CENTRAL ELECTRICITY REGULATORY COMMISSION
NOTIFICATION
New Delhi, the 25th June, 2025
No. L-1/260/2021/CERC.βIn exercise of the powers conferred under Section 178 of the
Electricity Act, 2003 and all other powers enabling it in this behalf and after previous publication, the
Central Electricity Regulatory Commission, hereby makes the following regulations, to amend the
Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters)
Regulations, 2024 (hereinafter referred to as the "Principal Regulations") namely: -
1. Short Title And Comments
1.1
1.2
2.
2.1
These regulations may be called the Central Electricity Regulatory Commission (Deviation
Settlement Mechanism and Related Matters) (Second Amendment) Regulations, 2025.
These regulations shall come into force with effect from 01.07.2025.
Amendment Of Regulation 8 (Charges For Deviations) Of The PrincipalRegulations:
Clause (8) of Regulation 8 of the Principal Regulations shall be substituted as under:
"(8) Charges for injection of infirm power -
(1) The charges for injection of infirm power shall be zero, except in cases specified under
clauses (2) and (3) of this Regulation:
(2) In case of thermal generating stations, the infirm power injected into the grid from the
date of first synchronization of the unit up to the successful completion of the trial run
shall be paid @ Normal Rate of Charges for Deviations for each time block, subject to a
ceiling of 2.86/kWh.
(3) If infirm power is scheduled after a successful trial run as specified in the Grid Code,
the charges for deviation over the scheduled infirm power shall be as applicable for a
general seller or WS seller, as the case may be.
(4) Notwithstanding the provisions of clauses (2) and (3) of this Regulation, when the
system frequency, f> 50.05Hz, the charges for injection of infirm power or for deviation
of scheduled infirm power after the successful trial run by way of over injection by a
general seller or WS seller, as the case may be, shall be zero."
HARPREET SINGH PRUTHI, Secy.
[Advt.-III/4/Exty./206/2025-26]
Note:
(i)
(ii)
The Central Electricity Regulatory Commission (Deviation Settlement Mechanism and
Related Matters) Regulations, 2024 were published in Part III, Section 4, No. 642 of the
Gazette of India (Extraordinary) dated 21.08.2024.
The Central Electricity Regulatory Commission (Deviation Settlement Mechanism and
Related Matters) (First Amendment) Regulations, 2024 were published in Part III,
Section 4, No. 1030 of the Gazette of India (Extraordinary) dated 24.12.2024.