Full Text
REGD. No. D. L.-33004/99
The Gazette of India
CG-DL-E-23052025-263337
EXTRAORDINARY
PART II-Section 3-Sub-section (ii)
PUBLISHED BY AUTHORITY
No. 2254]
NEW DELHI, FRIDAY, MAY 23, 2025/JYAISTHA 2, 1947
MINISTRY OF PETROLEUM AND NATURAL GAS
NOTIFICATION
New Delhi, the 20th May, 2025
S.O. 2308(E). - Whereas by notification of Government of India in the Ministry of Petroleum and Natural
Gas, number S.O. 1086(E) dated 28-02-2025, issued under sub-section (1) of Section 3 of the Petroleum and Minerals
Pipelines (Acquisition of Right of User in Land) Act, 1962 (50 of 1962) (hereinafter referred to as the said Act), the
Government of India had declared its intention to acquire the Right of User in land, specified in the Schedule appended
to that notification for transportation of Gaseous Ethylene from Hazira Manufacturing Division (HMD) to Dahej
Manufacturing Division (DMD) of M/s. Reliance Industries Limited (RIL) in Gujarat, an extension pipeline (HDPL
Extn.2) to the existing Hazira – Dahej Natural Gas Pipeline (HDPL) should be laid by M/s. Reliance Industries Limited;
And whereas, the copies of the said Gazette notification were made available to the public from
12-03-2025 to 17-03-2025;
And whereas, the objections received from the public to the laying of the said pipeline have been considered
and disallowed by the Competent Authority;
And whereas, the Competent Authority has under sub-section (1) of Section 6 of the said Act, submitted report
to the Government of India;
And whereas, the Government of India, after considering the said report and on being satisfied that the said
land is required for laying the said pipeline, has decided to acquire the Right of User therein, free from all encumbrances;
Now, therefore, in exercise of the powers conferred by sub-section (1) of Section 6 of the said Act, the
Government of India hereby declares that the Right of User in the land, specified in the Schedule, appended to this
notification, is hereby acquired for laying the said pipeline;
And further, in exercise of the powers conferred by sub-section (4) of Section 6 of the said Act, the Government
of India hereby directs that the Right of User in the said land for laying the pipeline shall, instead of vesting in the
Government of India, vest on the date of publication of the declaration, in M/s. Reliance Industries Limited, free from
all encumbrances.
SCHEDULE
Taluka: ADAJAN District: SURAT State:GUJARAT
Name of Village Survey No./Sub-Division No. Area to be acquired for ROU
+--------------------+--------------------------+----------+-------+-------+
| | | Нec | Are | Sq.m. |
+--------------------+--------------------------+----------+-------+-------+
| 1 | 2 | 3 | 4 | 5 |
+====================+==========================+==========+=======+=======+
| 1) Ichchhapor | 766 | 00 | 17 | 77 |
| | 765 | 00 | 15 | 43 |
| | 736/1 | 00 | 12 | 74 |
| | 735/Paiky1 | 00 | 00 | 98 |
| | 734 | 00 | 10 | 69 |
| | 733/A | 00 | 12 | 54 |
| | 732 | 00 | 01 | 85 |
| | 716/Paikyl | 00 | 07 | 46 |
| | 716/Paiky1+2 | 00 | 07 | 39 |
| | 716/Paiky 3-1 | 00 | 17 | 45 |
| | 698/Paiky1 | 00 | 03 | 60 |
| | 698/Paiky 2-1 | 00 | 07 | 95 |
+--------------------+--------------------------+----------+-------+-------+
| Taluka: CHORYASI | District: SURAT | State: GUJARAT |
+--------------------+--------------------------+--------------------------+
| 1) Damka | 443-1 | 00 | 03 | 09 |
| | 441-2 | 00 | 15 | 33 |
+--------------------+--------------------------+----------+-------+-------+
[ F. No. L-14014-21-2024-GP-II(E-51557)]
RAMJI LAL MEENA, Under Secy.