The Gazette of India
CG-DL-E-10012025-260111
EXTRAORDINARY
PART II-Section 3-Sub-section (ii)
PUBLISHED BY AUTHORITY
No. 152]
NEW DELHI, THURSDAY, JANUARY 9, 2025/PAUSHA 19, 1946
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
NOTIFICATION
New Delhi, the 8th January, 2025
S.O. 154(E).- Whereas by notification of the Government of India in the Ministry of Road Transport and
Highways number S.O. 910 (E), Dated 21st April 2010, issued under Section 11 of the National Highway Authority of
India Act 1988 (68 to 1988), the Central Government has entrusted the stretch from km 103.00 to km 610.000 of
Agra -Indore section, km 0.00 at Agra and from km 0.00 to km 12.600 of Indore-Mumbai section, of National
Highway No 52 (old NH3) in the state of Madhya Pradesh to the National Highways Authority of India (hereinafter
referred to as the "Authority");
Now, therefore, in exercise of the powers conferred by section 7 of the National Highways Act, 1956 (48 of
1956), read with rule 3 of the National Highways Fee (Determination of Rates and Collection) Rules, 2008
(hereinafter referred to as the "rules") and in suppression to notification S.O. 1354 (E), Dated 10th June, 2011, the
Central Government hereby levies the fee at the rate specified in column (2) of the Table 1 for net road section length
of 13.144 km [Table-2] and for equivalent structure length (having length more than 60m) of 9.66 km (having length
of 0.966 km [Table-4]) and at one and one half times the base rate for bypasses having length of 30.940 km [Table-3]
costing rupees ten crore or more, on the type of vehicles specified in column (1) of the Table 1 below for the use of
four and more lane of Indore to Dewas section from design km 577.550 to km 610.00 & km 00.000 to km 12.600 of
National Highway number 52 (Old NH-3) in the State of Madhya Pradesh and authorises the Authority to collect,
either through its officials or through a contractor, the said fee, namely:-
Table-1
+-----------------------------------------------------+---------------------------------------------+
| Type of vehicle | Base rate of fee per km for the base |
| | year 2007-08 (in Rupees) |
+=====================================================+=============================================+
| (1) | (2) |
+=====================================================+=============================================+
| Car, Jeep, Van or Light Motor Vehicle | 0.65 |
+-----------------------------------------------------+---------------------------------------------+
| Light Commercial Vehicle, Light Goods Vehicle or Mini Bus | 1.05 |
+-----------------------------------------------------+---------------------------------------------+
| Bus or Truck (Two Axles) | 2.20 |
+-----------------------------------------------------+---------------------------------------------+
| Three-axle commercial vehicles | 2.40 |
+-----------------------------------------------------+---------------------------------------------+
| Heavy Construction Machinery (HCM) or Earth Moving Equipment (EME) or | 3.45 |
| Multi Axle Vehicle (MAV) (four to six axles) | |
+-----------------------------------------------------+---------------------------------------------+
| Oversized Vehicles (seven or more axles) | 4.20 |
+-----------------------------------------------------+---------------------------------------------+
1. The fee to be levied and collected hereunder shall be due and payable at the Fee Plaza for net road length
specified for such Fee Plaza,namely: -
Table-2
+-----------------------------------------------------+---------------------------------------------+------------------------------+
| Location of Fee Plaza (chainage) | Length (in km) for which Fee is | Rate at which fee is payable |
| | payable | |
+=====================================================+=============================================+==============================+
| At Design Km 591.775( Existing km | 13.144 | 100% for four or more lane of|
| 591.775) of NH-52 (old NH 3) near | [Excluding length of Bypass | the base rates mentioned in |
| Mangaliya village in Indore district of | (costing >10 Cr.) and length of | Table-1 above |
| Madhya Pradesh. | structures (>60m)] | |
+-----------------------------------------------------+---------------------------------------------+------------------------------+
| At Design Km 0.550( Existing km | 13.144 | 100% for four or more lane of|
| 0.550) of NH-52 (old NH 3) near | [Excluding length of Bypass | the base rates mentioned in |
| Mangaliya village in Indore district of | (costing >10 Cr.) and length of | the base rates mentioned in |
| Madhya Pradesh. | structures (>60m)] | Table-1 above |
+-----------------------------------------------------+---------------------------------------------+------------------------------+
2. In addition to above, the following fee shall also be due and payable for the use of the bypass costing Rs 10
crore or more at the following Fee Plaza for net bypass length specified for such Fee Plaza: -
Table-3
+-----------------------------------------------------+--------------------+------------+----------+-----------------------------------------------------+----------------+
| Location of Fee Plaza | Name of the | Taking Off | Merging | Length and Cost of | Rate at which fee|
| (chainage) | Bypass | | at | bypass for which | is payable |
| | | | | additional fee is payable | |
| | | | | (excluding structure > 60 | |
| | | | | m) | |
| | | | | +------------------+----------------+ | |
| | | | | | Length | Cost | | |
| | | | | | (in Km.) | (in Rs. | | |
| | | | | | | Crore) | | |
+=====================================================+====================+============+==========+==================+================+================+
| At Design Km 591.775( Existing km | Indore | Design | Design | 18.60 | 730.24 | 150% for four or|
| 591.775) of NH-52 (old NH | Dewas | km 591+00 | km | | | more lane of the|
| 3) near Mangaliya village | Bypass of | | 610.00 | | | base rates |
| in Indore district of Madhya | NH-52 (old | | | | | mentioned in |
| Pradesh. | NH 3) | | | | | Table-1 above |
| | | Design km | Design | 12.34 | | |
| | | 00.000 | km | | | |
| | | | 12.600 | | | |
+-----------------------------------------------------+--------------------+------------+----------+------------------+----------------+----------------+
| Total | | | | 30.94 | | |
+-----------------------------------------------------+--------------------+------------+----------+------------------+----------------+----------------+
3. In addition to above, the following fee shall also be due and payable for the use of the following structures
having length more than 60m at the following Fee Plaza(s), by converting the length of structures into an equivalent
length of highway by multiplying the length of such structures by an equalisation factor of 10: -
Table-4
+-----------------------------------------------------+---------------------------------------------+-----------------------------+------------------------------+
| Location of Fee Plaza | Length of structures^ (in | Equivalent road | Rate at which fee is payable |
| (chainage) | km) to be converted into | length (in km) | |
| | equivalent road length | | |
+=====================================================+=============================================+=============================+==============================+
| At Design Km 591.775( Existing km | 0.966^ | 9.66 | 100% for four and more lane |
| 591.775) of NH-52 (old NH | | | of the base rates mentioned in|
| 3) near Mangaliya village | | | Table-1 above |
| in Indore district of Madhya | | | |
| Pradesh. | | | |
+-----------------------------------------------------+---------------------------------------------+-----------------------------+------------------------------+
| At Design Km 0.550( Existing km | 0.306^^ | 3.06 | 100% for four and more lane |
| 0.550) of NH-52 (old NH 3) near | | | of the base rates mentioned in|
| Mangaliya village in Indore | | | Table-1 above |
| district of Madhya Pradesh. | | | |
+-----------------------------------------------------+---------------------------------------------+-----------------------------+------------------------------+
^The detail is as under:
+-------+---------------+------------+----------+---------------+
| S.No. | Structure | Chainage (Km) | Length in Km |
| | | From | To | |
+=======+===============+============+==========+===============+
| 1 | Major Bridge | 581.420 | 581.644 | 0.224 |
+-------+---------------+------------+----------+---------------+
| 2 | Flyover | 590.895 | 590.977 | 0.082 |
+-------+---------------+------------+----------+---------------+
| 3 | Flyover | 600.055 | 600.175 | 0.120 |
+-------+---------------+------------+----------+---------------+
| 4 | Flyover | 600.535 | 600.715 | 0.180 |
+-------+---------------+------------+----------+---------------+
| 5 | Flyover | 607.890 | 607.990 | 0.100 |
+-------+---------------+------------+----------+---------------+
| 6 | Flyover | 3.770 | 3.870 | 0.100 |
+-------+---------------+------------+----------+---------------+
| 7 | Flyover | 12.326 | 12.486 | 0.160 |
+-------+---------------+------------+----------+---------------+
| Total | | | | 0.966 |
+-------+---------------+------------+----------+---------------+
^^The detail is as under:
+-------+---------------+------------+----------+---------------+
| S.No. | Structure | Chainage (Km) | Length in Km |
| | | From | To | |
+=======+===============+============+==========+===============+
| 1 | Major Bridge | 581.420 | 581.644 | 0.224 |
+-------+---------------+------------+----------+---------------+
| 2 | Flyover | 590.895 | 590.977 | 0.082 |
+-------+---------------+------------+----------+---------------+
| Total | | | | 0.306 |
+-------+---------------+------------+----------+---------------+
4. The rate of monthly pass for a person who owns a mechanical vehicle registered for non-commercial purposes
and resides within a distance of twenty kilometers from the fee plaza is Rs. 340.000 (Rupees Three Hundred and Forty
Only) for the year 2024-25 and is subject to revision every year as per the provisions of the said rules.
5. For multiple journeys on the highway section, passes shall be issued at the following rates, namely: -
Table-5
+-----------------------------------------------------+---------------------------------------------+--------------------------------------+
| Amount Payable | Maximum number of | Period of validity |
| | one way journeys | |
| | allowed | |
+=====================================================+=============================================+======================================+
| One and one-half times of the fee for one | Two | Twenty-four hours from the time of payment|
| way journey | | |
+-----------------------------------------------------+---------------------------------------------+--------------------------------------+
| Two-third of amount of the fee payable | Fifty | One month from date of payment |
| for fifty single journeys | | |
+-----------------------------------------------------+---------------------------------------------+--------------------------------------+
6. Fee for commercial vehicle (excluding vehicles plying under National permit) registered in the district where
the fee plaza falls shall be 50% of the specified rate for that category of vehicle provided no service road or alternative
road is available for use of such commercial vehicles.
7. The driver or owner or a person in charge of a mechanical vehicle which is loaded in excess of permissible
load specified for its category, shall be liable to pay fee for entering the overloaded vehicle on the National Highway
to the fee collecting agency, equal to the fee specified in sub-rule 1A of rule 10 of the said rules, and shall not be
entitled to make use of the highway section unless the excess load has been removed from such mechanical vehicle.
8. All definitions including category of mechanical vehicles, its permissible load, category of exempted vehicles,
service road, alternative road, etc. shall be as per definitions specified in the said rules.
9. The fee rates shall be displayed for information of the users in accordance with rule 12 of the said rules.
10. Based on the base rate of fee per kilometer for the base year 2007-08 as mentioned in Table-1 above, the actual
amount of fee to be charged from the mechanical vehicles and the discounts will be calculated by the Authority on the
basis of the completed length of the section and revised annually in accordance with the rule 5 of the said rules and the
same shall be published in at least one newspaper in English and vernacular language.
11. The estimated capital cost of the project is Rupees 1066.10 Crore. The capital cost is subject to variation as the
activities of land acquisition, utility shifting, tree cutting, etc. are yet to be completed. The Authority shall maintain a
record of the recovery of capital cost through user fee realised.
[F. No. NHAI/13013/547/CO/21-22/CB/IDTLAandBFeePlazas-Part(1)/E-242372]
KAMLESH CHATURVEDI, Jt. Secy.