Ministry of Railways
Published with 5 days delay5d
Request for Publication of Extraordinary Gazette Notification Corrigendum for the below mentioned Land Schedule under Part II Section 3 Sub section ii as per the Railways Act 1989
The Central Government declares the acquisition of specified lands for the 'Talcher-Bimalagarh New B.G. Rail Link Project' under Section 20E of the Railway Act, 1989, vesting them absolutely in the Central Government.
Extract:
wise Abstract.
+----------+----------+----------------+
| SL NO. | VILLAGE | AREA (In Acre) |
+==========+==========+================+
| 1 | Jangada | 0.330 |
+----------+----------+----------------+
| 2 | Jayapura | 1.620 |
+----------+----------+----------------+
| Total | | 1.950 |
+----------+----------+----------------+
[F. No. CE/CON/II/BBS/TLHR-BUF/20E/2 village/Corrigendum]
H.ANANTHARAMAN, Chief Engineer...Manjari |
| | | | | | | | Pradhan D/O-Narattama Sahoo Caste- |
| | | | | | | | Chasa,Village-Badasada |
+----+------------+----------+--------------+-------------+--------------+------------+------------------------------------------+
| | Total | | | 1.020 | 0.330 | | |
+----+------------+----------+--------------+-------------+--------------+------------+------------------------------------------+
| 2 | Jayapura | 80/09 | 59/575 | 3.700 | 0.300 | Taila-1 | Jogeswar Naik S/O- Bandia Naik, Caste
Wednesday, June 03, 2026
Ministry of Railways
Request for Publication of Extraordinary Gazette Notification for the below mentioned Land Schedule under Part II Section 3 Sub section ii as per the Railways Act 1989
The Central Government declares the acquisition and vesting of specific lands in Angul District, Odisha, for the 'Talcher-Bimalagarh New B.G. Rail Link Project' under Section 20E of the Railway Act, 1989.
Extract:
Manjari Pradhan D/O-Narattama |
| | | | | | | | Sahoo Caste-Chasa, Village- |
| | | | | | | | Badasada |
+-----+-----------+-----------+-----------+-----------+------------+------------+-----------------------------------------------------------------+
| | Total | | | 1.020 | 0.330 | | |
+-----+-----------+-----------+-----------+-----------+------------+------------+-----------------------------------------------------------------+
| 2 | Jayapura | 80/09 | 59/575 | 3.700 | 0.300 | Taila-1 | Jogeswar Naik S/O- Bandia Naik, |
| | | | | | | | Caste...Pana, Village- Sushaba |
+-----+-----------+-----------+-----------+-----------+------------+------------+-----------------------------------------------------------------+
| 3 | Jayapura | 80/09 | 63/574 | 0.300 | 0.250 | Taila-1 | Jogeswar Naik S/O- Bandia Naik, |
| | | | | | | | Caste-Pana, Village- Sushaba |
+-----+-----------+-----------+-----------+-----------+------------+------------+-----------------------------------------------------------------+
| 4 | Jayapura | 80/66 | 553/667
Thursday, February 19, 2026
Ministry of Railways
Request for publication of Corrigendum to Gazette Notification
The Central Government declares its intention to acquire land for the public purpose of executing the Special Railway Project, namely, "Talcher-Bimalagarh New B.G. Rail Link Project", under sub-section (1) of section 20A of the Railways (Amendment) Act, 1989.
Extract:
Jangada | 3 | 2 | 1.020 | 0.330 | Sarad-1 | PVT. |
| | Total | | | 1.020 | 0.330 | | |
| 2 | Jayapura | 80/9 | 59/575 | 3.700 | 0.300 | Taila-1 | PVT. |
| 3 | Jayapura | 80/09 | 63/574...Taila-1 | PVT. |
| 4 | Jayapura | 80/66 | 553/667 | 1.800 | 0.620 | Taila-1 | PVT. |
| 5 | Jayapura | 80/95 | 61/573/697 | 0.200 | 0.200 | Taila-1 | PVT. |
| 6 | Jayapura | 80/95 | 59/575/698
Friday, January 30, 2026
Ministry of Railways
Request for Publication of Gazettee Notification for the below mentioned Land Schedule under Subsection 1 of section 20A of the Railways Amendment Act 1989
The Central Government declares its intention to acquire land for the "Talcher-Bimalagarh New B.G. Rail Link Project" under sub-section (1) of section 20A of the Railways (Amendment) Act, 1989.
Extract:
Jangada | 3 | 2 | 1.020 | 0.330 | Sarad-1 | PVT. |
+-----+-----------+----------+---------------+--------------+------------+------------+-----------+
| | Total | | | 1.020 | 0.330 | | |
+-----+-----------+----------+---------------+--------------+------------+------------+-----------+
| 2 | Jayapura | 80/9 | 59/575 | 3.700 | 0.300 | Taila-1 | PVT. |
+-----+-----------+----------+---------------+--------------+------------+------------+-----------+
| 3 | Jayapura | 80/09 | 63/574...Taila-1 | PVT. |
+-----+-----------+----------+---------------+--------------+------------+------------+-----------+
| 4 | Jayapura | 50/66 | 553/667 | 1.800 | 0.620 | Taila-1 | PVT. |
+-----+-----------+----------+---------------+--------------+------------+------------+-----------+
| 5 | Jayapura | 80/95 | 61/573/697 | 0.200 | 0.200 | Taila-1 | PVT. |
+-----+-----------+----------+---------------+--------------+------------+------------+-----------+
| 6 | Jayapura | 80/95 | 59/575/698