Full Text
REGD. No. D. L.-33004/99
The Gazette of India
CG-DL-E-09012025-260087
EXTRAORDINARY
PART II-Section 3-Sub-section (ii)
PUBLISHED BY AUTHORITY
No. 13]
NEW DELHI, THURSDAY, JANUARY 2, 2025/ PAUSHA 12, 1946
MINISTRY OF PETROLEUM AND NATURAL GAS
NOTIFICATION
New Delhi, the 23rd December, 2024
S.O. 13(E). Whereas by notification of the Government of India in the Ministry of Petroleum and
Natural Gas S.O. No. 2673(E) dated 08.07.2024, issued under sub-section (1) of section 3 of the Petroleum
and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962 (50 of 1962), (hereinafter referred
to as the said Act), published in the Extra Ordinary Gazette of India dated the 09.07.2024, the Government
of India declared its intention to acquire the Right of User in the land specified in the Schedule appended to
that notification for the purpose of laying pipeline for transportation of Natural Gas through Panisagar-
Agartala Gas Pipeline in the state of Tripura by Indradhanush Gas Grid Limited (IGGL).
And whereas copies of the said Extraordinary Gazette notification were made available to the
public.
And whereas the objections received from the public to the laying of the pipeline have been
considered and disposed by the Competent Authority.
And whereas the Competent Authority has, under sub-section (1) of section 6 of the said Act
submitted its report to the Government of India.
And whereas the Government of India after considering the said report and on being satisfied that
the said land is required for laying the pipeline, has decided to acquire right of user therein;
Now, therefore, in exercise of the powers conferred by sub-section (1) of the section 6 of the said
Act, the Government of India hereby declares that the right of user in the land specified in the Schedule
appended to this notification is hereby acquired for laying the pipeline;
And further, in exercise of the powers conferred by sub-section (4) of section 6 of the said Act, the
Government of India hereby directs that the Right of User in the land for laying the pipeline shall, instead
of vesting in Government of India, vest, on this date of the publication of the declaration, in the
Indradhanush Gas Grid Limited (IGGL), free from all encumbrances.
SCHEDULE
+------------+----------+--------------------------+----------+----------+-----+-------+
| District: Dhalai | State: Tripura |
+------------+----------+--------------------------+----------+----------+-----+-------+
| | Area |
| Circle | Tehsil | Name of Village | Dag No. | Hectare | Are | Square|
| | | | | | | Metre |
+============+==========+==========================+==========+==========+=====+=======+
| (1) | (2) | (3) | (4) | (5) | (6) | (7) |
+------------+----------+--------------------------+----------+----------+-----+-------+
| Manu | Manu | Dakshin Dhumachhar-04 | 2163 | 00 | 19 | 89 |
+------------+----------+--------------------------+----------+----------+-----+-------+
| Ambassa | Dalubari | Kamalachhara-20 | 6 | 00 | 06 | 92 |
| | | | 4/1070 | 00 | 03 | 18 |
| | | | 4 | 00 | 06 | 02 |
+------------+----------+--------------------------+----------+----------+-----+-------+
| Ambassa | Ambassa | Lalchari-16 | 1578 | 00 | 56 | 65 |
+------------+----------+--------------------------+----------+----------+-----+-------+
[F.No. L-14014-150-2021-GP-II (E-40247)]
RAMJI LAL MEENA, Under Secy.
NOTIFICATION
New Delhi, the 23rd December, 2024
S.O. 14(E). Whereas by notification of the Government of India in the Ministry of Petroleum and Natural
Gas S.O. No. 2365(E) dated 14.06.2024, issued under sub-section (1) of section 3 of the Petroleum and Minerals
Pipelines (Acquisition of Right of User in Land) Act, 1962 (50 of 1962), (hereinafter referred to as the said Act),
published in the Ordinary Gazette of India dated the 19.06.2024, the Government of India declared its intention to
acquire the Right of User in the land specified in the Schedule appended to that notification for the purpose of laying
pipeline for transportation of Natural Gas through Panisagar-Agartala Gas Pipeline in the state of Tripura by
Indradhanush Gas Grid Limited (IGGL).
And whereas copies of the said Extraordinary Gazette notification were made available to the public.
And whereas the objections received from the public to the laying of the pipeline have been considered and
disposed by the Competent Authority.
And whereas the Competent Authority has, under sub-section (1) of section 6 of the said Act submitted its
report to the Government of India.
And whereas the Government of India after considering the said report and on being satisfied that the said
land is required for laying the pipeline, has decided to acquire right of user therein;
Now, therefore, in exercise of the powers conferred by sub-section (1) of the section 6 of the said Act, the
Government of India hereby declares that the right of user in the land specified in the Schedule appended to this
notification is hereby acquired for laying the pipeline;
And further, in exercise of the powers conferred by sub-section (4) of section 6 of the said Act, the
Government of India hereby directs that the Right of User in the land for laying the pipeline shall, instead of vesting in
Government of India, vest, on this date of the publication of the declaration, in the Indradhanush Gas Grid Limited
(IGGL), free from all encumbrances.
SCHEDULE
+------------+----------+--------------------------+----------+----------+-----+-------+
| District: Dhalai | State: Tripura |
+------------+----------+--------------------------+----------+----------+-----+-----+
| | Area |
| Circle | Mouza | Name of Village | Dag No. | Hectare | Are |Square|
| | | | | | |Metre |
+============+==========+==========================+==========+==========+=====+======+
| (1) | (2) | (3) | (4) | (5) | (6) | (7) |
+------------+----------+--------------------------+----------+----------+-----+------+
| Manu | Manu | Uttar Dhumachhara - 05 | 581 | 00 | 02 | 03 |
| | | | 1623 | 00 | 04 | 40 |
| | | | 895 | 00 | 05 | 86 |
+------------+----------+--------------------------+----------+----------+-----+------+
[F. No. L-14014-150-2021-GP-II (E-40247)]
RAMJI LAL MEENA, Under Secy.
NOTIFICATION
New Delhi, the 23rd December, 2024
S.O. 15(E). Whereas by notification of the Government of India in the Ministry of Petroleum and Natural
Gas S. O. No. 2366(E) dated 14.06.2024 issued under sub-section (1) of section 3 of the Petroleum and Minerals
Pipelines (Acquisition of Right of User in Land) Act, 1962 (50 of 1962), (hereinafter referred to as the said Act),
published in the Ordinary Gazette of India dated the 19.06.2024, the Government of India declared its intention to
acquire the Right of User in the land specified in the Schedule appended to that notification for the purpose of laying
pipeline for transportation of Natural Gas through Panisagar-Agartala Gas Pipeline in the state of Tripura by
Indradhanush Gas Grid Limited (IGGL).
And whereas copies of the said Extraordinary Gazette notification were made available to the public.
And whereas the objections received from the public to the laying of the pipeline have been considered and
disposed by the Competent Authority.
And whereas the Competent Authority has, under sub-section (1) of section 6 of the said Act submitted its
report to the Government of India.
And whereas the Government of India after considering the said report and on being satisfied that the said
land is required for laying the pipeline, has decided to acquire right of user therein;
Now, therefore, in exercise of the powers conferred by sub-section (1) of the section 6 of the said Act, the
Government of India hereby declares that the right of user in the land specified in the Schedule appended to this
notification is hereby acquired for laying the pipeline;
And further, in exercise of the powers conferred by sub-section (4) of section 6 of the said Act, the
Government of India hereby directs that the Right of User in the land for laying the pipeline shall, instead of vesting in
Government of India, vest, on this date of the publication of the declaration, in the Indradhanush Gas Grid Limited
(IGGL), free from all encumbrances.
SCHEDULE
+------------+-----------+--------------------------+----------+----------+-----+-------+
| District: West Tripura | State: Tripura |
+------------+-----------+--------------------------+----------+----------+-----+-------+
| | Area |
| Circle | Mouza | Name of Village | Dag No. | Hectare | Are | Square|
| | | | | | | Metre |
+============+===========+==========================+==========+==========+=====+=======+
| (1) | (2) | (3) | (4) | (5) | (6) | (7) |
+------------+-----------+--------------------------+----------+----------+-----+-------+
| Jirania | Shibnagar | Dinabandhu Nagar No. 10 | 2477 | 00 | 00 | 20 |
| | | | 2478 | 00 | 04 | 71 |
| | | | 2479 | 00 | 00 | 10 |
+------------+-----------+--------------------------+----------+----------+-----+-------+
[F. No. L-14014-150-2021-GP-II (E-40247)]
RAMJI LAL MEENA, Under Secy.