Full Text
REGD. No. D. L.-33004/99
The Gazette of India
CG-DL-E-18052024-254247
EXTRAORDINARY
PART III—Section 4
PUBLISHED BY AUTHORITY
No. 363]
NEW DELHI, FRIDAY, MAY 17, 2024/VAISAKHA 27, 1946
CENTRAL ELECTRICITY REGULATORY COMMISSION
NOTIFICATION
New Delhi, the 2nd April, 2024
No. Eco T1/2024-CERC.— In pursuance of the "Tariff based Competitive-bidding Guidelines for
Transmission Service", amended up to 10th October, 2008, issued by the Ministry of Power and Schedule-7 of the
Standard Transmission Service Agreement documents, the Central Electricity Regulatory Commission (CERC) hereby
notifies the following rate for the purpose of payment for the period from 01.04.2024 to 30.09.2024.
Annual Escalation Rate applicable for the purpose of payment as per the Transmission Service Agreement:
+--------+-------------------------------------------------------------+-----------------------------+
| Sl. No. | Description | Annual Escalation Rate for |
| | | Payment |
+========+=============================================================+=============================+
| 1. | Annual inflation rate for escalable transmission charges for | 4.96% |
| | the purpose of payment | |
+--------+-------------------------------------------------------------+-----------------------------+
2. In accordance with Schedule-9 of the Standard Transmission Service Agreement under the "Revised
Guidelines and Standard Bidding Documents (SBDs) for procurement of Inter-State Transmission Services (ISTS)
through Tariff Based Competitive Bidding (TBGB) process" dated 6th August 2021 issued by the Ministry of Power,
the CERC hereby notifies the following discount rate for the period from 01.04.2024 to 30.09.2024.
Discount rate for determining the Relief under Force Majeure Event & Change in Law during Construction
Period as per the Transmission Service Agreement:
+--------+-------------------------------------------------------------------------------------------------+--------+
| Sl. No. | Description | Rate |
+========+=================================================================================================+========+
| 1. | Discount rate for determining the Relief under Force Majeure Event & Change in Law during | 9.25% |
| | Construction Period | |
+--------+-------------------------------------------------------------------------------------------------+--------+
HARPREET SINGH PRUTHI, Secy.
[ADVT.-III/4/Exty./130/2024-25]
5Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064
and Published by the Controller of Publications, Delhi-110054.
Login to read full text