Full Text
REGD. No. D. L.-33004/99
The Gazette of India
CG-DL-E-06092025-265987
EXTRAORDINARY
PART III—Section 4
PUBLISHED BY AUTHORITY
No. 611]
NEW DELHI, THURSDAY, SEPTEMBER 4, 2025/BHADRA 13, 1947
RAIL VIKAS NIGAM LIMITED
NOTIFICATION
New Delhi, the 4th September, 2025
F. No.13 INDB-BNI/LA/Gazette/11/Work Correspondence date 03/09/2025.—In exercise of the powers
conferred by sub-section (1) of section 20A of the Railways Amendment Act, 2008 the Central Government,after
being satisfied that for the public purpose, the land, the brief description of which is given in the schedule annexed
hereto, is required for execution, maintenance, management and operation of Special Railway Project namely
"Indore-Budni New B.G. Railway Line" in the district Indore, Dewas and Sehore in the State of Madhya Pradesh,
hereby declares its intention to acquire such land.
Any person interested in the said land may, within 30 (thirty) days, from the date of publication of this
notification in the Official Gazette raise objection to the acquisition and use of such land for the aforesaid purpose
under sub-section (1) of section 20D of the said act;
Every such objection shall be made to the Competent Authority, namely, the Sub-Divisional Officer
(revenue) and Land Acquisition Officer Budni Madhya Pradesh, in writing and shall set out the grounds there of and
the Competent Authority shall give the objector an opportunity of being heard, either in person or by a legal
practitioner, and may after hearing all such objections and after making such further enquiry, if any, as the competent
authority thinks necessary, by order, either allow or disallow the objections.
Any order made by the competent authority under sub-section (2) of section 20D of the said act shall be final.
The land plans and other details of the land covered under this notification are available and can be inspected
by the interested person at the aforesaid office of the competent authority.
SCHEDULE
Brief Description of the land to be acquired, with or without structures falling within the Proposed Special
Railway Project "Indore-Budni section" District- Sehore in the state of Madhya Pradesh
+-----+-------------+------------+-----------+----------+-----------+-----------+----------+
| SI. | Name of the | Name of | Name of the | Survey | Type of | Nature of | Area (in |
| No. | District | the Tahsil | Village | Number | Land | Land | hectare) |
+-----+-------------+------------+-----------+----------+-----------+-----------+----------+
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
+-----+-------------+------------+-----------+----------+-----------+-----------+----------+
| 1 | Sehore | Budni | Pilikarar | 16/1/3/1 | Private | Irrigated | 0.012 |
| | | | | 16/5/3/1 | Private | Irrigated | 0.130 |
| | | | | 13/2/2/3/1 | Private | Irrigated | 0.052 |
| | | | | 13/2/3/3/1 | Private | Irrigated | 0.113 |
| | | | | 13/2/4/3/1 | Private | Irrigated | 0.115 |
| | | | | 13/2/5/3/1 | Private | Irrigated | 0.111 |
| | | | | 13/2/6/3/1 | Private | Irrigated | 0.051 |
| | | | | 13/3/3/1 | Private | Irrigated | 0.242 |
| | | | | 12/2/1/1 | Private | Irrigated | 0.038 |
| | | | | 12/2/2/1 | Private | Irrigated | 0.233 |
| | | | | 9/8/1/1 | Private | Irrigated | 0.043 |
| | | | | 5/3/1 | Govt | Forest | 1.492 |
| | | | | 2/3/1 | Govt | Forest | 0.016 |
| | | | | 10/1/1 | Govt | Charokhar | 0.099 |
| | | | | | | Nistar | |
| | | Rehti | Taalpura | 6/2/1 | Private | Irrigated | 0.397 |
| | | | Nayagaon | 108/2 | Private | Irrigated | 0.103 |
| | | | | 108/5 | Private | Irrigated | 0.493 |
| | | | Bayan | 441/329/2 | Private | Irrigated | 0.010 |
| | | | Mogra | 12/1 | Private | Irrigated | 0.00 |
| | | | Total | | | | 3.750 |
+-----+-------------+------------+-----------+----------+-----------+-----------+----------+
RAGHVENDRA SARASWAT, Chief Project Manager,
[ADVT.-III/4/Exty./344/2025-26]
Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064
and Published by the Controller of Publications, Delhi-110054. SARVESH KUMAR
SRIVASTAVA
16:49:04+0530