No. JERC-JKL/Reg/2024/6.—In exercise of the powers conferred under section 46, read with section 181,
of the Electricity Act, 2003 (36 of 2003) and all other powers enabling it in this behalf, the Joint Electricity Regulatory
Commission for the UT of Jammu & Kashmir and the UT of Ladakh hereby makes the following Regulations.
18
THE GAZETTE OF INDIA : EXTRAORDINARY
[PART III-SEC.4]
Chapter-I
1. Short Title, Commencement and Extent
1.1. These Regulations shall be called the Joint Electricity Regulatory Commission for the UT of Jammu &
Kashmir and the UT of Ladakh (Licensee's Power to Recover Expenditure incurred in providing supply and
other miscellaneous charges) Regulations, 2024.
1.2. These Regulations shall be applicable to all the distribution licensees in the UT of Jammu & Kashmir and the
UT of Ladakh.
1.3. These Regulations shall come into force from the date of their publication in the UT of Jammu & Kashmir and
the UT of Ladakh.
Chapter-II
2. Definitions
2.1 In these Regulations, unless the context otherwise requires:
a. "Act" means the Electricity Act, 2003 (36 of 2003), including amendments thereto;
b. "Applicant” means an owner or occupier of any land/premises (including the authorized representative of
such owner or occupier) who makes an application to a licensee for the supply of electricity and/or for any
other purpose covered under these Regulations;
с. "Commission” means the Joint Electricity Regulatory Commission for the UT of Jammu & Kashmir and the
UT of Ladakh;
d. "Distribution Licensee” means a Licensee authorized to operate and maintain a Distribution System for
supplying electricity to the Consumers in their Area of Supply.
e. "Distribution main" means the portion of any main with which a service line is, or intended to be,
immediately connected.
f. "Demand Notice” means the notice to be issued by the licensee to the applicant in accordance with the Joint
Electricity Regulatory Commission for the UT of Jammu & Kashmir and the UT of Ladakh (Electricity
Supply Code) Regulations, 2023, read with the provisions of these Regulations.
g. "Distribution system” means the system of wires and associated facilities between the delivery points on the
transmission lines or the generating station connection and the point of connection to the installation of the
consumer;
h. "Electrical plant" means any plant, equipment, apparatus, or appliance or any part thereof used for, or
connected with, the generation, transmission, distribution, or supply of electricity but does not include:
i. an electrical line; or
ii. a meter used for ascertaining 'the quantity of electricity supplied to any premises; or
iii. an electrical equipment, apparatus, or appliance under the control of a consumer.
i. "Extra high tension (EHT)” means supply voltages above 33000 volts;
j. "High Tension (HT) supply” means electricity supplied at a Voltage greater than 400 V and lesser than
33000 V.
k. "Low Tension (LT) supply” means electricity supplied at a Voltage not exceeding 440 volts.
l. "Supply Code" means the Joint Electricity Regulatory Commission for the UT of Jammu & Kashmir and
the UT of Ladakh (Electricity Supply Code) Regulations, 2023, read with its amendments from time to time
and the provisions of these Regulations; and
m. Other words and expressions used and not defined in these Regulations, but defined in the Act, shall have the
meanings as assigned to them in the Act.
n. "Year" means financial year
2.2 The words and expressions used in these Regulations and not defined herein, but defined in the Act / Rules or
any other Regulations of the Commission, shall have the meaning assigned to them under the Act / Rules or
any other Regulations of the Commission.
19
THE GAZETTE OF INDIA : EXTRAORDINARY
[PART III-SEC.4]
2.3 Interpretation:
In the interpretation of these Regulations, unless the context otherwise requires:
(a) Words in the singular or plural term; as the case may be, shall also be deemed to include the plural or the
singular term, respectively.
(b) The terms "include" or "including" shall be deemed to be followed by "without limitation" or "but not limited
to" regardless of whether such terms are followed by such phrases or words of like import.
(c) References herein to the "Regulation" shall be construed as a reference to these Regulations as amended or
modified by the Commission from time to time in accordance with the applicable laws in force.
(d) The headings are inserted for convenience and may not be taken into account for the purpose of interpretation
of these regulations.
(e) References to the statutes, regulations, or guidelines shall be construed as including all provisions
consolidating, amending, or replacing such statutes, regulations, or guidelines, as the case may be, referred to.
Chapter-III
3.1 Duty of the distribution licensee to supply electricity on request and recovery of expenditure
i. The Distribution Licensee shall, subject to the provisions contained in Section 43 of the Act, fulfill his
obligation to supply electricity to the premises of consumers. Subject to the provisions of the Act and these
Regulations and subject to such directions, orders, or guidelines as the Commission may issue from time to
time, every Distribution Licensee is allowed to be recovered from an applicant, requiring supply of electricity,
any expenses that the Distribution Licensee shall be required to reasonably incur to provide any electric line or
electric plant specifically for the purpose of giving such supply to the applicant.
ii. The Licensee shall lay free of charge a service line (overhead line or underground cable depending upon the
type of distribution system existing) up to a length of 30 meters from its nearest distributing main on public
roads, outside the limits of the property in respect of which requisition for electricity supply is received.
iii. The entire service line, notwithstanding that a portion thereof has been paid for by the Consumer, shall be the
property of the Distribution Licensee and by whom it shall be maintained and the Distribution Licensee has a
right to use it for the supply of energy to any other person by taping the service or otherwise except if such
supply is detrimental to the supply to the consumer already connected therewith.
3.2 Power to recover expenditure: Subject to the provisions of the Act and these Regulations and subject further
to such directions, orders, or guidelines that the Commission may issue, the distribution licensee is authorized
to recover such expenses as may be reasonably incurred by it in providing any electric line and the electrical
plant used for the purpose of giving supply of electricity and the recoverable expenditure shall be computed in
accordance with the principles contained in these Regulations and at the rates approved by the Commission
pursuant to these Regulations.
3.3 Expenses for providing service line- The distribution licensee shall recover all expenses reasonably incurred
on the works related to laying of the service line to the premises of the applicant as well as the cost of
providing terminal equipment and other arrangements (except the cost of meter, CT and PT) at the applicant's
premises:
Provided that the distribution licensee may, with the approval of the Commission, recover the expenses on the
basis of average or normative rates for providing the service lines for the purpose of giving supply of electricity
to one or more categories of applicants based on connected load or contract demand, voltage level, nature of
load, tariff classification and length and specification of service lines:
Provided further that in cases where the normative rates have been approved by the Commission for a
particular period for a particular type of service line, the recovery for laying of that type of service line shall be
made by the distribution licensee only in accordance with the rates and terms and conditions so approved by
the Commission for that period:
Provided further that the Commission may direct the licensee to recover the cost-of-service line under this
regulation at fixed per kilometer rates, based on the standard cost data, for all or any of the categories:
Provided further that the average or normative rates shall, unless specifically approved by the Commission, not
apply to the temporary connections.
20
THE GAZETTE OF INDIA: EXTRAORDINARY
[PART III-SEC.4]
3.4 Expenses for the distribution system other than service lines- (1) The distribution licensee shall also be
authorized to recover such proportion, as may be considered reasonable by the Commission, of the expenses
incurred, or to be incurred, for creation, including augmentation or additions, of the distribution system, other
than those for the service lines, for the infrastructural development as a continuous and coordinated process, so
as to meet its obligations for supply of power to the applicants for permanent connections under the Supply
Code and such recovery shall be regulated under the provisions of this regulation and also other relevant
provisions of these regulations.
(2) Other than provisions provided under sub-regulation (3), the distribution licensee shall recover the expenses in
the shape of infrastructural development charges at the normative rates and associated terms and conditions, as
may be approved by the Commission for the various slabs and categories based on the connected load or
contract demand and/or supply voltages and/or nature of loads and/or geographical areas and/or tariff
classification:
Provided that for determining the normative rates per kW or kVA for the connected load or contract demand,
as the case may be, the Commission shall ordinarily consider the following on a normative basis:
i. the estimated cost of providing, erecting, and commissioning one transformer of appropriate capacity and
voltage ratings on normative basis, along with two bays (i.e., one on each side of the transformer) but
excluding the cost of land and other components of the sub-station;
ii. the estimated costs of two electrical lines (i.e., one for each side of the transformer considered under the
preceding clause (i)) of such normative lengths as may be considered appropriate by the Commission;
iii. any other costs as may be considered appropriate by the Commission;
iv. the connected loads or contract demands, as the case may be, that can be catered for various categories under
preceding clauses (i), (ii), and (iii) after applying suitable demand and diversity factors and suitable factor(s)
for redundancy in the system; and
V. allocation factors as well as the terms and conditions, as the Commission may find to be reasonable and
appropriate:
Provided further that the Commission may fix the normative rates in terms of per kVA of the contract demand
and per kW of connected load, as the case may be:
Provided further that the Commission may, while fixing the normative rates, restrict the rates worked out under
the first proviso to this sub-regulation to such ceiling limits for respective categories as it may consider
necessary:
Provided further that the normative rates shall, unless specifically approved by the Commission, not apply to
the temporary connections:
Provided further that the entire cost, including the cost of all components as well as the additional recovery or
refund under sub-regulation (9), of the bays required to be executed at the sub-station(s), including the cost of
re-organizing the bays, if any, exclusively for facilitating and/or controlling the supply of power to an applicant
or group of applicants shall also be recovered from the applicant(s) in addition to the normative rates:
Provided further that in cases where provisions of sub-regulation (3) are attracted, the amounts worked out
under this sub-regulation and sub-regulation (9) shall be considered as the minimum amounts to be borne by
such applicants.
(3) In case of an applicant or group of applicants (s), where-
i. The supply of power is required at a site in an area, that does not have appropriate infrastructure for
catering loads of the nature and quantum required by the applicant(s) and where no other significant
growth of load, at the voltage level similar to that at which supply is required, is foreseen in the immediate
future, including the sites where locations of the loads depend upon the geographical factors and
availability of basic raw-material such as for cement factories and construction power for hydro-electric
projects; and
ii. the total estimated cost of the works required to be executed for the appropriate capacities, keeping in view
the minimum capacities standardized or generally planned by the licensee for the relevant voltage level(s),
exceeds the summation of the amounts payable by the applicant or the group of applicants pursuant to sub-
regulation (2);
The licensee may require the applicant or the group of applicants to deposit the entire estimated cost of the
works required for facilitating adequate provision in backup system and supply of power to such applicants:
Provided that if subsequent to receipt of applications but before the commissioning of works, some more
application(s) are received for loads to be released on a permanent basis, at voltage levels similar to those for
the original applicant(s), by using the works envisaged for the original applicants, such additional applications
shall be clubbed together with the original applications for the purpose of recovery of costs and treated at par
with original applicants and shall also be considered as an original applicant(s) for all intents and purposes of
regulation 3.4 and regulation 3.5:
Provided further that in case of works required to be executed for a group of applicants under this sub-
regulation, the costs shall be apportioned as under-
i. cost of common works shall be recovered on a pro-rata basis in the ratio of contract demands of various
applicants;
ii. cost of exclusive works shall be charged exclusively to the applicant(s) for whom such works have
been/are required to be executed; and
iii.cost of other works shall be charged, on a proportionate basis, to the applicants for whose benefit such
works are required to be used:
Provided further that the provisions under the succeeding sub-regulations (4) to (9) shall also be applicable in
case of the connections released under this sub-regulation.
(4) The licensee shall be entitled to use the spare capacity in the works executed under sub-regulation (3) for the
release of connections to the subsequent applicant(s), or otherwise, and also to recover the charges/costs, as
per sub- regulations (2) and (9) as applicable, from such subsequent applicant(s).
(5) The original applicant (s) under sub regulation 3, who have borne the entire cost of the infrastructural works,
shall be entitled to use the spare capacity, if any, after providing for 30% redundancy in the total system
created at their cost and the capacities used pursuant to preceding sub-regulation(4), on first come first serve
basis, and no additional infrastructural development charges shall be recovered from such an original
applicant/developing agency for use of such spare capacity so long as the amount borne by him after
excluding the cost of exclusive work(s) and after adjusting the amount of refunds, if any, under succeeding
sub-regulations(6),(7) and (8) is more than the minimum amount payable by him as per the sub-regulations
(2) and (9) in respect of the total connected load/contract demand sanctioned, including the same sought to be
sanctioned under this sub-regulation in his favour, as worked out at the rates for the respective periods in
which such loads/demands are sanctioned.
(6) If a subsequent application(s) are received within 5 years after the date of commissioning of works executed
under sub-regulation (3), for permanent supply of power at a voltage level similar to that for the original
applicant(s) under sub-regulation (3) and supply of power to such applicant(s) essentially involves usage of
such works, on regular basis, the infrastructural development charges, if any, actually recovered from such
subsequent applicants for the usage of spare capacity as quantified in accordance with sub-regulation (8) shall
be refunded, on pro-rata basis, to the original applicant(s) under sub-regulation (3), who had borne the full
cost, to the extent of the permissible amount of refund under succeeding sub-regulations (7) and (8) :
Provided that if the provision for supply to such new applicant (s) requires execution of certain additional
infrastructural works, apart from the usage of the facilities/works created at the cost of original applicant(s)
under sub-regulation (3), the cost of such additional works shall first be deducted from the infrastructural
development charges recovered from such new applicant (s) and only the balance amount, if any, out of the
amounts recovered from such new applicants, shall be refunded, on pro-rata basis, to the original applicant(s)
who had borne the entire cost.
(7) The maximum permissible amount of refund to any original applicant under sub-regulation (3) shall not
exceed the amount actually paid by him in excess of the summation of the following-
i. the infrastructural development charges under sub-regulations (2) and (9) on the total connected
load/contract demands sanctioned originally and including those availed subsequently by the same
applicant, under sub-regulation (5), at the rates applicable for the respective periods in which such
loads/demands are sanctioned; and
ii. the cost of works, including the bays required at the existing and/or new sub-stations, as may be
executed or required to be executed exclusively for facilitating, control, and or supply of power to such
applicant or group of applicants:
Provided that such applicant(s) shall not be entitled to any interest on any part of the amount paid by them in
respect of the period between the date of payment and refund, if any.
(8) For the purpose of these Regulations, the spare capacity shall be determined with reference to the capacity of
all main components of the works referred to in sub-regulation (3), including line(s) and transformer(s), and
only such spare capacity as is concurrently available in all the components, after providing for 30%
redundancy in each of the components, shall be taken as the spare capacity:
Provided that in the case of EHT works the spare capacity may be determined separately for the two main
components i.e. EHT line(s) and EHT Sub-station(s) after providing for 30% redundancy in each of the said
components and in that case, the amounts paid by each original applicant under sub-regulation (3) as well as the
entitlements under the preceding sub-regulations (4), (5), (6) and (7) shall be determined separately with
reference to the actual costs of the two main components i.e. EHT line(s) and EHT sub-station(s) and the spare
capacity available in the said two components.
(9) In case of the exclusive works under sub-regulation (2) or of any of the works under sub-regulation (3), the
recovery of cost shall be made initially on the basis of estimated cost which shall be subject to additional
recoveries or refunds, as the case may be, in the same manner as outlined in sub-regulations (2) and (3) of
regulation 18 of these Regulations.
3.5 Electrification of colonies and complexes etc.- (1) In cases involving electrification of the areas developed
and/or sponsored by the development agencies, like the Jammu & Kashmir Housing Board, Private
Developers, Universities, Educational Institutions, the Industries Development Corporation and the Housing
Societies and the like, the developing agency shall bear the entire charges and/or costs for the infrastructural
development under sub-regulations (2) and (9), or sub-regulations (3) and (9), of regulation 5, whichever are
applicable, and the licensee shall take up the execution of such works only after receiving the entire amounts,
excepting those for the adjustments for the difference between estimated costs and actual costs under sub-
regulation(9) of regulation 3.4:
Provided that in case the developing agency bears the entire cost of the works under sub-regulations (3) and (9)
of Regulation 3.4, the provisions of sub-regulation (4) to (8) of Regulation 3.4 shall also be applicable.
(2) The licensee shall recover the cost-of-service lines and other works for the individual connections from the
individual applicants under regulation 3.3 and/or regulation 14:
Provided that the licensee shall make adequate provisions for distribution mains and works in the estimates for
the infrastructural works under sub-regulation (1) in a manner that the service lines required for the individual
applicants are as short as reasonably feasible.
3.6 Recovery of expenditure for additional loads:
(1) Save as provided in sub-regulation (2), where an existing consumer availing permanent connection for
electricity applies for additional connected load or contract demand, as the case may be, in excess of the
connected load or contract demand, already sanctioned in his favour, the recovery shall be made as under:
(a) in relation to the expenses/charges for the cost-of-service line under regulation 3.3 -
i. if the existing service line has sufficient spare capacity, after meeting the requirements of all the
connections released and/or committed to be released through the same service line and redundancy of
about 30% of the total capacity of such line, no additional cost shall be recovered for the service line;
ii. if sufficient spare capacity is not available, in accordance with the preceding sub-clause (i), in the service
line for meeting the additional connected load or contract demand, the cost of strengthening the existing
service line, or of providing a new service line, shall be recovered from the applicant:
Provided that the cost to be recovered under sub-clause (ii) shall not exceed the cost of providing a new service
line for the total connected load or contract demand under regulation 3.3 of these Regulations;
(b) in relation to the infrastructural development charges under regulation 3.4:
i. if the supply voltage for the total load remains unchanged as per the standard supply voltages fixed by
the Commission under the applicable Tariff Order of the Commission and the provisions of sub-
regulation (3) of regulation 3.4 are not attracted, then, subject to succeeding sub-clause (iii), such charges
shall be recovered only for the additional connected load/contract demand in accordance with sub-
regulations (2) and (9) of regulation 3.4, regulations 11 and 12 of these Regulations; and
ii. if the supply voltage gets changed, but provisions of sub-regulation (3) of regulations 3.4 are not
attracted, then the recoverable amount shall be worked out and recovered in accordance with sub-
regulations (2) and (9) of regulation 3.4 for the total revised connected load or contract demand, as the
case may be, sanctioned at the new voltage; and
iii. if the supply of additional connected load or contract demand, as the case may be, requires the execution
of works referred to in sub-regulation (3) of regulation 3.4, the recovery shall be made for the total
revised load or contract demand, as the case may be, in accordance with the provisions of the sub-
regulations (3) and (9) of regulation 3.4;
(2) In case of reduction of the connected load or contract demand, by a consumer-
i. The licensee shall maintain adequate spare capacity in the service line for a period of 365 days reckoned
from the date of such reduction, so as to meet the load if the said consumer subsequently applies for
restoration of his connected load or contract demand so reduced, during the said period of 365 days;
ii. the infrastructural development charges leviable under sub-clause (i) of clause (b) of sub-regulation (1)
shall be charged only for the additional quantum of connected load or contract demand, exceeding the
total quantum which was being availed by him prior to such reduction, if the said consumer subsequently
applies for restoration of his connected load or contract demand so reduced, during the said period of 365
days
(3) Where a consumer having a temporary connection for electricity seeks a permanent connection, the matter
shall be dealt with in accordance with respective provisions for disconnection of a temporary connection
under regulation 3.7 and for providing a new connection under relevant provisions of these Regulations.
3.7 Temporary supplies- Notwithstanding anything to the contrary contained in these Regulations, but subject to
the prior payment of an initial security deposit in the case of temporary supplies and the estimated cost of the
works required to be executed for giving such supply, the requisite works shall be executed by the licensee
subject to adjustments based on actual cost including the cost of material, labour and departmental charges:
Provided that in case an applicant/consumer for a temporary supply of power seeks revision of sanctioned
connected load/contract demand, he shall be required to pay the estimated cost of additional works and/or of
strengthening of existing works, if any, which shall also be subject to adjustments based on actual cost, and the
difference in security amount on account of such revision of connected load/demand shall also be
payable/refundable as the case may be in accordance with other Regulations:
Provided further that in case the works so executed are dismantled after discontinuance of supply, the cost of
the material removed shall, after taking into consideration its condition, be reduced from the costs recovered
from the applicant under this regulation and the balance amount, if any, after adjusting any other dues against
the applicant/consumer shall be refunded to him:
Provided further that if the works or a part thereof are not dismantled and the distribution licensee uses the
same for some other purposes, the applicant shall bear only 30% of the actual cost of such works as are not
dismantled and the accounts shall be settled accordingly:
Provided further that where the licensee refunds the amount so worked out, after making adjustment of the
outstanding amount due to him by the applicant/consumer, within a period of thirty days, no interest shall be
paid to the applicant/consumer.
Chapter-IV
4. Provision for low tension supply
4.1 In case of applications for Low Tension supply, where such supply requires only laying the service line from
the existing distributing main to the consumer's premises, the Distribution licensee shall estimate the cost-of-
service line and the cost of terminal and metering arrangements at the premises of the consumer, but not
including the cost of meter. The estimate of the cost of electric lines, electrical plants, and metering
arrangements shall be based on the latest cost data as published by the Distribution Licensee.
In respect of the above consumers, the Distribution Licensee may dispense with the process of preparation of
detailed individual estimates and instead charge on the basis of per KV/ of contracted load and per Meter rate.
Although it will not prepare individual estimates, the Distribution Licensee shall maintain the cost incurred in
respect of such categories of the consumers who are provided with electricity only through the extension of the
service line (without undertaking any of the work like DTR or laying of HT line). The average cost incurred
(according to the latest cost data as published by the Distribution Licensee) shall be used as the yardstick for
determining the per kW cost of these categories of consumers.
4.2 (i) For extending supply to the applicants for Low Tension connection, the licensee shall estimate the cost of
electrical plant such as distribution transformer (DTR) along with switch gear, etc, as follows:
Cost of the works of erection of DTR including switchgear (in Rupees) = P
Rated capacity of DTR in KVA = Q
Cost per KVA (in Rupees) = P/Q
Contracted load in KVA of the applicant = K
The amount payable by the applicant towards the electrical plant (in Rupees) = K × (P/Q)
On the requirement of the augmentation of the capacity of an existing electrical plant (such as DTR and
switchgear etc.), the differential cost of the existing and new electrical plant will form the basis of the
calculation of pro-rata charges.
The distribution licensee shall continue to estimate the amounts payable by subsequent applicants as above
till the full cost of the transformer is recovered.
In all cases, the estimate of the cost of the electrical plant shall be based on the latest cost data as published
by the Distribution licensee.
(ii) In cases of applications which besides the erection of an electrical plant (such as DTR and switchgear etc.),
need laying or extension of the HT line for providing supply to the applicant, the estimate of the cost of such
section of HT line shall be made on a per kilometer basis based on the latest cost data as published by the
Distribution Licensee.
The Distribution Licensee shall recover the cost, as mentioned in the sub-clause 4.2(i) and 4.2(ii), from all the
applicants excluding following categories:
a) Agricultural consumers with the exception of Agricultural connection to be given under special schemes
like "Tatkal Scheme" which maybe brought out in future.
b) Water Works and Sewerage Pumps operated by/for any local authority other than
c) Municipal Corporation.
d) Domestic consumers
e) Commercial consumers up to 100 KVA/125 HP of contract demand.
Chapter-V
5. Provision for high-tension / extra high-tension supply
i. In case of applications where there is a need to erect a new HT line or EHT line from the sub-station or
extend the existing HT or EHT line or strengthen of existing HT or EHT line in order to extend supply to the
applicants, the Distribution Licensee, on its own in case of HT, and in co-ordination with Transmission
Licensee in case of EHT, shall prepare an estimate of the cost of aforementioned work including the cost of
terminal and metering arrangements at the premises of the consumer, but not including the cost of meter.
Such estimate shall be based on the latest cost data as published by the Distribution Licensee and/or
Transmission Licensee.
ii. In case of applications where there is a need to erect a new sub-station for extending supply to the applicant,
the Distribution Licensee, on its own or in coordination with the Transmission Licensee, shall prepare an
estimate of the cost of the necessary works in the same way as indicated in sub-clause 4.2 (i) above. In cases
of applications when the capacity of the existing substation is required to be augmented, the differential cost
of existing and new such electrical plants will form the basis of the calculation of pro-rata charges. The
estimate of the cost of such substation shall be based on the latest cost data as published by the Distribution
Licensee and/or the Transmission Licensee.
iii. The Distribution Licensee may recover the charges for seeking new demand/ Load extension at HT level on
Rs. Per kVA/Kw basis from prospective applicants and may dispense with the preparation of detailed
individual estimates depending on technical and other constraints and parameters, if any.
Necessary details shall be submitted to the Commission, as may be required. The Commission may accept the
same after detailed scrutiny or ask the Distribution Licensee to file necessary details, as may be required or
issue suo moto directions.
iv. The methodology to be adopted by the Distribution Licensees shall require the Commission's approval.
Chapter-VI
6. Withdrawal of application before the release of connection- In case of withdrawal, or deemed withdrawal,
of an application by the applicant for the supply of power before the actual release of connection, the expenses
actually incurred for the works for providing supply under regulations 3.3, 3.4, 3.5 and 3.6 for permanent
supply and under regulation 3.7 for temporary supply, shall be adjusted as per the provisions of the Supply
Code:
Provided that for the purpose of such adjustment, actual expenditure for the works under regulations 3.3, 3.4,
3.5, and 3.6 for permanent supply and under regulation 3.7 for temporary supply shall be computed as under-
i. The actual expenditure (including departmental charges) incurred on the service lines and other works under
regulation 3.3 shall be considered in addition to the expenses determined as per the succeeding clauses of this
provision;
ii. in cases involving works under sub-regulation (3) of regulation 3.4, the actual expenditure (including
departmental charges) of such works or 10% of the infrastructural development charges at the normative rates
under sub-regulation (2) of regulation 3.4, whichever of the two is higher, shall be considered in addition to
the expenditure mentioned in the preceding clause (i) of this proviso;
iii. in cases where the works under sub-regulation (3) of regulation 3.4 are not involved, an amount equal to 10%
of the amount of infrastructural development charges worked out at the rates fixed by the Commission
pursuant to sub-regulation (2) of regulation 3.4 shall also be considered as the actual expenses in addition to
the expenditure mentioned in clause (i) of this proviso;
iv. in cases involving exclusive work(s) for facilitating the supply of power as per the fifth proviso to sub-
regulation (2) of regulation 3.4, the actual expenditure on such exclusive works shall also be considered in
addition to preceding clauses (i), (ii) and (iii) of this proviso;
V. in cases of applications for additional connected loads or contract demands under regulation 7 of these
Regulations, the computations and adjustments shall be done separately for the respective works falling under
regulation 3.3 and regulation 3.4 or regulation 3.5, based on the demand notice issued pursuant to the
provisions of regulation 3.6; and
vi. in case of temporary supplies, including for additional connected loads/contract demands for temporary
supplies, under regulation 3.7, the actual expenditure on the works required to be executed for giving such
supply or additional connected loads/contract demands shall be considered.
Chapter-VII
7. Restoration of supply after permanent disconnection- In case the supply to premises having a permanent
connection of electricity has been permanently disconnected in accordance with the provisions of the Supply
Code and the original consumer or some other person applies for a connection at such premises, the
distribution licensee shall provide supply within the time allowed for a new connection after recovery of
expenses applicable for new connections under these Regulations:
Provided that if the service line to such premises has not been removed or used for the release of other
connections and is in good condition and also has sufficient spare capacity, after meeting the requirements of
all the connections released or committed to be released through the same service line and redundancy of about
30% of the total capacity of such line, to cater to the connected load or contract demand applied for by such
applicant, the cost of service line under regulation 3.3 shall not be recovered and the connection shall be
released at the earliest subject to other conditions applicable for release of new connections:
Provided further that in case of such applicants, the amounts worked out under regulation 3.5 and other
Regulations of the Commission shall be recoverable in the same manner as applicable for new connections:
Provided further that if -
i. The application for such a new connection is for a similar connected load or contract demand and supply
voltage, as had been sanctioned for the original connection;
ii. The application from the new applicant is received simultaneously or within 60 days from the date on which
the original connection was permanently disconnected;
iii. The provisions of sub-regulation (3) of regulation 3.4 are not attracted; and
iv. The applicant clears all outstanding dues, if any, against such previous connection which has been
permanently disconnected;
The amount of infrastructural development charges and other costs payable by the applicant for the connected
load or contract demand applied for, as per the provisions of regulation 3.4 shall be reduced by 90% of the
amount of the infrastructural development charges worked out at the normative rates under sub-regulation (2)
of regulation 3.4 for the connected load/ contract demand originally sanctioned or for the same applied for by
the new applicant, whichever of the two is lower:
Provided further that if-
i. The application from the new applicant is received after a period of 60 days from the date on which the
original connection is permanently disconnected; and
ii. All other conditions, other than condition (ii) as per the third proviso to this regulation are fulfilled:
iii. The percentage rate of such rebate as per the third proviso to this regulation shall be reduced by 5% for every
period of 30 days or part thereof after the expiry of the initial period of 60 days:
Explanation.- If the application for the new connection is received by the licensee on or after the 61st day but
up to and inclusive of the 90th day from the date of permanent disconnection, the rebate under the fourth
proviso to this regulation shall be allowed @ 85% of infrastructural development charges worked out at the
normative rate as per sub-regulation (2) of regulation 5 for the connected load/contract demand originally
sanctioned or for the same applied for by the new applicant, whichever of the two is lower, and so on for every
subsequent block of 30 days till such time the rate of rebate becomes zero:
Provided further that the rebate admissible as per the third and fourth provisos to this regulation shall be
applicable only on the amount of infrastructural development charges worked out at normative rates under sub-
regulation (2) of regulation 3.4 and not on any other charges/costs as may be recoverable in accordance with
the second proviso to this regulation.
Chapter-VIII
8. Maintenance of works. -
(1) Notwithstanding anything contained in any other law for the time being in force, all the works erected for
providing supply in pursuance of requisition by the applicant, or any portion thereof, which may have been
paid for by the applicant making requisition, shall be maintained by the licensee and the licensee shall also
have the right to supply electricity to any other prospective applicants or the consumers, through the said
works and the said works shall become the property of the licensee.
(2) The interface points of commencement of supply, as determined under the provisions of the Supply Code and
the relevant agreements, shall constitute the liability between the licensee and the consumer/ applicant.
Chapter-IX
9. Supervision charges- The expenses recoverable by the licensee under these regulations shall also include the
licensee's supervision charges at the rate as mentioned under the Supply Code.
Explanation- For the purposes of these regulations, the expression “Supervision charges” shall include
establishment charges, tools and plant charges, audit and accounts charges, maintenance during construction,
loss on stock, design charges, manpower expenses, and head office pro rata expenses.
Chapter-X
10. Standard cost data-
(1) The distribution licensee shall, after inviting public objections, submit, on an annual basis, to the Commission
for its scrutiny, by 30th September of each year, a cost data book (including departmental charges) duly
approved by its Board of Directors/competent authority, which it proposes to adopt for the subsequent
financial year, and publish the standard cost data book by 15th November of each year, after attending to the
observation or directions, if any, of the Commission, and the same shall form the basis for approving the
average or normative rates as per these regulations and also for making the initial estimates for erection of
electric lines and/or electrical plants and/or any other works to be executed in order to provide supply to the
applicants in cases where the cost is to be recovered on actual basis:
(2) The distribution licensee shall upload the standard cost data, published under sub-regulation (1), on its
website and also make available copies of the same to any interested person on demand at a reasonable
charge.
Chapter-XI
11. Schedule of service connection charges-
(1) The distribution licensee shall file a schedule of service connections charges along with their Tariff Petition
every year before the Commission for approval, which is to be levied for the matters contained in these
regulations and such other related miscellaneous activities, not covered elsewhere, as are required to be
undertaken by the distribution licensee to fulfill its obligations to supply electricity to the consumers under
the Act:
Provided that the distribution licensee shall also file the schedule of service connection charges along with
every application for determination of tariff under section 64 of the Act together with such particulars as the
Commission may require:
Provided further that while preparing the schedule of service connection charges, the standard cost data as per
the sub regulation (2) of Regulation 10, shall be taken into account.
(2) The Commission shall, after examining the schedule of service connection charges filed before it by a
distribution licensee under sub-regulation (1), may-
i. Approve the schedule of charges with such modifications or such conditions as may be prescribed in that
order; or
ii. reject the schedule of service connection charges filed before it for reasons to be recorded in writing if it
is not in accordance with the provisions of the Act and/or these Regulations:
Provided further that the schedule of service connection charges approved by the Commission shall, unless
otherwise amended or revoked, continue to be in force for such period as may be prescribed in the order of the
Commission granting such approval and also for such extended period as may be approved by the Commission.
(3) Any deviation from the approved schedule of service connection charges shall be only with the prior approval
of the Commission.
12. Provisional schedule of the service connection charges-
(1) Notwithstanding anything to the contrary contained in these Regulations, the Commission may notify
provisional schedule of service connection charges to be levied for any of the activity/activities required to
be undertaken by the distribution licensee to fulfill its obligations to supply electricity under the Act and the
Regulations framed thereunder.
Provided that the provisional schedule of service connection charges notified under sub-regulation (1) shall be
for a period of one hundred and eighty days and shall, unless extended by the Commission, cease to be valid
and effective on the expiry of the period of one hundred and eighty days or the date on which the order
approving the schedule of service connection charges is issued under regulation 11, whichever is earlier.
(2) The amount charged under the provisional schedule of service connection charges notified under sub-
regulation (1) shall be adjusted against the amount chargeable under the schedule of service connection
charges approved by the Commission under regulation 11.
Chapter-XII
13. Accounting of the amounts recovered- The amounts recovered by the distribution licensee under various
provisions of these Regulations on various accounts for supply at different voltage levels shall be accounted for
separately as capital receipts under separate accounting heads and sub-heads for permanent and temporary
connections and also each type of charges as well as for each category of voltage level and shall, subject to the
provisions of sub-regulations (5), (6), (7) and (8) of regulation 3.4, be used exclusively for meeting a part of the
capital expenditure under the capital expenditure plan:
Provided that such capital receipts shall, as far as possible, be utilized in an equitable proportion of the
estimated cost of various works of the respective categories and respective voltage levels:
Provided further that the capital receipts in respect of the works required exclusively for an applicant or group
of applicants shall be used for such exclusive works only.
Chapter-XIII
14. Execution of works- The service lines and other works required for supplying power to the applicant(s) shall
normally be executed by the distribution licensee:
Provided that the applicant or the consumer, as the case may be, may, with the prior approval of the distribution
licensee which shall ordinarily not be refused, execute the service line through an electrical contractor licensed
by the Electrical Inspector, and in such cases, the following provisions shall apply-
i. all the requisite clearances under various laws shall be obtained by the applicant;
ii. the applicant shall be liable to pay the Supervision charges for the specific works;
iii. such option shall be available to the applicant only for the service line to be executed exclusively for the
applicant; and
iv. works other than service line shall be executed by the distribution licensee unless mutually agreed
otherwise by the distribution licensee with the applicant, on mutually agreed terms and conditions.
Note: The provisions under the first proviso to this regulation shall also apply for execution of service lines to
be executed exclusively for a group of applicants or consumers, as the case may be, if all the members of such
group enter into an agreement amongst themselves and nominate their representative who shall then deal with
the distribution licensee for such matters.
15. Differential costs-
(1) The distribution licensee shall recover the expenses and/or charges for giving electricity connections to the
applicants as per the provisions of these Regulations and any other additional expenses, that are not
recoverable from the applicants under any Regulations or Law and shall be met out of the approved financial
provisions of the capital expenditure plan.
(2) In cases where the cost of certain works is to be recovered from the applicant or group of applicants initially
on the basis of estimate and such recovery is subject to adjustment as per actual the provisions of these
regulations, the following provisions shall apply-
i. The estimate shall be prepared on the basis of the standard cost data as per sub-regulation (2) of Regulation
10; and
ii. the licensee shall, within ninety days of commissioning of the works, render to the applicant/consumer, the
account of expenditure showing the excess or deficit in relation to the initial estimated amount giving
details of item-wise estimation and actual expenditure along with the item wise figures of variance to the
extent possible and if applicant requires any additional information, the distribution licensee shall furnish
the same within ten days of receipt of such requisition.
(3) The distribution licensee shall recover or refund, as the case may be, the difference between the actual
expenditure and the estimated cost within 60 days from the submission of the account and the unrefunded or
unrecovered amounts, as the case may be, shall attract simple interest @ 12% per annum for the period
beyond the said limit of 60 days.
16. Way-leaves, consents, and acquisitions-
(1) Subject to the provisions of the rules framed by the Union Territory Government under sub-section (2) of
section 67 and clause (b) of sub-section (2) of section 180, of the Act, the licensee shall try to obtain any way
leaves, consents and acquisitions required for placing of any wires, poles, wall brackets, stays apparatus and
appliances for the carrying electricity, or for the transmission of telegraphic or telephonic communications
necessary for proper coordination of the works of the licensee while giving connection to the applicant:
Provided that in cases where the cost of works is to be recovered from the applicant on an actual basis, the cost
of obtaining the permissions shall also be recovered on an actual basis, and in cases where the recovery is to be
made at normative rates, the cost of obtaining such permissions shall be borne by the licensee:
Provided further that where wires are to pass over other person's land, premises, or building, the wires shall be
routed along the boundary lines of the said land, set back of the building, streets, and roads, whichever is
feasible.
(2)The applicant/consumer shall provide the required space within his premises for the transformer and
associated equipment including metering arrangements, if so required by the licensee at any stage.
17. Manner of payments- The applicant shall, before the commencement of work of laying service line under
regulation 4 and any other works for which the entire cost of the works is required to be paid by him as per the
provisions of these regulations, deposit on notice of demand, the entire amount, not limited to the cost of such
works only, payable under these Regulations and all other relevant Regulations.
18. Demand notice- Demand notice valid for 90 days shall be sent by the registered AD post to the applicant
within the time frame mentioned under Supply Code:
Provided that the demand notices to be issued on or after the date of commencement of these regulations shall
suitably incorporate the terms and conditions of these regulations, apart from other conditions as per other
Regulations and Codes of the Commission:
Provided further that if any of the terms and conditions of these regulations remain unaccounted for in any of
the demand notices issued on or within 90 days from the date on which these regulations come into force, the
licensee may revise the same, so as to incorporate the terms and conditions as per these Regulations and the
Act:
Provided further that the demand notices issued prior to commencement of these Regulations and/or the
demands still to be raised against the loads/demands released prior to commencement of these Regulations
shall continue to be governed by other relevant Regulations and Codes of the Commission, but not including
these Regulations, unless the Commission issues any specific order in this regard:
Provided further that in case of non-compliance of the demand notice within the period mentioned in such
notice or within such period as may be mutually agreed between the licensee and the applicant, the application,
against which the demand notice had been issued, shall be treated as withdrawn and the matter shall be further
dealt with in accordance with relevant governing Regulations and Codes of the Commission.
19. Power to remove difficulties- If any difficulty arises in giving effect to any of the provisions of these
regulations, the Commission may, suo motu or on an application, by general or special order, take suitable
action or direct the distribution licensee to take such suitable action not being inconsistent with the Act which,
in the opinion of the Commission, is necessary or expedient for removing such difficulties.
20. Issue of orders and practice directions- Subject to the provisions of the Act and these Regulations, the
Commission may, from time to time, issue orders and practice directions in regard to the implementation of
these regulations and the procedures to be followed on various matters for which the Commission has been
empowered by these Regulations or the Act to lay down and also for the matter's incidental or ancillary
thereto.
21. Inherent power of the Commission-
(1) Nothing in these Regulations shall be deemed to limit or otherwise affect the inherent powers of the
Commission to make such orders as may be necessary for meeting the ends of justice or to prevent the abuse
of the process of the Commission.
(2) Nothing in these Regulations shall bar the Commission from adopting a procedure, which is at variance with
any of the provisions of these regulations, if the Commission, in view of the special circumstances of a matter
or class of matters and for reasons to be recorded, in writing, deems it necessary or expedient.
(3) Nothing in these Regulations shall, expressly or impliedly, debar the Commission to deal with any matter or
exercise any power under the Act for which no regulations have been framed and the Commission may deal
with such matters, powers, and functions in a manner it thinks fit.
By Order of the Commission.
V. K. DHAR, (JKAS) Sec.
[ADVT.-III/4/Exty./781/2023-24]
Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064
and Published by the Controller of Publications, Delhi-110054.
Login to read full text