmental
clearance, forest clearance, land procurement etc. before the commencement of construction of the project.
The Procurer shall not be responsible in case of delay in obtaining any required clearances. The selected
bidder (s) may be required to submit the approved DPR before signing the PPA.
4.1. Indicative Timelines
a. The indicative timeline for different activities under the Mode 1 and Mode 2 shall be as under:
+-----+---------------------------------------------------------------------------------------------------------------------+---------------------------------------+-------------------------------------+
| Sl. | Event | Time from Zero date (for | Time from Zero date (for |
| No | | Mode 1 of procurement) | Mode 2 of procurement) |
+=====+=====================================================================================================================+=======================================+=====================================+
| 1 | Date of issue of Bid Documents | Zero date | Zero date |
+-----+---------------------------------------------------------------------------------------------------------------------+---------------------------------------+-------------------------------------+
| 2 | Pre-bid conference, Bid Clarifications, | ** | ** |
| | opening of online Data Room to share project | | |
| | specific details including site, if specified by | | |
| | the Procurer etc., and revision of RfS | | |
| | document | | |
+-----+---------------------------------------------------------------------------------------------------------------------+---------------------------------------+-------------------------------------+
| 3 | Bid submission | 90 days | 60 days |
+-----+---------------------------------------------------------------------------------------------------------------------+---------------------------------------+-------------------------------------+
| 4 | Evaluation of Technical bids | 120 days | 90 days |
+-----+---------------------------------------------------------------------------------------------------------------------+---------------------------------------+-------------------------------------+
| 5 | Evaluation of Financial bids and conduct of | 150 days | 120 days |
| | e-RA | | |
+-----+---------------------------------------------------------------------------------------------------------------------+---------------------------------------+-------------------------------------+
| 6 | Issuance of Letter of Award | 195 days | 165 days |
+-----+---------------------------------------------------------------------------------------------------------------------+---------------------------------------+-------------------------------------+
| 7 | Date of filing of petition for adoption of tariff | 225 days | 195 days |
| | by SERC/CERC# | | |
+-----+---------------------------------------------------------------------------------------------------------------------+---------------------------------------+-------------------------------------+
| 8 | a. Signing of Share purchase agreement of | 285 days | 255 days |
| | SPV (Mode-1) (if applicable) | | |
| | and/or | | |
| | b. Signing of PPA and PSA (if applicable) | | |
+-----+---------------------------------------------------------------------------------------------------------------------+---------------------------------------+-------------------------------------+
** In case of any change in RfS document, the Procurer shall provide the bidders with additional time.
# Commission shall adopt tariff within 60 days of filing the petition.
5.1 Bidding Parameters:
a. Storage charge (Rs/{MW/kW}/{year/month})
b. Storage charge (Rs/{MW/kW}/{year/month}) with a pre-specified VGF/ Annuity support
c. Composite Tariff (Rs/kWh basis) for electricity including the cost of input power and storage. In
this case input power is arranged by the Developer ("Composite Tariff Model")
Note:
1. In case the procurement is based on storage charge i.e., “Tolling Tariff Model”, the input power shall be
arranged by the Procurer of the storage capacity.
2. The Procurer may specify an escalating tariff structure for the Bid Parameters specified in 5.1(a), (b) and
(c) in the Bid document.
5.3 Minimum Bid Capacity: For ISTS connected projects, the minimum bid capacity that can be offered by
the bidder should be 50 MW. For InSTS connected projects, i.e., when the Procurer and the identified PSP
are within the same State, the minimum bid capacity may be at least 10 MW. For projects in North-Eastern
States, Special Category States, and other InSTS-connected projects, based on the availability of land and
transmission facilities, a smaller minimum capacity may be allowed but this should be clearly specified
beforehand in the RfS. However, the Procurer may specify a project size different from the limits specified
hereunder in the RfS document.
5.6 Qualification requirements to be met by the bidders
a. Technical Eligibility Criteria: Applicants must demonstrate experience in developing infrastructure
sector projects within the past five (5) years. Specific details will be outlined in the Request for
Proposal (RfS), including:
• Minimum Aggregate Capital Expenditure: The total capital expenditure for all qualifying
infrastructure projects undertaken in the last five (5) years must meet a threshold specified
in the RfS.
• Minimum Capital Expenditure per Project: Each qualifying infrastructure project must
have a minimum capital expenditure as defined in the RfS.
b. Financial Eligibility Criteria:
ii. Net-worth/Assets under Management (AUM) or Investible Funds: Net-worth equivalent of
at least 20% of the estimated capital cost of the contracted capacity of the PSP for the
financial year in which bids are issued. The estimated capital cost will be determined by the
Bidding Agency.
ii. Liquidity: It is necessary that the Bidder has sufficient cash flow/internal accruals to manage the
fund requirements for the Project. The Procurer may stipulate suitable parameters such as annual
turnover, Profit Before Depreciation, Interest and Tax (PBDIT), internal resource generation, bidding
capacity etc.
5.7. The quoted tariff shall be exclusive of GST. The developer will be obligated to undertake measures to reduce
GST incidence by availing Input Tax Credit (ITC) or any other tax refund, exemption, or benefit under
applicable tax laws. The final impact of GST shall be reimbursed by the Procurer on production of supporting
documents adjusting for the benefits.
6. Technical Requirements
6.1. The Procurer shall specify the Technical Requirements in the Bid Documents as per the Special Conditions of
Bid.
6.2. The Procurer will encourage the use of proven and operational technologies to reduce technology risks and
ensure timely project commissioning. The specific technical standards applicable to the types of energy storage
projects covered by these Guidelines will be outlined in the bidding documents. These standards will be
regularly updated to align with the latest guidelines, notifications, and industry standards.
6.3. The technical Parameters of PSP, PSP Characterization and Performance Parameters are mentioned in
Appendix-I.
7. Contractual Guarantees
7.1. The Developer shall provide the following instruments to the Procurer in terms of the RfS and the Contract.
7.2. Earnest Money Deposit (EMD)
a EMD shall not be less than 2% (two percent) of the estimated capital cost of the contracted
capacity in MW for the new PSP for the year in which bids are invited or as per the upper limit
stipulated by Ministry of Finance from time to time, whichever is lower.
b EMD shall be released within 15 days of issue of LOA for other than selected bidder.
7.3 Performance Guarantee (PG)
a PG shall not be less than 5% (five percent) of the estimated capital cost of the contracted capacity
in MW for the new PSP for the year in which bids are invited, or as per the upper limit stipulated by
Ministry of Finance from time to time, whichever is lower.
d Timeline 'D' = Sixty (60) days, 'M' = Six (6) months
PART C: CONTRACT
A. GENERAL CONDITIONS OF CONTRACT
1. Contract Award and Conclusion
1.1. The PPA shall be signed by the Procurer with the successful Bidder/ Project Company or the SPV as the case
may be.
1.2. In case of involvement of an Intermediary Procurer, the Intermediary Procurer shall enter into a PPA with the
Developer(s) and a PSA with the End Procurer (s). The PSA shall contain the relevant provisions of the PPA to
enable back-to-back contracting of stored energy/storage capacity between the Developer and the Procurer. The
PPA(s) should preferably be signed immediately after signing of the PSA(s). The Intermediary Procurer shall
be entitled to charge a trading margin at 7 paise per unit of discharged energy or as specified by the
Appropriate Commission, for composite tariff model and 1% of the capacity charges in ( Rs/MW/month) or as
specified by the Appropriate Commission, for Tolling tariff model, from the Procurer for purchase and sale of
storage capacity or stored energy.
1.3. The power procurement for Distribution licensees in some States is centralized through a holding company or a
government agency. Such companies/ agencies will be considered as Procurer and not as Intermediary Procurer
for the purposes of these Guidelines.
1.4. In case of delay in signing of PPA beyond a period of six (6) months from the date of issuance of LoAs, or any
other extended date as mutually agreed between the Bidding Agency and the successful bidders not exceeding
12 months, the awarded capacity shall stand cancelled. In certain cases, after the above deadline, if the
cumulative capacity eligible for signing of PPAs is lower than the cumulative capacity awarded under the
tender, further course of action to be decided by the Bidding Agency will be clearly specified in the Bid
document.
1.5. To ensure transparency, the Procurer shall, after the execution of the PPA, publicly disclose the name(s) of the
successful bidder(s) and the tariff/ charges quoted by them together with breakup into components, if any. The
public disclosure shall be made by posting the requisite details on the website of the Procurer for at least thirty
(30) days.
1.6. The Procurer or the Intermediary Procurer shall approach the Appropriate Commission for adoption of tariff
under section 63 of the Act within thirty (30) days of issue of LoA.
1.7. The tariff shall be adopted by the Appropriate Commission within sixty (60) days of the application date. If the
Appropriate Commission fails to decide within sixty (60) days of the application date, the Procurer(s) shall
grant an extension of time in Scheduled Commencement of Supply Date (SCSD) and Financial Closure (FC)
Date to the Developer. This extension should correspond to the time taken by the Appropriate Commission in
adoption of tariff beyond sixty (60) days of application date.
1.8. The PPA shall include standard provisions, including but not limited to the following, which, unless otherwise
specified, will be mirrored in the PSA.
2. Term
The term of the PPA will be determined by the Procurer based on the intended use of the plant, and this will be
explicitly specified in the RfS document. Following the expiry of the PPA period, the Developer will be free to
continue operating the Project. It is important to note that when the Project site is designated by the Procurer,
the Procurer's responsibility for land arrangements shall be limited to the PPA period.
3. Performance Parameters
Performance parameters and other conditions shall be as specified in the Special Conditions of Contract
4. Liquidated Damages
4.1. The Liquidated Damages on account of shortfall in meeting performance criteria, specified in the Bidding
Documents, PPA, or PSA, should be genuine and a reasonable estimate of potential damages for the Procurer/
Intermediary Procurer(s).
4.2. Any shortfall in availability of capacity below the committed capacity shall incur charges on a pro-rata basis at
the capacity rate or at a predetermined number specified in the RfS.
4.3. Predefined Liquidated Damages for deviations related to ancillary services parameters, as specified in the RfS,
will be imposed.
4.4. Any other Liquidated Damages specified in the Special Conditions of Contract and RfS Document.
5. Terms of procurement
5.1. The penalty for non-performance shall be as specified in the RfS. The scheduling and its punching thereof at
different Regional Load Despatch Centres (RLDCs) / State Load Despatch Centres (SLDCs) (including the
injecting, intervening and buyer SLDCs / RLDCs) shall be the responsibility of Developer.
5.2. Additional terms will be as specified in the Special Conditions of Contract
b. Extension charges will be Rs. 1,000 per MW of contracted capacity per day of delay in SCSD.
8. Transmission Connectivity
8.2 Connectivity/GNA/Open Access to the CTU/STU Grid to be applied with 'D' = Sixty (60) days of issue of
LoA.
8.5. Transmission Connectivity additional conditions
In case of procurement of storage capacity, the responsibility of supplying charging energy to the contracted
PSP capacity at the Metering Point as well as transmission of discharged energy from contracted PSP capacity
beyond the Metering Point shall be that of the End Procurer.
9. Commencement of Supply
9.2 Commencement of Storage Schedule
(i) Projects shall generally commence within a period of:
+-------+---------------------------+--------------+-----------------------------------------+
| Sl. No. | Procurement Mode Type | Type of PSP | SCSD (Months) after Effective Date of PPA |
+-------+---------------------------+--------------+-----------------------------------------+
| 1. | Mode 1 | Off-river | 48 months |
| | | On-river | 66 months |
+-------+---------------------------+--------------+-----------------------------------------+
| 2. | Mode 2 | - | As per the requirement of procurer |
+-------+---------------------------+--------------+-----------------------------------------+
9.3 Early Commencement
Notice period will be at least 'D' = Fifteen (15) days
9.4 Minimum part capacity for commissioning
The minimum capacity of first part for part commissioning shall be 50% of Project Capacity or 50 MW,
whichever is lower.
9.5. Early and Part Commissioning
In capacity procurement contracts, if the project is partially commissioned, payments according to the PPA
may be made on pro-rata basis, proportionate to the commissioned capacity. The decision to procure the part-
commissioned capacity lies solely with the Procurer/Intermediary Procurer. If they choose not to consider
procurement until full commissioning, the part-commissioned capacity can be sold in the open market until
the SCSD.
10. Compensation for off-take constraints
The Procurer may be constrained to off-take the energy storage capacity offered/ power scheduled by the
Developer on account of transmission constraints and grid security and in such case, the applicable
Compensation for reduced off-take shall be as under:
a. In case of procurement being on Tolling Tariff Model: Period of reduced off-take to be considered as
deemed available for payment to Developer if the annual availability is less than normative annual
availability specified in RfS. The total availability after such adjustment shall not be higher than
normative availability.
b. In case of procurement being on Composite Tariff Model: If the annual energy supplied falls below
the contracted amount specified in the Request for Selection (RfS), the following provision shall apply:
(i). Payment Adjustment: - The Procurer for the reduced energy will pay at a rate stipulated in the
RfS but not exceeding 60% of the composite tariff in the Power Purchase Agreement (PPA).
13. Event of Default and Consequences Thereof
b Damages equivalent to 'M' = 24 (Twenty-Four) months
c Damages equivalent to 'M' = 24 (Twenty-Four) months
e Damages equivalent to 'M' = 24 (Twenty-Four) months
Appendix-I
Technical Parameters of PSP, PSP Characterization and Performance Parameters
I. For Mode 1 Procurement, the Procurer shall submit the Pre-Feasibility Report (PFR) and Detailed Project
Report (DPR) of the project along with the RfS, which shall also specify the status of requisite clearances and
approvals, including those already obtained or applied for by the Procurer. However, for Mode 2
Procurement, relevant information may be specified in the tender.
II. A tentative format for the PFR is provided below. The table below is not exhaustive, and the Procurer may add
additional information as needed.
III. General Technical particulars for PSP shall be as under (applicable for Mode-I only):
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| S. No. | Parameter | Unit |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 1 | Type of Power plant (Underground/Surface) | |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 2 | Type of PSP | |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 3 | Capacity of the plant | MW |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 4 | Duration of storage | Hours |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 5 | Number of Generation Cycles (per Day) | |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 6 | Number of Pumping Cycles (per Day) | |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 7 | Number of units | |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 8 | Unit Capacity (Turbine/Pump) | MW |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 9 | Maximum Head (Turbine) | Meter |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 10 | Rated Head (Turbine) | Meter |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 11 | Minimum Head (Turbine) | Meter |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 12 | Maximum Head (Pump) | Meter |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 13 | Rated Head (Pump) | Meter |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 14 | Minimum Head (Pump) | Meter |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 15 | Elevation & dimensions of upper dam | Meter |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 16 | Elevation & dimensions of lower dam | Meter |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 17 | Maximum head(upper/lower) | Meter |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 18 | Minimum head (upper/lower) | Meter |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 19 | Suction Head | Meter |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 20 | Proposed Speed | RPM |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 21 | Upper reservoir capacity | MCM |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 22 | Lower reservoir capacity | MCM |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 23 | Live storage capacity (Upper/Lower Reservoir) | MCM |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 24 | Unit Discharge | Cubic Meter/ Second |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 25 | Length of water conductor system | Meter |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 26 | Centre line of unit | Meter |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 27 | Planned Unit spacing | Meter |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 28 | Planned Elevation of machine floor | Meter |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 29 | Generator barrel diameter | Meter |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 30 | Planned Size of powerhouse (L X W X H) | MxMxM |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 31 | Planned Size of Transformer Cavern/Hall (L X W X H) | MxMxM |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 32 | Planned Switchyard Type (AIS/GIS) | |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 33 | Planned Maximum possible transportation dimensions of any E&M equipment | MxMxM |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 34 | Planned Max possible weight of any E&M equipment | Kg |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 35 | Planned Size of Switchyard (L X W) | MxM |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 36 | Transmission Voltage | kV |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 37 | Proposed Nearest Pooling Station | |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
| 38 | Proposed Location/Locations of Pumping Energy Source | |
+-------+-------------------------------------------------------------------------------------------------+-------------------+
IV. Technical features and performance of PSP Machine
+-------------------------------------------------------------------------+-----------------------------------------------------+
| Features | Requirements |
+=========================================================================+=====================================================+
| Efficiency | Pump Turbine eff. >90.5% |
| | Motor Generator eff. >98% |
+-------------------------------------------------------------------------+-----------------------------------------------------+
| Cycle efficiency* | >75% |
+-------------------------------------------------------------------------+-----------------------------------------------------+
| Fast transition between operating modes | ~7 - 15 min |
+-------------------------------------------------------------------------+-----------------------------------------------------+
| Power factor | Yes |
+-------------------------------------------------------------------------+-----------------------------------------------------+
| Controllable reactive power | Yes |
+-------------------------------------------------------------------------+-----------------------------------------------------+
| Grid oscillation damping (PSS) | Yes |
+-------------------------------------------------------------------------+-----------------------------------------------------+
| Inertia | Yes |
+-------------------------------------------------------------------------+-----------------------------------------------------+
| Fast transition in turbine power (min.-Full load) / (Full – min. load) | <60s. Limited by hydraulic transient. |
+-------------------------------------------------------------------------+-----------------------------------------------------+
| Synchronous Condenser Mode | Yes |
+-------------------------------------------------------------------------+-----------------------------------------------------+
*Procurer may specify any higher efficiency not exceeding 80%.
V. Codes & Standards
1. Material and equipment pertaining to construction and machine shall conform to relevant IS codes and
international codes.
2. Field and laboratory testing, and procedures for material shall conform to relevant IS codes and international
codes.
VI. Design & Safety
1. These projects shall have simpler design with minimum requirement of River Diversion works, Desilting &
Silt Flushing arrangements, Surge Chambers and very small water conductor systems.
2. Location of project shall have minimal environmental issues such as, Fisheries, Environmental Flows and
CAT Plans including R&R.
Note: Bidding Agency may modify these specifications based on specific requirements considering applicable
Guidelines, Standards, etc. issued by CEA or any other Govt. Agency.
HEMANT KUMAR PANDEY, Chief Engineer